Elawyers Elawyers
Ohio| Change

JOYCE (JOY) E. TOWLES CUMMINGS vs BUCKEYE FLORIDA, L.P., AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 97-000692 (1997)

Court: Division of Administrative Hearings, Florida Number: 97-000692 Visitors: 13
Petitioner: JOYCE (JOY) E. TOWLES CUMMINGS
Respondent: BUCKEYE FLORIDA, L.P., AND DEPARTMENT OF ENVIRONMENTAL PROTECTION
Judges: DON W. DAVIS
Agency: Department of Environmental Protection
Locations: Perry, Florida
Filed: Feb. 10, 1997
Status: Closed
Recommended Order on Thursday, September 11, 1997.

Latest Update: Oct. 24, 1997
Summary: Whether Respondent Buckeye Florida L.P., (Buckeye), has provided reasonable assurances to Respondent Department of Environmental Protection (Department) that construction activity for the proposed project will comply with applicable provisions of Chapter 373, Florida Statutes, and related administrative rules.Petitions should be dismissed for lack of standing and lack of verified petitions.
97-0692.PDF

STATE OF FLORIDA

DIVISION OF ADMINISTRATIVE HEARINGS


JOYCE (JOY) E. TOWLES CUMMINGS, ET AL.,

)

)



)

Petitioners,

)


)

vs.

) Case Nos.

97-0692


)

97-0930

STATE OF FLORIDA, DEPARTMENT OF

)

97-1449

ENVIRONMENTAL PROTECTION, and

)


BUCKEYE FLORIDA, L.P.,

)



)


Respondents.

)


)


RECOMMENDED ORDER


Pursuant to notice, Administrative Law Judge Don W. Davis, duly designated by the Division of Administrative Hearings, held a formal hearing in the above-styled case on July 7-10, 1997, in Perry, Florida. The following appearances were entered:

APPEARANCES


For Petitioner Sharon Cutter:


Sharon Cutter, pro se Route 1, Box 1130

Perry, Florida 32347


For Petitioners Ronnie Edwards, Rebecca Edwards, and Mitchell Edwards:


Ronnie Edwards Rebecca Edwards

Mitchell Edwards, pro se Route 1, Box 160

Perry, Florida 32347 For Petitioner Joyce T. Cummings:

No Appearance

For Respondent Department of Environmental Protection:


Lynette L. Ciardulli, Esquire Jennifer L. Fitzwater, Esquire Department of Environmental

Protection,

2600 Blair Stone Road Tallahassee, Florida 32399


For Respondent Buckeye Florida, L.P.:


Terry Cole, Esquire Pat Renovitch, Esquire Post Office Box 6507

Tallahassee, Florida 32314-6507


STATEMENT OF THE ISSUE


Whether Respondent Buckeye Florida L.P., (Buckeye), has provided reasonable assurances to Respondent Department of Environmental Protection (Department) that construction activity for the proposed project will comply with applicable provisions of Chapter 373, Florida Statutes, and related administrative rules.

PRELIMINARY STATEMENT


Buckeye filed an application with the Department for a permit to construct a pipeline, conveying treated effluent from the current discharge point near Buckeye’s pulp mill in Perry, Florida, to a discharge point in the estuary of the Fenholloway River. Subsequently, the Department issued its Notice of Intent to permit the proposed project on December 31, 1996.

Between February 10-27, 1997, the Department forwarded the Petitioners’ challenges to the Division of Administrative Hearings for conduct of formal administrative proceedings.

The cases of the various Petitioners were consolidated by order issued March 31, 1997, and, following one continuance, the matter was set for final hearing to be convened on July 7, 1997.

At the final hearing, Petitioners presented testimony of eight witnesses and six exhibits. Respondents presented nine witnesses and 25 exhibits. Petitioner Cummings did not appear at the final hearing and no evidence was presented on her behalf.

Upon commencement of the final hearing, the Petition of Cummings was dismissed upon motion of Buckeye. Petitioner Cummings was the only party who challenged the construction variance related to the proposed permit and was also the only party who asserted that closed loop technology should be considered. The parties stipulated that these matters were no longer at issue.

The transcript of the final hearing was filed with the Division of Administrative Hearings on August 11, 1997.

Petitioners requested, and were granted, leave in excess of ten days of the transcript’s receipt in which to file proposed findings of fact. Proposed findings submitted by the parties have been utilized in the preparation of this Recommended Order.

FINDINGS OF FACT


The Parties


  1. Petitioner Sharon Cutter lives in Taylor County, Florida. Her home is about two miles south of the closest point of the pipeline project.

  2. Petitioners Ronnie, Rebecca, and Mitchell Edwards also reside in Taylor County. Their home is about two miles north of the closest point of the pipeline project.

  3. The Department is the state agency that reviewed Buckeye's application for the proposed permit and issued notice of intention to permit the construction activity.

  4. Buckeye is the applicant for the proposed permit. Since 1993, the Florida limited partnership has owned and operated a softwood dissolving kraft pulp mill in Taylor County, southeast of Perry.

    BACKGROUND


    Mill Operation


  5. Two stand-alone pulp manufacturing lines at the mill in Perry daily produce about 1200 tons of cellulose. The first line manufactures unique and highly specialized products used in meat casings, rayon tire cord, rayon textile filament, pharmaceuticals, rocket propellants, cellulose ethers for food, and a variety of other products. The second line manufactures fluff pulp for the disposable diaper industry, a specialty product.

