IN RE: FLORIDA POWER AND LIGHT COMPANY PORT EVERGLADES ENERGY CENTER vs *, 12-000422EPP (2012)

Court: Division of Administrative Hearings, Florida Number: 12-000422EPP Visitors: 25
Petitioner: IN RE: FLORIDA POWER AND LIGHT COMPANY PORT EVERGLADES ENERGY CENTER
Respondent: *
Judges: LAWRENCE P. STEVENSON
Agency: Department of Environmental Protection
Locations: Hollywood, Florida
Filed: Jan. 27, 2012
Status: Closed
Settled and/or Dismissed prior to entry of RO/FO on Monday, September 24, 2012.

Latest Update: Dec. 22, 2024

Docket for Case No: 12-000422EPP
Issue Date Proceedings
Sep. 25, 2012 Transmittal letter from Claudia Llado forwarding the three-volume Port Everglades Next Generation Clean Energy Center Site Certification Application, to the agency.
Sep. 24, 2012 Order Closing File and Relinquishing Jurisdiction. CASE CLOSED.
Sep. 19, 2012 Joint Stipulation and Motion of the Parties to Cancel Certification Hearing and to Relinquish Jurisdiction to the Department of Environmental Protection for Entry of Final Certification Order filed.
Sep. 18, 2012 Notice of Substitution of Counsel (Anthony Pinzino) filed.
Sep. 18, 2012 Notice of Appearance (Anthony Pinzino) filed.
Sep. 04, 2012 Notice of Filing Project Analysis Report filed.
Aug. 16, 2012 Order of Pre-hearing Instructions.
Jul. 27, 2012 Notice of Hearing (hearing set for October 15 through 17, 2012; 9:00 a.m.; Hollywood, FL).
Jul. 16, 2012 Broward County's Supplemental Notice of Intent to be a Party filed.
Jul. 09, 2012 Notice of Intent to be a Party filed.
Apr. 26, 2012 Department of Environmental Protection's Determination that Application is Complete filed.
Apr. 09, 2012 South Florida Water Management District's Notice of Intent to be a Party filed.
Apr. 09, 2012 Broward County's Notice of Intent to be a Party filed.
Apr. 05, 2012 Notice of Submittal of Responses to Agency Completeness Questions and Comments filed.
Mar. 09, 2012 FPL's Statement in Response to Determination of Incompleteness filed.
Mar. 05, 2012 Department of Environmental Protection?s Determination that Application is Incomplete filed.
Feb. 07, 2012 Response to Initial Order filed.
Feb. 06, 2012 Order Establishing Schedule.
Jan. 31, 2012 Initial Order.
Jan. 31, 2012 Corrected Proposed Initial Schedule filed.
Jan. 30, 2012 Proposed Initial Schedule filed.
Jan. 27, 2012 Port Everglades Next Generation Clean Energy Center Site Certification Application, Volume I through III, filed.
Jan. 27, 2012 Department of Environmental Protection's Request for Assignment of Administrative Law Judge filed.
Jan. 27, 2012 Statement of Additional Agencies Entitled to Copies of the Application and Amendments filed.
Jan. 27, 2012 Notice of Filing Application for Power Plant Certification filed.
Source:  Florida - Division of Administrative Hearings

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer