Summary: IN THE DISTRICT COURT OF APPEAL FIRST DISTRICT, STATE OF FLORIDA HAINES O’NEIL, individually NOT FINAL UNTIL TIME EXPIRES TO and O’NEIL FILE MOTION FOR REHEARING AND TRANSPORTATION DISPOSITION THEREOF IF FILED SERVICES, INC., CASE NO. 1D13-4545 Appellant, v. WALTON COUNTY, A POLITICAL SUBDIVISION OF THE STATE OF FLORIDA, EBSCO GULF COAST DEVELOPMENT, INC., A FLORIDA FOR-PROFIT CORPORATION, and A.E. FOSTER, JR., INDIVIDUALLY, Appellee. _/ Opinion filed September 16, 2014. An appeal from the Circu
More
                                    IN THE DISTRICT COURT OF APPEAL
                                    FIRST DISTRICT, STATE OF FLORIDA

HAINES O’NEIL, individually         NOT FINAL UNTIL TIME EXPIRES TO
and O’NEIL                          FILE MOTION FOR REHEARING AND
TRANSPORTATION                      DISPOSITION THEREOF IF FILED
SERVICES, INC.,
                                    CASE NO. 1D13-4545
      Appellant,

v.

WALTON COUNTY, A
POLITICAL SUBDIVISION OF
THE STATE OF FLORIDA,
EBSCO GULF COAST
DEVELOPMENT, INC., A
FLORIDA FOR-PROFIT
CORPORATION, and A.E.
FOSTER, JR., INDIVIDUALLY,

     Appellee.
_____________________________/

Opinion filed September 16, 2014.

An appeal from the Circuit Court for Walton County.
Kelvin C. Wells, Judge.

Stephen A. Ecenia and Marsha E. Rule of Rutledge, Ecenia & Purnell, and Thomas
G. Tomasello, Tallahassee for Appellant.

W. Douglas Hall and Christine Davis Graves of Carlton Fields, P.A., Tallahassee,
and Mark D. Davis of Andrews & Davis, Defuniak Springs, and Gary A. Vorbeck
of Theriaque Vorbeck & Spain, Destin for Appellee.
OSTERHAUS, J.

      Appellants have challenged an order approving a 20-unit planned unit

development (PUD) immediately seaward of their beach-view property at Inlet

Beach in Walton County. Citing § 163.3215, Florida Statutes (2013), they assert

that the order conflicts with Walton County’s comprehensive plan (Comp Plan) by

approving new lots seaward of the coastal construction control line (CCCL);

approving other construction (dwellings, roads, grading, drainage, etc.) on the

primary dune within the Coastal Protection Zone (CPZ); and mis-locating the CPZ.

Appellees moved for summary judgment, which the circuit court granted.

      We now affirm because the 2013 order being challenged here did not

materially alter the development, CCCL, or CPZ. Rather, an earlier development

order from 2010, had already approved the developer’s first-step PUD application,

including its site plan and the location of development relative to the CCCL and

CPZ. The Board of County Commissioners (“County”) further found this earlier

application “in compliance and consistent with” the Comp Plan. And nobody

challenged it. See § 163.3215(3), Fla. Stat. (requiring consistency challenges to be

filed “no later than 30 days following rendition”). Instead, Appellants filed this

action after the County approved the follow-up, detailed plan in 2013. But because

§ 163.3215 is predicated upon showing a material alteration of property

inconsistent with a Comp Plan, and here the County’s 2010 order had already
                                         2
approved the placement and relative location of the things that Appellants

challenge, this challenge to the 2013 order fails to meet the requirements of

§ 163.3215.

                                         I.

      A. The Two Development Orders

      In 2009, Appellees EBSCO Gulf Coast Development, Inc., and A.E. Foster,

Jr., (collectively, “Developer”) set out to develop a 20-unit coastal residential

community on Inlet Beach in Walton County. Walton County’s Land Development

Code sets forth a two-step approval process for PUD projects: a concept plan phase

and a detailed plan phase. Walton Cnty. Land Dev. Code § 2.06.02 (hereinafter

“LDC”).