  6. The mill directly employs about 825 people. In economic terms, the mill pays about $40 million annually in salaries and has an overall annual regional impact of approximately $180 million.

  7. The mill’s wastewater system captures effluent from the

    manufacturing process and includes 150 acres of aerated and treatment lagoons. This system is common in terms of its use in the industry.

  8. The mill discharges about 50 million gallons daily (MGD) of treated effluent from an aeration pond into the Fenholloway River near the river crossing of U.S. Highway 19, approximately

    24.6 miles upstream from the Gulf of Mexico.


  9. Headwaters of the 27-mile Fenholloway River originate in the San Pedro Bay at 100 feet above sea level. The river generally runs from east to west through Taylor County to the Gulf of Mexico at sea level. The major freshwater input to the Fenholloway River below the current discharge point is Spring Creek at mile point (MP) 13.6. The river is tidally influenced and subject to salt water influence to about MP 3.5, and would not be affected by reductions in flow from the current discharge point.

    History of the Fenholloway River


  10. Buckeye's discharge of treated industrial wastewater to the Fenholloway River is regulated by state and federal permits. The river has traditionally been a Class V (industrial use) water body.

  11. A use attainability analysis is required by the Clean Water Act every three years for any waterbody that is not at least Class III (possible to use for recreation, propagation, and maintenance of a healthy, well-balanced population of fish and

    wildlife). The purpose of this analysis is to determine if Class III uses are attainable, considering economic, technological, and social factors. Historically, use attainability analyses have primarily focused on changes in the manufacturing process, as well as any modifications to the treatment of the wastewaters.

  12. In 1991, the Department began a use attainability analysis on the feasibility of reclassifying the Fenholloway River from Class V to Class III. The three-year analysis was completed in 1994 and indicated that Class III (fishable and swimmable) designated uses and water quality criteria in the Fenholloway River were technologically and economically feasible through installation of technologies, involving mill changes, to reduce pollutant generation. The technologies also include construction of a pipeline to an area downstream where more dilution of Buckeye’s discharged waste water will be available. Additionally, the technologies include augmentation of natural flow of the river with mitigative measures at the river headwaters. Under these plans, the pipeline would remove the mill discharge from about 20 miles of the river.

  13. Specifically, three major elements in the completed use analysis are change in the manufacturing process to reduce the color of the effluent by 50 percent; relocation of the discharge point from its present location to a location 1.7 miles upstream from the mouth of the river where there is more assimilative

    capacity and dilution; and restoration of portions of the 7,000- acre San Pedro Bay to wetlands by construction of a water control structure.

  14. As a result of the completed 1994 Use Attainability Analysis, the Environmental Regulation Commission (ERC) voted on December 15, 1994, to repeal the Class V designation of the Fenholloway River. The reclassification decision designating the river as a Class III water body is effective December 31, 1997.

  15. The action of the ERC was subject to review by the United States Environmental Protection Agency (EPA). Upon review, the EPA approved the change after concluding that Class III water standards could be attained with implementation of the proposed pipeline and restoration of portions of San Pedro Bay wetlands through construction of a water control structure. The EPA also concluded that "the only other alternative that would result in the attainment of Class III standards would also have widespread economic and social impacts, i.e., closure of the mill."

  16. The Department and Buckeye executed the Fenholloway River Agreement on March 29, 1995. In that agreement, the parties set forth steps and schedules necessary to achieve standards required for reclassification of the Fenholloway River to a Class III water body. The agreement was publicly noticed and was not challenged by anyone.

    Permit Application

  17. Buckeye applied for the proposed permit on August 31, 1995, in accordance with the terms of the Fenholloway River Agreement. The Department then requested and received additional information from Buckeye. Thereafter, on December 31, 1996, the Department notified Buckeye of its intention to issue the proposed permit.

  18. Buckeye has applied for other authorizations and permits that are required from the Department for the pipeline project, but which are not part of this proceeding. For example, Buckeye applied for an easement from the state for private use of sovereignty submerged lands and an operation and discharge permit for its wastewater treatment system.

    Pipeline Project


  19. Buckeye proposes to construct a 15.3-mile underground, linear pipeline from the mill (MP 24.6) in Perry to an underwater discharge point (MP 1.7) in the Fenholloway River. The project also includes a water control structure in the San Pedro Bay, an effluent pump station at the Perry mill, an oxygenation facility near the end of the pipeline, and an outfall diffuser structure at the discharge point.

  20. The pipeline route is 80,200 feet long. It was selected over alternative routes to minimize environmental impacts. The river crossings are underground primarily to minimize water quality impacts during construction.

  21. The underground pipeline will be constructed from 20-

    foot sections of semi-flexible ductile iron pipe manufactured by the American Cast Iron Pipe Company in Birmingham, Alabama. The sections will be connected with flexible joints. Most of the pipeline will have 30 inches of earth over it; however, the pipe is strong enough to support 20 feet of earth. At the underground river crossings and outfall/diffuser area, the pipe will have five feet of earth over it.

  22. The ductile iron pipe is 60 inches in diameter and 1/2 inch thick. The pipe is lined with 1/4 inch thick cement to prevent internal erosion and wrapped with polyethylene (double wrapped for the last 9000 feet of wetlands ) to prevent external corrosion. The treated effluent that will flow through the pipe is an easy material to handle from a corrosion viewpoint, as it is a weak and stable effluent, similar to water. Ductile iron pipe is routinely used to transmit raw sewage.

