Issue Date |
Proceedings |
Nov. 09, 2007 |
Transmittal letter from Claudia Llado forwarding records to the agency.
|
Oct. 09, 2007 |
Transmittal letter from Claudia Llado forwarding records to the agency.
|
Jul. 25, 2007 |
Order Closing File. CASE CLOSED.
|
Jul. 24, 2007 |
Florida Power & Light Company`s Notice of Withdrawal of Site Certification Application for FPL Glades Power Project filed.
|
Jun. 19, 2007 |
Notice of Appearance (filed by E. Jacobs).
|
Jun. 15, 2007 |
Order Cancelling Hearing and Placing Case in Abeyance (parties to advise status by August 13, 2007).
|
Jun. 14, 2007 |
Florida Power and Light Company`s Motion to Suspend Site Certification Schedule filed.
|
Jun. 07, 2007 |
Order Granting Continuance and Re-scheduling Hearing (hearing set for September 11 and 12, 2007; 9:00 a.m.; Moore Haven, FL).
|
Jun. 05, 2007 |
FPL Glades Power Park Site Certification Application (Volume IV) filed.
|
Jun. 05, 2007 |
FPL Glades Power Park Site Certification Application (Volume III part II) filed.
|
Jun. 05, 2007 |
FPL Glades Power Park Site Certification Application (Volume III part I) filed.
|
Jun. 05, 2007 |
FPL Glades Power Park Site Certification Application (Volume II part II) filed.
|
Jun. 05, 2007 |
FPL Glades Power Park Site Certification Application (Volume II part 1) filed.
|
Jun. 05, 2007 |
FPL Glades Power Park Site Certification Application (Volume I part II) filed.
|
Jun. 05, 2007 |
FPL Glades Power Park Site Certification Application (Volume I part I) filed.
|
Jun. 05, 2007 |
Bobwhite-Manatee 230-KV Transmission Line Project; Application for Corridor Certification filed.
|
Jun. 05, 2007 |
CASE STATUS: Hearing Partially Held; continued to September 11, 9:00 a.m. |
Jun. 04, 2007 |
South Florida Water Management District`s Notice of Intenet to be a Party filed.
|
Jun. 04, 2007 |
South Florida Water Management District`s Notice of Substitution of Counsel filed.
|
Jun. 01, 2007 |
Order on Pending Motions.
|
May 31, 2007 |
Site Certification Application (3 Binders) filed.
|
May 31, 2007 |
Letter to Judge Johnston from D. Roberts enclosing copy of signature page to Prehearing Stipulation signed by S. Yu filed.
|
May 31, 2007 |
CASE STATUS: Motion Hearing Held. |
May 31, 2007 |
Supplemental Material to Joint Motion to Strike Portions of Petitions filed.
|
May 31, 2007 |
Notice of Filing Petitioners Signature Sheet to Pre-Trial Stipulation filed.
|
May 30, 2007 |
Notice of Publication of Notice of Land Use and Zoning Hearing for an Electrical Power Plant Site Certification to be Located in Glades and Hendr County, Florida: FPL Glades Power Park filed.
|
May 30, 2007 |
Prehearing Stipulation for Land Use and Zoning Hearing filed.
|
May 29, 2007 |
Letter to Judge Johnston from M. Learn requesting that the judge oppose FP&L proposal of a coal fired power plant filed.
|
May 29, 2007 |
Petitioner Conservancy of Southwest Florida`s Response to Joint Motion of Glades County, Department of Community Affairs and Florida Power & Light to Strike Portions of Petitions Disputing Glades County Land Use Determination etc... filed.
|
May 25, 2007 |
Notice of Appearance (J. Shore) filed.
|
May 24, 2007 |
Notice of Telephonic Motion Hearing (motion hearing set for May 31, 2007; 1:30 p.m.).
|
May 23, 2007 |
Petitioners` Response to Respondents` Joint Motion to Strike Portions of Petitions and Motion for Protective Order to Preclude Discovery on Those Matters filed.
|
May 23, 2007 |
Department of Community Affairs` Notice of Filing Responses to Petitioner`s First Request for Production of Documents and First Set of Interrogatories filed.
|
May 23, 2007 |
Petitioners` Notice of Taking Deposition Duces Tecum filed.
|
May 22, 2007 |
Glades County`s Notice of Service of Answers and Objections to Petitioners` First Set of Interrogatories filed.
|
May 22, 2007 |
Order Granting Leave to Intervene (Southern Alliance for Clean Energy).
|
May 22, 2007 |
Florida Power and Light Company`s Notice of Filing Responses to Florida Wildlife Federation, ET AL.S` First Set of Interrogatories and First Request for Production of Documents filed.
|
May 22, 2007 |
Notice of Service of Petitioners` Answers to Florida Power and Lights First Set of Interrogatories Regarding Land Use Plans and Zoning filed.
|
May 21, 2007 |
Petitioners` Motion for Leave to Amend Petition filed.