      At the first step, the County specifically reviews a concept plan “for

compliance with the goals, objectives and policies of the comprehensive plan and

compatibility with the character of the surrounding area.” 
Id. A report
is then made

publically available at least one week in advance of a public hearing held by the

Planning Commission. After the hearing, the Board of County Commissioners

holds another public hearing in order to approve or deny the concept plan, or to

approve it with conditions. 
Id. At the
second step, “an applicant has the option to

submit a Detailed PUD Plan for all or part of the development approved in the

conceptual plan approval.” LDC § 2.06.02(B). If technical requirements are met,

                                         3
the Board issues another final order memorializing its approval of the detailed

plan. LDC §§ 2.06.02(B), 10.02.01, 10.02.03.

      In this case, Developer submitted a “Concept Plan” with maps showing all

twenty new parcels on the site plan, proposed dwellings, roads, driveways,

landscape buffers, the CCCL, and the CPZ. After the requisite notice and a

hearing, the Board of County Commissioners approved the Concept Plan, finding it

to be “in compliance and consistent with both the [Comp Plan] and the LDC.” The

County’s approval came with certain conditions, including requiring Developer to

construct a turnaround and parking spaces, pay for construction of a public

boardwalk, and re-pave a road after completing the dune enhancement project

called for by the Concept Plan. 1 The County recorded the final order approving the

Concept Plan on March 16, 2010.

      In 2012, Developer followed-up by submitting a “Detailed Plan” that was

also approved by the County. The 2013 Order approving the Detailed Plan noted

that it had “previously approved . . . and rendered a Final Order for the Lupin

Beach Conceptual PUD Plan on March 16, 2010, which is hereby incorporated by

reference.” Nothing in the Detailed Plan or 2013 Order indicated that the location

of development relative to the CCCL, CPZ, or primary dune had been materially

1
  The affidavit of Appellee Mr. Foster, Vice President of Appellee EBSCO Gulf
Coast Development, Inc., stated that after the 2010 Order was entered EBSCO
spent about $200,000 to fund construction of the boardwalk and about $500,000 to
construct the dune enhancement project, as contemplated by the order.
                                        4
altered. Rather, each remained in the same place in relation to the other, as had

been approved by the 2010 Order—lots remained seaward of the CCCL and the

CPZ’s upland boundary line (as marked by the primary dune) remained seaward of

the proposed construction of dwellings, roads, driveways, and other infrastructure.

        B. The Litigation

        After the Detailed Plan was approved in 2013, Appellants challenged the

PUD under § 163.3215.2 The Complaint alleged that the 2013 Order conflicted

with three of the Comp Plan’s environmental protection provisions:

        [1.] Defendants propose to destroy significant primary dunes
        through grading, the construction of 20 dwelling units, the
        construction of access roads and utility corridors in the primary dunes,
        and the construction of a 610 foot long retaining wall and extensive
        associated excavation, grading, and associated infrastructure within
        the Lupin Beach PUD. The existing dune contours will be extensively
        altered and will be reduced by as much as 16 feet. *        *     *

        [2.] The Project violates the [Comp] Plan and LDC because a
        portion of the proposed development is located within the coastal
        protection zone, whereas specific provisions of the Comp Plan and
        LDC] prohibit construction of dwellings within the [CPZ]. . . . The
        CPZ, if properly located, would allow only very limited development
        on the lots proposed to be created . . . and [preclude] the proposed

2
    Section 163.3215(3) specifically provides:

        Any aggrieved or adversely affected party may maintain a de novo
        action . . . against any local government to challenge any decision
        [granting] an application for . . . a development order, as defined in s.
        163.3164, which materially alters the use or density or intensity of use
        on a particular piece of property which is not consistent with the
        comprehensive plan.

                                           5
        development in that area contrary to what is permitted by the
        Development Order.    *    *      *

        [3.] According to the approved site plan, . . . new parcels [will] be
        created entirely seaward of the CCCL on which dwellings are
        proposed. . . . The [lots] are being created in violation of the [Comp
        Plan’s] prohibition against creating new parcels entirely seaward of
        the CCCL. 3

(Emphasis added).