  23. The diffuser will be made of concrete pipe, with a steel core and wrap wires around it, since the durability of concrete is proven in a saltwater environment. At the outfall/diffuser, the river is about 700-900 feet wide and 8 to

    11 or 12 feet deep (low to high tide).


  24. The maximum working pressure in the pipeline will be 50-60 pounds per square inch (psi). The ductile iron pipe is rated at 150 psi.

  25. The pump station will have capacity to transmit about


    76 million gallons of treated effluent per day. The pipeline is

    capable of receiving up to 100 MGD of the type of treated effluent now discharged by the mill.

  26. Presuming correct installation, the pipeline will not leak or crack. It will be tested for water tightness before, during, and after construction.

  27. Monitoring of the pressure in the pipeline will occur at the effluent pump station near the mill. Any significant change in pressure will activate an alarm system. The mill can immediately shut off the pumps.

  28. The pipeline meets all industry standards and should last well over 100 years. The concrete diffuser may have to be replaced every 10-20 years, but there is easy access for replacement.

  29. Test borings along the pipeline route have revealed no sinkholes. If sinkholes are encountered during construction, they will be filled before the pipe is installed. The predominant type of sinkholes that could develop after installation are doline or solution sinks. They typically settle at a rate of 1 foot every 5,000-6,000 years. The pipe and flexible joints (which flex 12 inches) will easily tolerate this minimal movement.

  30. The diffuser has 20 ports, spaced five feet apart which can be rotated based on desired direction of discharge. Some will face upstream and some downstream to ensure good mixing of the treated effluent and river water. At mean low water, there

    will be about six feet of clearance above the ports. When the plume from the ports reaches the surface, it will have a ripple of about a quarter of an inch. The ripple will not impact a canoe. The closest port to the west bank is 25 feet, but due to the angle of that port, effect of any discharge from that port will be 73 feet from the bank.

  31. The contractor selected to construct the pipeline is believed to have an outstanding reputation for construction projects similar to this one. Buckeye will accept responsibility for the pipeline and implement its usage only after extensive tests (culminating in final hydrostatic testing), assuring that construction meets all requirements of the proposed permit and industry standards.

  32. Buckeye will operate, maintain, and inspect the pipeline and related facilities once they are completed, using acceptable

    management practices. Coverage will be seven days a week, the same as for the mill facility at present.

  33. Cleaning the pipe will be a mechanical process, not using cleaning agents. Barnacles will not be a problem due to the constant flow in the pipe.

    Water Quality Standards


  34. Buckeye will meet all water quality standards, except for turbidity during construction at the two river crossings and outfall/diffuser. A variance for turbidity at these three

    locations during construction was requested by Buckeye and approved by the Department. The only challenge to that variance has been dismissed.

  35. Buckeye will minimize turbidity during construction by using a series of best management practices. For example, Buckeye will use silt curtains, silt fences and filtration bags. As a consequence, turbidity will be minimal, temporary in nature and negligible.

  36. The technologies which Buckeye will employ is expected at this time to improve the water quality in the river, estuary and Gulf.

    Environmental Impacts


  37. Buckeye provided reasonable assurance to the Department that construction of the proposed pipeline project will not adversely affect the public health, safety, welfare, or property of others. Overall, the proposed project will positively affect the public health, safely, welfare, and property of others.

  38. There is no risk to humans and ecological receptors that may be associated with metals or dioxin in river sediments.

    Conservation


  39. There are no threatened or endangered wildlife species that will be impacted by the proposed project. The four species of special concern (gopher tortoise, American alligator, eastern indigo snake, and Sherman fox squirrel) in the project area will be minimally affected due to special protection programs and

    temporary relocation.


  40. The draft permit contains conditions providing for the protection of species of special concern that were recommended by the Florida Game and Fresh Water Fish Commission. The relocation of gopher tortoises and the eastern indigo snake are examples. These conditions are typically used to ensure the protection of species.

  41. Buckeye will provide for the protection of manatees that was recommended by the Department's Bureau of Protected Species Management, even though none have been observed in the project area.

  42. There will be minimal or negligible effect on the habitat value of fish and wildlife.

    Navigation, Erosion or Shoaling


  43. At each of the two subaqueous river crossings (upstream at MP 17.8 and MP 24.4), boats will not be able to navigate approximately 100 feet of the river for the six-seven days during construction of the coffer dam structures. However, a canoeist could portage around these sites. Due to tree-falls in this upper reach of the river, portages are required anyway.

  44. The permit conditions require Buckeye to work 24-hours per day while constructing the subaqueous river crossings in order to minimize adverse affects to navigation.

  45. At the outfall/diffuser area downstream in the estuary, boat traffic will never be prevented from moving up and down the

    river. However, it will be slowed or temporarily stopped (no more than 20 minutes during four blasts) during a 30-day construction period. Detonation will be conducted in a manner to reduce total acoustical shockwave. The minimum six-foot clearance above the diffuser ports will not be an impedance to navigation.

  46. Presently, there is erosion of the banks at the outfall/diffuser site due to boat wake and tidal influence. The construction of the last 80 feet of the diffuser has the potential of temporarily accelerating this erosion on the west bank of the river by causing boat traffic to be moved closer to that bank during construction. To protect this bank during construction, Buckeye has agreed to place filter fabric overlaid with sandbags on the exposed sections of the bank. This will prevent erosion caused by the construction of the diffuser.