|
May 21, 2007 |
Southern Alliance for Clean Energy`s Petition to Intervene filed.
|
May 17, 2007 |
Florida Power & Light Company`s Response and Objection in Part to Petitioners` Motion for Leave to Amend Petition filed.
|
May 16, 2007 |
Joint Motion of Glades County, Department of Community Affairs and Florida Power and Light Co. to Strike Portions of Petitions Disputing Glades County`s Land use Determination Filed by Florida Wildlife Federation, Inc.,ET AL. and Conservancy,etc. filed.
|
May 16, 2007 |
Order Accepting Qualified Representative.
|
May 15, 2007 |
Amended Notice of Taking Deposition Duces Tecum for Location Purposes only filed.
|
May 15, 2007 |
Notice of Appearance (filed by R. Grosso).
|
May 15, 2007 |
Notice of Appearance (filed by R. Hartsell).
|
May 14, 2007 |
Petitioners` Notice of Taking Depositions Duces Tecum of Larry Hilton, Wendell Taylor, and K.S. "Butch" Jones filed.
|
May 14, 2007 |
Petitioners` Amended Notice of Taking Depositions Duces Tecum of Grover Whidden and Richard Zwolak (amended as to Date and Time) filed.
|
May 14, 2007 |
Petitioners` Notice of Taking Deposition Duces Tecum of Mark Morton filed.
|
May 11, 2007 |
Notice of Taking Deposition Duces Tecum filed.
|
May 11, 2007 |
Petitioners` Motion for Leave to Amend Petition filed.
|
May 10, 2007 |
Petitioners` Notice of Taking Depositions Duces Tecum of Grover Whidden and Richard Zwolak filed.
|
May 10, 2007 |
Notice of Appearance (filed by K. Oertel).
|
May 09, 2007 |
Petitioners, Florida Wildlife Federation, et al.`s Notice of Filing Amended Potential Witness List filed
|
May 04, 2007 |
Petitioner Conservancy of Southwest Florida`s Potential Witness Disclosure filed.
|
May 03, 2007 |
Petitioners, Florida Wildlife Federation, et al.`s Notice of Filing Potential Witness List filed.
|
May 02, 2007 |
Notice of Land Use and Zoning Hearing for an Electrical Power Plant to be Located in Glades County, Florida: FPL Glades Power Park filed.
|
May 02, 2007 |
Notice of Publication of Notice of Receipt of Hendry County`s Determination of Land Use and Zoning Consistency for Electrical Power Plant to be Located in Hendry County, Florida: FPL Glades Power Park filed.
|
May 02, 2007 |
Notice of Rescheduling of Land Use and Zoning Hearing for an Electrical Power Plant to be Located in Glades County, FLorida: FPL Glades Power Park filed.
|
May 02, 2007 |
Glades County List of Witnesses for Hearing on Glades County Land Use Determination filed.
|
May 02, 2007 |
FPL Witness List for Glades County Land Use Hearing filed.
|
May 01, 2007 |
Department of Community Affairs` Witness List filed.
|
May 01, 2007 |
Request for Naming of Qualified Representatives (J. Spalding and K. Henry) filed.
|
Apr. 24, 2007 |
Notice of Service of Petitioners` First Set of Interrogatories Regarding Land Use Plans and Zoning on Glades County filed.
|
Apr. 24, 2007 |
Petitioners` First Request for Production of Documents to the Florida Department of Community Affairs filed.
|
Apr. 24, 2007 |
Notice of Service of Petitioners` First Set of Interrogatories Regarding Land Use Plans and Zoning on Florida Power and Light filed.
|
Apr. 24, 2007 |
Petitioner`s First Request for Production of Documents to Florida Power and Light filed.
|
Apr. 23, 2007 |
Corrected Notice of Service of Florida Power & Light Company`s First Set of Intrerrogatories Regarding Land Use Plans and Zoning to Petitioner`s Slorida Wildlife Federation, Inc., Save our Creeks, Inc., etc., filed.
|
Apr. 20, 2007 |
Notice of Service of Florida Power and Light Company`s First Set of Interrogatories Regarding Land Use and Zoning to Petitioner the Conservancy of Southwest Florida filed.
|
Apr. 20, 2007 |
Notice of Service of Florida Power and Light Company`s First Set of Interrogatories Regarding Land Use Plans and Zoning to Petitioners, etc., filed.
|
Apr. 12, 2007 |
Order Granting Leave to Intervene.
|
Apr. 11, 2007 |
Sierra Club, Florida Chapter`s Petition to Intervene filed.
|
Mar. 26, 2007 |
Department of Environmental Protection`s Determination of Completeness filed.
|
Mar. 21, 2007 |
Order of Pre-hearing Instructions.
|
Mar. 21, 2007 |
Order Granting Continuance and Re-scheduling Hearing (hearing set for June 5 through 7, 2007; 1:00 p.m.; Moore Haven, FL).