        Developer moved for summary judgment. 4 It argued that Appellants could

not attack matters addressed by the 2010 Order by challenging the 2013 Order. In

Developer’s view, the 2013 Order approving the Detailed Plan merely

implemented development rights that had already been granted. After a hearing,

the trial court entered summary judgment for Appellees, concluding that the 2013

Order did not materially alter the property as required to bring a § 163.3215-based

challenge. Appellant then filed a timely appeal.

                                         II.

        A trial court may grant a motion for summary judgment only if there is no

genuine issue of material fact and if the moving party is entitled to a judgment as a

matter of law. See Fla. R. Civ. P. 1.510(c). “Once the moving party establishes that

there are no genuine issues of material fact, the burden shifts to the nonmoving

party to show the existence of a disputed issue of fact.” Master Tech Satellite, Inc.
3
  A fourth allegation stated in the Complaint that is not at issue in this appeal
involved the PUD’s alleged non-compliance with FEMA floodplain limits.
4
    Appellee Walton County adopted Developer’s motion.
                                       6
v. Mastec N. Am., Inc., 
49 So. 3d 789
, 790 (Fla. 3d DCA 2010). The trial court

must view the evidence and draw all inferences in favor of the opposing party.

Castle Key Ins. Co. v. Raymond H. Duke Enterprises, Inc., 
135 So. 3d 578
, 579

(Fla. 1st DCA 2014). But a party cannot create disputed issues of fact “by merely

stating factual conclusions.” Master Tech Satellite, 
Inc., 49 So. 3d at 790
.

                                         A.

      Appellants claim that the 2013 Order materially altered the Lupin Beach

property inconsistent with Comp Plan in three ways: (1) locating lots seaward of

the CCCL; (2) allowing development on the primary dune; and (3) incorrectly

locating the CPZ and allowing development therein. See Compl. ¶ 24. But the

2013 Order didn’t materially alter the property in these ways; and, if any order did,

it was the 2010 Order.

      1.   The 2013 Order didn’t “alter” the property by locating parcels seaward
           of the CCCL.

      Appellants argue first that the 2013 Order altered the property by approving

new lots seaward of the CCCL contrary to the Comp Plan. See Comp Plan Policy

C-1.6.2.5 But maps submitted with Developer’s Concept Plan approved in 2010

designated all twenty parcels upon which new dwellings were planned, including

those alleged by Appellants to be located entirely seaward of the CCCL. Because

5
  Policy C-1.6.2 provides: “The County shall issue no development order or permit
for construction on a new parcel . . . if such new parcel lies entirely seaward of the
Coastal Construction Control Line.”
                                            7
these parcels were sited in the same location relative to the CCCL as addressed in

Developer’s County-approved and recorded 2010 application, the 2013 Order

cannot be considered to have “altered” the property per § 163.3215(3). Walton

County’s Land Development Code provides that consistency challenges may be

asserted as to matters “not specifically addressed” by a concept plan. See LDC §

2.06.02(A). And here the Concept Plan specifically addressed the location of

development relative to the CCCL.

      Moreover, at this point, it is well beyond the 30-day statutory deadline for

challenging the 2010 Order, a jurisdictional impediment for the court to consider

changes wrought by the 2010 Order. § 163.3215(3), Fla. Stat.; see also Presidents’

Council of SD, Inc. v. Walton County, 
36 So. 3d 764
, 765 (Fla. 1st DCA 2010).

We therefore affirm the summary judgment order entered by the circuit court on

the CCCL-related issue.

      2.   The 2013 Order didn’t “alter” the property by authorizing residential
           construction on the primary dune in the CPZ.

      For the same basic reason, the court appropriately entered summary

judgment on Appellants’ claims related to the destruction of the primary dune and

the location of the CPZ.

      As a preliminary matter, Appellants are correct that Walton County’s Comp

Plan severely limits almost all development on the primary dune within a CPZ. It

permits only “boardwalks, shoreline access structures, and erosion control
                                        8
measures that will enhance and protect the dune system” to be built in this area.

Comp Plan Policy C-1.6.1(2). But, as with the issue above, the 2010 Order—not

the 2013 Order—specifically addressed the location of the primary dune and CPZ

relative to the residential development. If the PUD materially altered the primary

dune and CPZ on the property for purposes of § 163.3215, then the alteration

occurred with the 2010 Order.