  47. The permit requires Buckeye to use the best management practices to control erosion during construction. With those in place, there will be minimal erosion or shoaling during construction.

  48. Construction will not adversely affect the fishing or recreational values or marine productivity.

  49. The proposed project will not cause adverse water quantity impacts to receiving waters or adjacent lands. It will not cause permanent dewatering.

  50. The proposed project will not cause sedimentation

    downstream of the outfall/diffuser, decrease the storage of waters, reduce the floodway conveyance, or reduce surface water storage volumes.

    Project Nature


  51. The project will be permanent. The construction trestle at the diffuser/outfall will be temporary.

  52. Most of the impacts of the project to vegetation and wildlife are temporary during construction. Natural revegetation will return most areas to their normal condition.

  53. The only permanent impact to wetlands is the loss of


    0.39 acres for construction of the oxygenation facility in a river swamp area. In addition, 5.48 acres of forested wetlands will be converted to shrub wetlands condition. These are the only permanent impacts to wetlands associated with the proposed project. Disturbance of wetlands will be minimized.

  54. The construction of the proposed pipeline project is expected to take less than one year. All of the necessary easements on private lands have been obtained. Buckeye's requested easements on sovereign submerged land are pending. Buckeye owns all of the other land for the proposed project.


    Historical And Archaeological Resources


  55. An extensive study of the pipeline corridor by an archeological firm with an excellent reputation reveals that there are no significant archeological sites found along the

    corridor. In addition to the study, subsequent examinations of the corridor by state and private archeologists (including underwater explorations by a consultant) confirmed this conclusion.

  56. The Department of State has advised the Department that the Buckeye project will not affect any sites eligible for listing in the National Register of Historic Places or any sites of historical or archaeological value. There are 16 possible historical sites along the project route. None are deemed significant or eligible for listing on the National Historic Registry.

  57. A study of the San Pedro Bay mitigation area also revealed no significant archeological sites.

  58. There is a significant archeological site (site 142) on the west bank of the river near the outfall/diffuser. Neither construction of the pipeline nor discharge of the treated effluent transmitted by the pipeline will impact that site, including the banks, due to the planned erosion control plan.

    Wetland Areas Affected


  59. The proposed project affects wetlands. However, any impacts to wetlands are sufficiently offset by the proposed mitigation plan in the San Pedro Bay.


    Cumulative Impacts


  60. There are no significant adverse cumulative impacts

    which would result from the proposed project. There is a beneficial cumulative impact in the improvement to the water quality of the river, allowing reclassification of the river from Class V to Class III.

  61. Along the pipeline route, there will be no adverse hydrological impact to the wetlands.

  62. The removal of Buckeye’s treated effluent from the current discharge point near the mill will cause a drop in the surface water elevations of the river’s upper reach (above Hampton Springs) by one-half foot, a drop which is not considered significant. Due to tidal effects in the river at the diffuser location, there will be no hydraulic difference at the proposed location of the discharge.

  63. Downstream of Spring Creek, the Fenholloway River picks up flow from springs, groundwater, discharge from Spring Creek and tidal effect. There will be no impact on water levels downstream of Spring Creek caused by the relocation of the discharge point from the mill to the estuary, due to these additional flow contributions.

    Mitigation Area in San Pedro Bay


  64. The proposed permit requires Buckeye to restore 25 acres of drained wetlands in San Pedro Bay included within a 7,000-acre parcel that Buckeye owns. In the past, the area was hydrologically altered due to forestry activities.

  65. The San Pedro Bay area is the headwaters of the Fenholloway River. Construction of the proposed water control structure in the part of the Bay that Buckeye owns will rehydrate the area and restore it to natural conditions.

  66. Through the development of a computer model of the San Pedro Bay, Buckeye studied how the hydrology and hydraulics in this area would be affected by the proposed water control structure. The model shows that the structure will enable the area to hold more water and return to more natural conditions (to rehydrate the area).

  67. The water control structure will reduce the low-flow days in the Main Bay Canal (connecting San Pedro Bay to the mill area). It will not cause flooding or affect any off-site property. It will reduce erosion.

  68. The proposed mitigation is sufficient to offset the impacts of the proposed project.

    Other Facts Relating to Petitioners


  69. Petitioners' properties are located about two miles from any part of the pipeline project. Construction of the pipeline project will have no substantial affect on Petitioners' properties or any other interest of Petitioners which is unique to them to the exclusion of the general public.

  70. Petitioners will continue to be able to travel to the river, use their boats on the river, and view the plants and wildlife along the river from their boats. Even during

    construction, they will be able to access the river and launch their boats from the Hicks Landing, located on Buckeye property. After construction, they will be able to launch from this site and at Peterson's Landing. Thus, construction of the project will not substantially affect access to the river or uses of the river related to boating activity.

    CONCLUSIONS OF LAW


  71. The Division of Administrative Hearings has jurisdiction over the parties and the subject matter. Section 120.57(1), Florida Statutes.

    Standing


  72. In their Amended Petitions, Petitioners state that they submitted their petitions pursuant to Section 120.57(1), Florida Statutes. That statute provides standing to Petitioners in this proceeding only if their "substantial interests will be affected by the proposed agency action." Yet, insofar as real property is concerned, Petitioners do not contend that their real property will be substantially affected by the proposed pipeline project, real property which is at least two miles from any portion of the project.