|
Mar. 21, 2007 |
Notice of Substitution of Counsel (filed by P. Comer).
|
Mar. 20, 2007 |
Letter to Judge Johnston from P. Cunningham regarding Motion for Continuance and Rescheduling of Land Use Hearing filed.
|
Mar. 16, 2007 |
Motion for Continuance and Rescheduling of Land Use Hearing filed.
|
Mar. 12, 2007 |
Hendry County`s Land Use Consistency Determination filed.
|
Mar. 12, 2007 |
Hendry County`s Notice of Intent to be a Party filed.
|
Mar. 09, 2007 |
Notice of Publication of Notice of Receipt of Glades County`s Determination of Land Use and Zoning Consistency for Electrical Power Plant to be Located in Glades and Hendry County, Florida: FPL Glades Power Park filed.
|
Mar. 09, 2007 |
Notice of Publication of Notice of Filing Application for Electrical Power Plant Site Certification to be Located in Glades and Hendry County, Florida: FPL Glades Power Park filed.
|
Mar. 06, 2007 |
Amended Notice of Hearing (hearing set for March 26 through 28, 2007; 1:00 p.m.; Moore Haven, FL; amended as to statement of the issues, dates, and time).
|
Mar. 06, 2007 |
Glades County`s Notice of Intent to be a Party filed.
|
Mar. 06, 2007 |
Notice of Intent to be a Party to the Siting Hearing filed.
|
Mar. 05, 2007 |
Department of Environmental Protection`s Second Notice of Receipt of Petition on Land Use Determination filed.
|
Mar. 02, 2007 |
Florida Power and Light Company`s Notice of Filing Responses to the Department of Environmental Protection`s Determination of Incompleteness filed.
|
Mar. 02, 2007 |
Land Use Hearing (hearing set for March 26 and 27, 2007; 9:00 a.m.; Moore Haven, FL).
|
Mar. 02, 2007 |
Department of Environmental Protection`s Notice of Reciept of Petition on Land Use Determination and Request for Hearing filed.
|
Feb. 23, 2007 |
Petition Disputing Glades County`s Determination that FPL`s Proposed Siting of a 1980 Megawatt Coal Fired Power Plant on 5000 Acres of Lands Designated for Agricultural/Open Uses is in Compliance with Existing Local Land Use Plans and Zoning Ordinances filed.
|
Feb. 12, 2007 |
Notice of Meeting filed (February 20, 2007, at 6:00 p.m., in Moore Haven, Florida).
|
Feb. 12, 2007 |
Notice of Appearance (filed by E. Swenson).
|
Feb. 01, 2007 |
Order Altering Time Limits.
|
Jan. 31, 2007 |
Department of Environmental Protection`s Determination of Incompleteness filed.
|
Jan. 23, 2007 |
Order of Pre-hearing Instructions.
|
Jan. 23, 2007 |
Notice of (Certification) Hearing (hearing set for September 11 through 14, 18 through 21, 25 through 28 and October 2 through 5, 2007; 9:00 a.m.; Moore Haven, FL).
|
Jan. 22, 2007 |
Statement of Facts and Determination of Compliance with Local Land use Plans and Zoning filed.
|
Jan. 19, 2007 |
South Florida Water Management District`s Motion for Alteration of Time Limits filed.
|
Jan. 19, 2007 |
Department of Transportation`s Notice of Intent to be a Party filed.
|
Jan. 17, 2007 |
Statement of Facts and Determination of Compliance with Local Land Use Plans and Zoning filed.
|
Jan. 10, 2007 |
Conservationist Parties` Response to the Initial Order filed.
|
Jan. 10, 2007 |
Department of Community Affairs` Notice of Intent to be a Party filed.
|
Jan. 10, 2007 |
Response to the Initial Order filed.
|
Jan. 08, 2007 |
Notice of Appearance (filed by D. Guest).
|
Jan. 08, 2007 |
Conservationist Parties` Motion to Reopen Time for Submitting Comments on Venue and Timeframes filed.
|
Jan. 08, 2007 |
Conservationist Organizations` Notice of Intent to Participate as Parties filed.
|
Jan. 05, 2007 |
Site Certification Application (Volume IV) filed.
|
Jan. 05, 2007 |
Department of Environmental Protection`s Notice of Filing of Site Certification Application filed.
|
Dec. 29, 2006 |
Department of Environmental Protection`s Statement of Additional Agencies Entitled to Copies of the Application and Amendments filed.
|
Dec. 29, 2006 |
Department of Environmental Protection`s Proposed Site Certification Application Schedule and Joint Motion and Stipultion for Alteration of Time Limits filed.
|
Dec. 29, 2006 |
Department of Environmental Protection`s Notice of Receipt of Power Plant Siting Application and Request for Assignment of Administrative Law Judge filed.
|
Dec. 29, 2006 |
Initial Order.
|