      The Complaint’s assumption about where the primary dune and CPZ were

located circa 2013 is wrong. Appellants asserted that the primary dune (and hence

the CPZ6) was located “immediately to the south of Plaintiff’s residence,” at a

place where construction was to occur on two lots identified by the PUD

application. But the CPZ was mapped in a different place in Developer’s Concept

Plan application that the County approved and recorded in 2010. In fact,

Developer’s Concept Plan included maps showing all twenty proposed residential

units with corresponding roadways and driveways, the beach, the dune, a proposed

landscape buffer, the properties of upland owners (including Appellants’ property),

the site’s topography, the CCCL, the CPZ, and the contours of a plan-proposed

dune enhancement project vis-a-vis the existing grade. The “CPZ Map” included in


6
  The CPZ is defined by reference to the primary dune. See Comp Plan Policy C-
1.6.1 (defining the CPZ as “extend[ing] seaward of the landward toe of the primary
dune ridge or, where the toe cannot be determined, 50 feet landward of the crest of
the primary dune or 25 feet landward of the top of the higher bluff regions where
no primary dune exists.” Here, the parties do not argue that no primary dune exists.
                                         9
the Concept Plan application specifically marked the “Coastal Protection Zoneline”

as being seaward of where Appellants allege and seaward of the construction that

Appellants allege to be on the primary dune. 7 And in the Detailed Plan, the CPZ

and primary dune remained seaward of the upland construction.

      In sum, Appellants cannot prevail with arguments that the 2013 Order

materially altered the property by allowing development within the CPZ, or on the

primary dune, because the Concept Plan in 2010 had already established the

relative location of the CPZ (and primary dune) elsewhere, in a place separate from

the upland development. As discussed earlier, to the extent that Appellants dispute

the 2010 placement of these things, they are too late. See § 163.3215(3), Fla. Stat.;

LDC § 2.06.02(A) (only matters “not specifically addressed” in a concept plan are

subject to Comp Plan consistency challenges).8

      3. No genuine issue of material fact remains.

      Appellants submitted two affidavits from individuals familiar with coastal

projects in response to the motion for summary judgment. But neither creates

7
  Appellants argue that the CPZ Map only shows an upland “Coastal Protection
Zoneline,” but not a “Zone” and thus actually failed to identify the CPZ. But this
argument is silly. Once the upland CPZ boundary is established on a map, the
zone’s location is obvious; by definition, it extends seaward to the water.
8
 Appellants’ other CPZ-related allegations related to the destruction of the primary
dune—regarding removal of vegetation, stormwater management, grading,
drainage, and the construction of a retaining wall—also fail because they hinge on
Appellants’ incorrect assumption that the CPZ lies farther inland of where it was
approved in 2010.
                                         10
genuine fact issues as to Appellants’ three claims. The affidavits identify many

details of the project not contained in the Concept Plan approved in 2010, such as

the materials and building processes to be used in completing the construction of

the dwellings, roads, driveways, and other adjacent infrastructure, and where

precise boundaries within the development would fall. But these details don’t bear

on the particular issues framed by Appellants’ Complaint that more narrowly

involve the location of development relative to the CCCL and CPZ/primary dune.

Again, Appellants’ Complaint “[s]pecifically . . . contend[ed] that the Project

violates [Comp Plan] provisions related to protection of the primary dune . . ., the

location of individual lots in relation of the CCCL, and the method by which the

location of the CPZ was determined.” Compl. ¶ 24. These three allegations relate

to the location of the CCCL and CPZ vis-à-vis the residential construction, but not

to the many details of upland construction that may (or may not) have altered the

property’s use or intensity of use in other ways. 9 In sum, the affidavits don’t raise

questions of material fact related to the discrete issues raised by Appellants’

Complaint, even if they might support a different set of consistency claims.




9
  For example, Appellants cite the construction of a retaining wall upland of the
proposed dwellings, which was not addressed in the Concept Plan, as having raised
a legitimate use, density, or intensity of use claim under the statute. But this is a
different issue than alleged in the Complaint, which framed this litigation in terms
of the impact of residential construction on the CCCL, CPZ, and primary dune.
                                          11
                                        B.