  73. Petitioners have the burden of showing, as a matter of fact, that they have "substantial interests" that will be adversely affected if the Department issues the proposed permit to Buckeye. The purpose of this standing requirement:

    [I]s to ensure that a party has a "sufficient interest in

    the outcome of the litigation which warrants the court's entertaining it," and to assure that a party has a personal stake in the outcome.


    Gregory v. Indian River Co., 610 So. 2d 547, 554 (Fla. 1st DCA 1992).

  74. The record is devoid of competent, substantial evidence demonstrating that the Department's action in issuing the proposed permit affects any substantial interest of Petitioners which is unique to Petitioners to the exclusion of the general public. Consequently, Petitioners failed to demonstrate any right to a 120.57 proceeding wherein they could challenge Buckeye's entitlement to the proposed permit. See Florida Department of Transportation v. J.W.C. Co., Inc., 396 So. 2d 778, 787 (Fla. 1st DCA 1981)

  75. In order to demonstrate that the Department's action affects their "substantial interests," Petitioners must prove the degree and nature of their alleged interests. Agrico Chemical Co. v. Department of Environmental Regulation, 406 So. 2d 478,

    482 (Fla. 2nd DCA 1981). To do this, they must demonstrate that they will suffer injury in fact which is of sufficient immediacy to entitle them to a Section 120.57 hearing and that such substantial injury is of a type or nature which the proceeding is designed to protect. Petitioners have not proven standing pursuant to provisions of Section 120.57(1), Florida Statutes.

  76. In the course of this proceeding, Petitioners have also disclosed that they rely upon provisions of Section 403.412(5), Florida Statutes, to permit their standing and participation. Section 403.412(5), Florida Statutes, provides:

    In any administrative, licensing, or other proceedings authorized by law for the protection of the air, water, or other natural resources of the state from pollution, impairment, or destruction, the Department of Legal Affairs, a political subdivision or municipality of the state, or a citizen of the state shall have standing to intervene as a party on the filing of a verified pleading asserting that the activity, conduct, or product to be licensed or permitted has or will have the effect of impairing, polluting, or otherwise injuring the air, water or other natural resources of the state. (emphasis supplied).

  77. Notably, the Petitioners' entry into the proceeding, pursuant to Section 403.412(5), Florida Statutes, is considered to be in the capacity of intervenors with the implied requirement of an existing controversy. Such a controversy may be considered to exist after an agency has entered, as in this case, an intended decision to grant the requested permit. MANASOTA-88, Inc. v. Department of Environmental Regulation, (Fla. App. 1st Dist. 1983).

  78. Although MANASOTA, supra, creates an opportunity for Petitioners to challenge the proposed permit, they must comply with procedures established by Section 403.412(5), Florida Statutes, requiring that any such intervention must be by "verified" petitions. It is observed that Petitioners did not

    provide such verified petitions. Consequently, all the Petitions are found to be deficit in that respect and, accordingly, should be dismissed on that basis.

  79. Alternatively, if it is assumed that Petitioners have standing, Buckeye has affirmatively provided the Department with the required "reasonable assurance that state water quality standards . . . will not be violated and reasonable assurance that such activity [construction of the pipeline project] . . . is not contrary to the public interest." Section 373.414(1), Florida Statutes; and Rule 62-312.080, Florida Administrative Code.

  80. Just as Petitioners are required to offer proof of standing, Buckeye must demonstrate entitlement to the proposed permit by a preponderance of the competent, substantial evidence. See J.W.C., supra. Buckeye has met this requirement.

  81. The proof establishes that the proposed pipeline project complies with the applicable surface water quality standards in Rule Chapters 62-302, Florida Administrative Code; and that the proposed project satisfies the "public interest test" of Section 373.414(1)(a), Florida Statutes, as well as related Rules 40B-4.2030 and 40B-400.103-.104, Florida Administrative Code.

  82. Finally, Section 373.414(8), Florida Statutes, requires a consideration of the "cumulative impacts upon surface water and wetlands." Respondents demonstrated at hearing that the proposed

project will meet all surface water quality standards, with the exception of turbidity during construction. However, such turbidity during construction is allowed by the temporary construction variance issued by the Department. Consequently, Buckeye has demonstrated compliance with applicable requirements of Section 373.414, Florida Statutes and related rules.

RECOMMENDATION


Based on the foregoing findings of fact and conclusions of law, it is

RECOMMENDED that a final order be entered dismissing all the Petitions and issuing the proposed draft environmental resource permit to Buckeye.

DONE AND ENTERED this 11th day of September, 1997, in Tallahassee, Leon County, Florida.


DON W. DAVIS

Administrative Law Judge

Division of Administrative Hearings The DeSoto Building

1230 Apalachee Parkway

Tallahassee, Florida 32399-3060

(904) 488-9675 SUNCOM 278-9675

Fax Filing (904) 921-6847


Filed with the Clerk of the Division of Administrative Hearings this 11th day of September, 1997.


