GoPro, Inc. v. C&A Marketing, Inc., 3:16-cv-03590-JST. (2017)

Court: District Court, N.D. California Number: infdco20170310a47 Visitors: 13
Filed: Mar. 09, 2017
Latest Update: Mar. 09, 2017
Summary: STIPULATION AND [PROPOSED] ORDER TO EXTEND TIME TO SERVE DAMAGES CONTENTIONS AND RESPONSIVE DAMAGES CONTENTIONS JON S. TIGAR , District Judge . Pursuant to Local Rule 6-1(b), Plaintiff GoPro, Inc. ("GoPro") and Defendants C&A Marketing, Inc.; C&A Licensing, LLC; and PLR IP Holdings, LLC ("Defendants") hereby stipulate as follows: WHEREAS, the Northern District of California revised its Patent Local Rules on January 17, 2017; WHEREAS, these revised Patent Local Rules now require the
More

STIPULATION AND [PROPOSED] ORDER TO EXTEND TIME TO SERVE DAMAGES CONTENTIONS AND RESPONSIVE DAMAGES CONTENTIONS

Pursuant to Local Rule 6-1(b), Plaintiff GoPro, Inc. ("GoPro") and Defendants C&A Marketing, Inc.; C&A Licensing, LLC; and PLR IP Holdings, LLC ("Defendants") hereby stipulate as follows:

WHEREAS, the Northern District of California revised its Patent Local Rules on January 17, 2017;

WHEREAS, these revised Patent Local Rules now require the exchange of Damages Contentions and Responsive Damages Contentions under Patent Local Rule ("Patent L.R.") 3-8 and 3-9, respectively;

WHEREAS, Patent L.R. 3-8 and 3-9 contemplate the prior identification of information and production of documents relating to damages under Patent L.R. 3-1(h), 3-2(f)-(j), and 3-4(c)-(e);

WHEREAS, GoPro previously served Infringement Contentions under Patent L.R. 3-1, and the parties produced documents pursuant to Patent L.R. 3-2 and 3-4 prior to the revision of the Patent Local Rules;

WHEREAS, the parties' compliance with these new Patent Local Rules relating to damages would assist their completion of Damages Contentions and Responsive Damages Contentions;

IT IS HEREBY STIPULATED AND AGREED that on April 5, 2017, GoPro will serve amended Infringement Contentions, amended only to "[i]dentify the timing of the point of first infringement, the start of claimed damages, and the end of claimed damages," pursuant to Patent L.R. 3-1(h);

IT IS FURTHER STIPULATED AND AGREED that on April 5, 2017, the parties will produce documents responsive to Patent L.R. 3-2(f)-(j) and 3-4(c)-(e) and in compliance with Patent L.R. 3-2 and 3-4;

IT IS FURTHER STIPULATED AND AGREED that GoPro will serve its Patent L.R. 3-8 Damages Contentions on May 25, 2017 (50 days after service of its amended Infringement Contentions);

IT IS FURTHER STIPULATED AND AGREED that Defendants will serve their Patent L.R. 3-9 Responsive Damages Contentions on June 26, 2017 (30 days after service of the Damages Contentions).

The parties previously stipulated to extend time to respond to the Complaint, to continue the initial case management conference, and to serve invalidity contentions and exchange preliminary claim constructions. This extension will not otherwise affect the schedule for the case.

PURSUANT TO STIPULATION, IT IS SO ORDERED.