      Finally, we reject Appellants’ contention that the 2013 Order presented the

first opportunity to challenge the County’s approvals because the 2010 Order

wasn’t a “development order.” Section 163.3215(3) only authorizes challenges to

local decisions involving applications for “a development order, as defined in

§ 163.3164.” Under § 163.3164(15), “development order” refers to “any order

granting, denying, or granting with conditions an application for a development

permit.” (Emphasis added). The term has been broadly construed. See Graves v.

City of Pompano Beach ex rel. City Com’n, 
74 So. 3d 595
(Fla. 4th DCA 2011);

Arbor Properties, Inc. v. Lake Jackson Prot. Alliance, Inc., 
51 So. 3d 502
(Fla. 1st

DCA 2010). The definition of “development permit” includes “any other official

action of local government having the effect of permitting the development of

land.” § 163.3164(16), Fla. Stat. (emphasis added). As recognized by the Fourth

District in 
Graves, 74 So. 3d at 598
, “development” is broadly construed and

includes “any building activity” (§§ 163.3164(14), 380.04(1)), or “change in the

intensity of use of land, such as an increase in the number of dwelling units in a

structure or on land or a material increase in the number of businesses,

manufacturing establishments, offices, or dwelling units in a structure or on land.”

§ 380.04(2)(b).




                                        12
      It follows here that the 2010 Order was a challengeable “development

order,” because it approved and recorded the Developer’s plan to subdivide the

property into many new parcels and build new dwellings, roads, driveways, and

other infrastructure. That the 2010 Order included conditions,10 or that Developer

submitted follow-up detailed construction plans, did not alter the 2010 Order’s

quality as a “development order.” See, e.g., Arbor Properties, 
Inc., 51 So. 3d at 503
(treating an order approving a concept plan with conditions as a development

order). Rather, both the 2010 and 2013 Orders were susceptible to de novo

challenge under § 163.3215. But Appellants’ challenge to the 2013 Order could

only be successful insofar as it identified material alterations to the property not

already addressed by the Concept Plan approved in 2010. See LDC § 2.06.02(A)

(only matters “not specifically addressed” in a concept plan remain subject to

Comp Plan consistency challenges).

                                        III.

      For the foregoing reasons, we AFFIRM.

VAN NORTWICK, J., CONCURS; BENTON, J., DISSENTS WITH OPINION.




10
  The LDC provides that, when approving the concept plan, “[t]he Board shall
have the discretion to place conditions that insure compatibility of the project with
surrounding areas, insure compliance with the comprehensive plan or enhance the
public health, safety and welfare.” LDC § 2.06.02(A).
                                         13
BENTON, J., dissenting.

      In its natural state, the parcel in question could not have been developed as

now proposed, in keeping with Walton County’s comprehensive plan (Comp Plan).

This is because, as the scholarly majority opinion explains, the Comp Plan allows

no beach houses—only “boardwalks, shoreline access structures, and erosion

control measures that will enhance and protect the dune system”—in the “coastal

protection zone.” Comp Plan Policy C-1.6.1(2). The 2013 development order at

issue here authorizes construction of at least two houses in what all parties seem to

agree was the coastal protection zone before the 2010 PUD order was entered.

      Insofar as pertinent here, the Comp Plan defines the coastal protection zone

as the area between the Gulf of Mexico and “the landward toe of the primary dune

ridge . . . .” Comp Plan Policy C-1.6.1. At the time the 2010 PUD order was

entered, the primary dune ridge lay landward of sites on which the 2013 order

allows construction of at least two houses. With the intention of removing the

legal impediment the primary dune ridge—and therefore the coastal protection

zone it defined—posed, the developer proposed in 2010 to bring in bulldozers to

move the primary dune closer to the Gulf, seaward of the construction it plans.

      The 2010 order which approved this approach was not appealed, and it may

be, as the majority opinion assumes, that it would be inequitable not to allow the

relocation of the coastal protection zone at this point. I express no view on the

                                         14
issue except to suggest that the answer might very well turn on factual questions

which should not be resolved on summary judgment. The developer did not show

otherwise. I reject any suggestion that the Developer’s Concept Plan submitted in

connection with the 2010 application automatically establishes the status quo

today. For these reasons, I would reverse the summary judgment entered below,

and remand for further proceedings.




                                       15