ENDNOTES

1/ For a site to be significant, it must be eligible to be listed on the National Historic Registry. For an archeological site, that means the archeological site must have contributed in the past or be able to contribute in the future information

significant to the region's prehistory. (Tr. IV at 429 - Hardin; Tr. VI at 626 - Kammerer)

The following procedure is followed to determine if a site is significant: test the site and collect artifact, evaluate the stratigraphy of the site to ascertain if it has been disturbed in the past, examine the collected information to learn the type and time of the site, and determine if the site can provide new information. (Tr. VI at 623-624 - Kammerer)

2/ Hydrology is the science involving the calculations or the methods to convert rainfall and distribution of rainfall to a particular runoff or a quantity of water. It takes into account the rainfall distribution, the quantity or rain, the cover of the land that you're looking at, the slope, the topography, and so forth, and converts all of that through systems of known relationship to a runoff quantity. (Tr. II at 209- Vickstrom)

3/ Hydraulics is taking a known quantity of water and routing it through structures like bridges or culverts or control structures like weirs or over dam embankments, through ditches, to convert that quantity of water to a flood elevation or a stage. (Tr. II at 209 - Vickstrom)


COPIES FURNISHED:


Ronnie Edwards Rebecca Edwards Mitchell Edwards Route 1, Box 167

Perry, Florida 32347


Terry Cole, Esquire Post Office Box 6507

Tallahassee, Florida 32314-6507


Sharon Cutter Route 1, Box 1130

Perry, Florida 32347


Lynette Ciardulli, Esquire

Department of Environmental Protection 3900 Commonwealth Boulevard

Tallahassee, Florida 32399-3000


Kathy Carter, Agency Clerk

Department of Environmental Protection Mail Station 35

3900 Commonwealth Boulevard

Tallahassee, Florida 32399-3000

F. Perry Odom, Esquire

Department of Environmental Protection 3900 Commonwealth Boulevard

Tallahassee, Florida 32399-3000


Virginia B. Wetherell, Secretary Department of Environmental Protection 3900 Commonwealth Boulevard

Tallahassee, Florida 32399-3000


NOTICE OF RIGHT TO SUBMIT EXCEPTIONS


All parties have the right to submit written exceptions within

15 days from the date of this Recommended Order. Any exceptions to this Recommended Order should be filed with the agency that will issue the Final Order in this case.


