Summary: ORDER J. RANDALL HALL , District Judge . On May 9, 2016, the Court extended discovery in this case until August 8, 2016. (Doc. 38.) Dispositive motions therefore were due on September 7, 2016. Nevertheless, Defendants filed a motion for summary judgment on May 3, 2017. (Doc. 42.) Because Defendants' motion is more than 200 days late, it is DENIED.
ORDER
J. RANDALL HALL, District Judge.
On May 9, 2016, the Court extended discovery in this case until August 8, 2016. (Doc. 38.) Dispositive motions therefore were due on September 7, 2016. Nevertheless, Defendants filed a motion for summary judgment on May 3, 2017. (Doc. 42.) Because Defendants' motion is more than 200 days late, it is DENIED.