Docket for Case No: 97-000692
Issue Date Proceedings
Oct. 24, 1997 Final Order filed.
Oct. 08, 1997 Transcript (Pending Motions) filed.
Oct. 03, 1997 Respondent Department of Environmental Protection`s Response to Petitioner Cutter`s Exceptions to Recommended Order filed.
Sep. 30, 1997 Respondent Department of Environmental Protection`s Response to Petitioner`s Exceptions to Recommended Order filed.
Sep. 11, 1997 Recommended Order sent out. CASE CLOSED. Hearing held 07/07-10/97.
Sep. 10, 1997 Buckeye Florida, L.P.`s Response to Petitioner`s Proposed Recommended Order filed.
Sep. 05, 1997 Proposed Recommended Order of Petitioner Cutter filed.
Sep. 02, 1997 (Petitioner) A Motion for Objection of Hearing Transcript (filed via facsimile).
Aug. 29, 1997 Petitioners Edwards, Ronnie, Rebecca and Mitchell Proposed Recommended Order; Cover Letter filed.
Aug. 26, 1997 Order on Request for Extension of Time to File Proposed Findings of Fact sent out.
Aug. 26, 1997 (Petitioner) Motion for Extension of Time for Filing a Recommended Order filed.
Aug. 21, 1997 Respondent Department of Environmental Protection`s Proposed Recommended Order; Disk filed.
Aug. 21, 1997 Proposed Recommended Order of Buckeye Florida, L.P.; Disk ; Buckeye Florida, L.P.`s Objection to Request for Extension filed.
Aug. 11, 1997 Respondent`s Exhibit 38; Cover Letter filed.
Aug. 11, 1997 Transcripts (Volumes 1 thru 7, tagged) filed.
Jul. 08, 1997 Governor Lawton Chiles` Motion to Quash Subpoena filed.
Jul. 07, 1997 CASE STATUS: Hearing Held.
Jul. 07, 1997 (Cutter and Edwards) An Affidavit of Service of the Following Subpoena`s; Cover Letter (filed via facsimile).
Jul. 03, 1997 Order Denying Continuance and Motion to Compel sent out.
Jul. 03, 1997 Buckeye Florida, L.P.`s Motion to Quash Subpoenas and Motion for Protective Order Regarding Charles S. Aiken; (2) Subpoena Duces Tecum (from S. Cutter, R. Edwards) filed.
Jul. 01, 1997 (DEP) Response to Petitioner`s Motion to Reschedule Hearing; Certificate of Service (Inadvertently failed to include in the Joint Pre-Hearing Stipulation) filed.
Jul. 01, 1997 Buckeye Florida, L.P Response in Opposition to Petitioners` Request to Reschedule Hearing filed.
Jun. 30, 1997 (Signed by P. Renovitch, L. Ciardulli) Joint Pre-Hearing Stipulation filed.
Jun. 30, 1997 (Petitioner) Motion to Reschedule Hearing; (Petitioner) A Motion for Order to Compel for Petitioner to a Full Discovery and a Request for a Continuance (filed via facsimile).
Jun. 27, 1997 (DEP`s) Order Closing File (Order filed in DOAH case 97-931) filed.
Jun. 27, 1997 (Respondent) Motion to Admit Matters Specified in Respondent`s Request for Admissions by Operation of Law and motion in Limine filed.
Jun. 27, 1997 (Respondent) Motion for Summary Recommended Order filed.
Jun. 25, 1997 Order Denying Consolidation sent out. (for 97-2902 to be added to 97-0692, 97-0930 & 97-1449)
Jun. 18, 1997 Response of Buckeye Florida, L.P. in Support of The Motion to Consolidate Filed by the Department of Environmental Protection filed.
Jun. 18, 1997 (2) Respondent, Department of Environmental Protection`s Response to Petitioner`s Request for Production of Documents filed.
Jun. 17, 1997 (Petitioners) Response to DEP`s Motion to Consolidate filed.
Jun. 17, 1997 Response (Including Objections) of Buckeye Florida, L.P. to Discovery Requests by Petitioners Cutter and Edwards; Notice of Answering Interrogatories of Petitioners Cutter and Edwards filed.
Jun. 12, 1997 Notice of Related Case and Motion to Consolidate by Respondent Department of Environmental Protection filed. (for 97-0692, 97-0930, 97-1449 & 97-2902)
Jun. 12, 1997 Buckeye Florida, L.P.`s Witness List; Amended Notice of Taking Deposition filed.
Jun. 06, 1997 (Buckeye) Notice of Taking Deposition filed.
Jun. 02, 1997 (Ronnie, Rebecca and Mitchell Edwards) Notice to Obtain for Subpoenas filed.
May 30, 1997 (Buckeye Fl. L.P.) Amended Notice of Taking Depositions Duces Tecum by Videotape filed.
May 28, 1997 (Buckeye Fl. L.P.) Notice of Taking Depositions Duces Tecum filed.
May 23, 1997 (From P. Renvoitch) (3) Request for Admissions filed.
May 22, 1997 Case No/s: unconsolidated. 97-000928
May 22, 1997 Order Closing File sent out. CASE 97-928 ONLY CLOSED.
May 22, 1997 Case No/s: unconsolidated. 97-000931 Order Closing File sent out. CASE NO 97-931 ONLY CLOSED.
May 21, 1997 (From R., R., M. Edwards) Notice of Service of Interrogatories and Production of Documents to Respondent Buckeye Florida L.P.; Notice of Service of Interrogatories and Production of Documents to Respondents Environmental Protection filed.
May 21, 1997 (Petitioner) A Motion to Withdraw Petition (Filed by Fax) filed.
May 20, 1997 (Buckeye Fl. L.P.) Second Motion for Order Compelling Discovery and Sanctions and Request for Expedited Hearing on Motion filed.
May 20, 1997 (From P. Renovitch) Third Amended Notice of Taking Depositions Duces Tecum filed.
May 19, 1997 (Petitioner) Notice to Obtain Subpoenas (filed via facsimile).
May 19, 1997 (Petitioner) A Motion to Withdraw My Petition filed.
May 19, 1997 Memo to DWD from Sharon Cutter (RE: request for subpoenas) (filed via facsimile).
May 19, 1997 (Petitioner) A Motion to Withdraw My Petition filed.
May 15, 1997 CASE NO. 97-927 ONLY CLOSED, per Petitioner`s notice of withdrawal sent out.
May 15, 1997 Case No/s: unconsolidated. 97-000927
May 13, 1997 Order Closing File, case 97-927 only filed.
May 07, 1997 Order sent out.
May 05, 1997 (Buckeye Fl. L.P.) Notice of Filing Interrogatory Answers; Interrogatories to Roy D. Sadler; Interrogatories to Margaret Terry; Interrogatories to James Green; Interrogatories to Ronnie Edwards, Rebecca Edwards and Mitchell Edwards filed.
May 05, 1997 (Respondent) Motion for Order Compelling Discovery and Sanctions and Request for Expedited Hearing on Motion filed.
Apr. 30, 1997 (From P. Renovitch) Order Upon Request for Prehearing Conference; Disk w/cover letter filed.
Apr. 29, 1997 Order Providing Notice of Prehearing Conference sent out. (set for 5/8/97; 10:00am; Perry)
Apr. 22, 1997 Order Upon Pending Motions sent out.
Apr. 21, 1997 Letter to DWD from Joy Towles (RE: notice of telephone hearing) (filed via facsimile).
Apr. 21, 1997 Notice of Filing Department`s December 31, 1996, Notice of Intent to Issue Environmental Resource Permit and Related Documents; Exhibits filed.
Apr. 18, 1997 Response of Buckeye Florida, L.P., to April 15, 1995 Ex Parte Communications by Petitioners Edwards filed.
Apr. 18, 1997 Response of Buckeye Florida, L.P., in Opposition to Petitioners` "Motion to Strike Some of Interrogatories Questions" and Request for Oral Argument filed.
Apr. 17, 1997 (Petitioner) A Motion to Strike Some of Interrogatories Questions filed.
Apr. 17, 1997 (Buckeye) Amended Notice of Taking Deposition Duces Tecum filed.
Apr. 17, 1997 (Buckeye) Amended Notice of Hearing filed.
Apr. 16, 1997 Order Upon Ex Parte Communication sent out. (Relief Requested by Exhibit "A" is Denied; Re: Fl Stats 120.66)
Apr. 15, 1997 (From M. Edwards) A Motion for the Removal of the Presiding Hearing Officer filed.
Apr. 15, 1997 (From R. & R. Edwards) A Motion for the Removal of the Presiding Hearing Officer filed.
Apr. 14, 1997 Order Granting Motion to Reschedule Final Hearing sent out. (hearing set for July 7-11, 1997; 10:00am; Perry)
Apr. 10, 1997 (Respondent) Notice of Hearing filed.
Apr. 08, 1997 Response of Buckeye Florida, L.P. to Initial Order in Sharon Cutter Case, Status Report Concerning Prehearing Meeting, and Updated Information About April 14 and 21, 1997, Motion Hearings filed.
Apr. 08, 1997 (Buckeye) Amended Notice of Hearing filed.
Apr. 07, 1997 Case No/s: unconsolidated. 97-000929
Apr. 07, 1997 Order Closing File sent out. CASE 97-929 ONLY CLOSED, per Motion to Withdraw Petition filed.
Mar. 31, 1997 Order of Consolidation sent out. (Cases to be consolidated: 97-692, 97-927, 97-928, 97-930, 97-931, 97-1449)
Mar. 31, 1997 (Buckeye) Notice of Hearing filed.
Mar. 28, 1997 (Respondent) Notice of Scheduling Conflict and Motion to Reschedule Hearing filed.
Mar. 27, 1997 (Buckeye) Notice of Service of Interrogatories to Petitioner James Green filed.
Mar. 27, 1997 (Buckeye) Notice of Service of Interrogatories to Petitioner Roy D. Sadler; (Respondent) Motion for Expedited Discovery filed.
Mar. 27, 1997 (Buckeye) Notice of Service of Interrogatories to Petitioners Ronnie Edwards, Rebecca Edwards and Mitchell Edwards; Notice of Service of Interrogatories to Petitioner Margaret Terry filed.
Mar. 27, 1997 (Buckeye) Notice of Service of Interrogatories to Petitioner Ruby Morgan filed.
Mar. 27, 1997 Buckeye Florida, L.P.`s Request for Production of Documents to Petitioner Margaret Terry filed.
Mar. 27, 1997 Buckeye Florida, L.P.`s Request for Production of Documents to Petitioner Roy D. Sadler; Buckeye Florida, l.P.`s Request for Production of Documents to Petitioner Ruby Morgan filed.
Mar. 27, 1997 Buckeye Florida, L.P.`s Request for Production of Documents to Petitioners Ronnie Edwards, Rebecca Edwards and Mitchell Edwards; Buckeye Florida, L.P.`s Request for Production of Documents to Petitioner James Green filed.
Mar. 21, 1997 Amended Order of Prehearing Instructions sent out.
Mar. 21, 1997 Amended Notice of Hearing sent out. (hearing set for May 5-9, 1997; 10:00am; Perry)
Mar. 21, 1997 (From T. Cole) Notice of Service of Interrogatories to Petitioner; Buckeye Florida, L.P.`s Request for Production of Documents to Petitioner, Joyce (Joy) Towles Cummings filed.
Mar. 20, 1997 Notice of Related Case and Motion to Consolidate by Respondent Department of Environmental Protection and Buckeye Florida, L. P. filed.
Mar. 20, 1997 Notice of Related Case and Motion to Consolidate by Respondent Department of Environmental Protection filed.
Mar. 17, 1997 Order of Prehearing Instructions sent out.
Mar. 17, 1997 Notice of Hearing sent out. (hearing set for 05/05-09/97;10:00a.m.;Perry)
Mar. 17, 1997 Joint Response of Buckeye Florida, L.P. and Florida Department of Environmental Protection to Initial Orders and Request for Scheduling Conference filed.
Mar. 14, 1997 Order of Consolidation sent out. Consolidated case are: 97-000692 97-000927 97-000928 97-000929 97-000930 97-000931 . CONSOLIDATED CASE NO - CN002664
Mar. 07, 1997 Response of Buckeye Florida, to Amended Petition for Administrative Hearing on Environmental Resource Permit Including Motion to Strike Irrelevant Issues Motion for A More Definite Statement, Motion to Dismiss Challenge to Variance etc... filed.
Mar. 07, 1997 (Cont) Motion to Dismiss "Amended" Petition, and Request for Oral Argument filed.
Mar. 07, 1997 Response of Buckeye Florida, L.P., to Amended "Petition for Administrative Hearing on Environmental Resource Permit," Including Motion to Strike Irrelevant Issues, Motion for A More Definite Statement, Motion to Dismiss Challenge to Variance, filed.
Mar. 07, 1997 Response of Buckeye In Support of Department`s Motion to Consolidate filed.
Mar. 04, 1997 Amended Response of Buckeye Florida, L.P., to Initial Order and Request for Scheduling Conference filed.
Mar. 04, 1997 Notice of Related Case and Motion to Consolidate By Respondent Department of Environmental Protection filed.
Feb. 27, 1997 Motion to Strike Allegations Contained in the Amended Petition (Respondent) filed.
Feb. 25, 1997 Response of Buckeye Florida, L.P. to Initial Order filed.
Feb. 19, 1997 Response of Buckeye Florida, L.P., to "Petition for Administrative Hearing on Environmental Resource Permit," Including Motion to Strike Irrelevant Issues, Motion for a More Definite Statement, Motion to Dismiss Challenge to Variance, and Request for Oral
Feb. 13, 1997 (From P. Renovitch) Notice of Appearance filed.
Feb. 13, 1997 Initial Order issued.
Feb. 10, 1997 Request for Assignment of Administrative Law Judge and Notice of Preservation of Record; Agency Action Letter; Petition for Administrative Hearing On Environmental Resource Permit; Notice Of Intent To Issue Permit; Draft Permit; Intent To Grant Variance;

Orders for Case No: 97-000692
Issue Date Document Summary
Oct. 22, 1997 Agency Final Order
Sep. 11, 1997 Recommended Order Petitions should be dismissed for lack of standing and lack of verified petitions.
Source:  Florida - Division of Administrative Hearings

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer