Elawyers Elawyers

Riverfront Development, Inc. v. Wepfer Marine, Inc., 19-6088 (2020)

Court: Court of Appeals for the Sixth Circuit Number: 19-6088 Visitors: 9
Filed: Jun. 26, 2020
Latest Update: Jun. 26, 2020
Summary: NOT RECOMMENDED FOR PUBLICATION File Name: 20a0382n.06 No. 19-6088 UNITED STATES COURT OF APPEALS FOR THE SIXTH CIRCUIT FILED Jun 26, 2020 RIVERFRONT DEVELOPMENT, INC., and ) DEBORAH S. HUNT, Clerk CITY OF MEMPHIS, TENNESSEE, ) ) Plaintiffs-Appellees, ) ON APPEAL FROM THE UNITED ) STATES DISTRICT COURT FOR v. ) THE WESTERN DISTRICT OF ) TENNESSEE WEPFER MARINE, INC., ) ) Defendant-Appellant. ) ) BEFORE: BATCHELDER, STRANCH, and MURPHY, Circuit Judges. MURPHY, Circuit Judge. One clear July day, a
More
                        NOT RECOMMENDED FOR PUBLICATION
                                File Name: 20a0382n.06

                                            No. 19-6088

                           UNITED STATES COURT OF APPEALS
                                FOR THE SIXTH CIRCUIT
                                                                                         FILED
                                                                                   Jun 26, 2020
RIVERFRONT DEVELOPMENT, INC., and                     )                        DEBORAH S. HUNT, Clerk
CITY OF MEMPHIS, TENNESSEE,                           )
                                                      )
       Plaintiffs-Appellees,                          )      ON APPEAL FROM THE UNITED
                                                      )      STATES DISTRICT COURT FOR
v.                                                    )      THE WESTERN DISTRICT OF
                                                      )      TENNESSEE
WEPFER MARINE, INC.,                                  )
                                                      )
       Defendant-Appellant.                           )
                                                      )


       BEFORE: BATCHELDER, STRANCH, and MURPHY, Circuit Judges.

       MURPHY, Circuit Judge. One clear July day, a towboat making its way to the Mississippi

River ran aground on the foot of Mud Island in Memphis, Tennessee. The vessel left large holes

on Mud Island’s banks. The City of Memphis and its agent, Riverfront Development, Inc., invoked

the district court’s admiralty jurisdiction to bring this negligence suit against Wepfer Marine, Inc.,

the owner of the grounded vessel. After finding Wepfer liable for the grounding, the district court

awarded $1,145,990 in damages. Wepfer now challenges only the damages ruling. For the most

part, we reject Wepfer’s claims under our deferential standard of review. But the district court did

commit one clear error in calculating the damages award. We thus reverse the judgment and

remand for entry of an amended award consistent with this opinion.
No. 19-6088, Riverfront Development, Inc., et al. v. Wepfer Marine, Inc.


                                                 I

                                                 A

       Mud Island sits in Memphis, Tennessee, where the Wolf River Harbor meets the

Mississippi River. It is not in fact an island, but a peninsula running north-and-south down the

Tennessee side of the Mississippi River. To the island’s west lies the Mississippi River and then

Arkansas; to its east lies the Wolf River Harbor and then downtown Memphis. Mud Island’s

undeveloped southern tip juts out where the Wolf River Harbor meets the Mississippi.

       On July 6, 2015, Captain Jared LaFrance was piloting the M/V Lucy Wepfer southbound

through the Wolf River Harbor toward the Mississippi. The Lucy Wepfer pushed a barge loaded

with concrete slurry. LaFrance intended to make a “U-turn” and steer his vessel northward up the

Mississippi River. As he entered the Mississippi, Mud Island was to his starboard (right) side.

The Mississippi was high that day, and Mud Island’s southern tip was submerged. LaFrance made

his starboard turn into the Mississippi prematurely, and the Lucy Wepfer ran aground on Mud

Island’s submerged southern tip. In the language of admiralty law, this was an “allision,” which

“occurs when a moving vessel strikes a stationary object[.]” Bessemer & Lake Erie R.R. Co. v.

Seaway Marine Transp., 
596 F.3d 357
, 362 (6th Cir. 2010). The Lucy Wepfer and the barge were

extracted after some effort. The water’s later receding revealed two large gashes on Mud Island’s

eastern shore.

                                                 B

       Riverfront Development, Inc., Mud Island’s managing agent, sued Wepfer Marine, Inc.,

the Lucy Wepfer’s owner, for negligence. Riverfront sought to recover the costs of repairing the

damage to Mud Island. The City of Memphis later intervened as a plaintiff. (The distinction

between the two plaintiffs does not matter on appeal so we will refer to them both as “Riverfront.”)



                                                 2
No. 19-6088, Riverfront Development, Inc., et al. v. Wepfer Marine, Inc.


The district court determined that Wepfer was fully liable and that the proper measure of damages

was restitutio in integrum—the cost of restoring Mud Island to its previous condition. The

Baltimore, 
75 U.S. 377
, 385 (1869).

        The district court held a hearing to establish the cost of repairing Mud Island. Following

the grounding, the Mississippi’s rising and falling waters had started filling the holes with

sediment. The parties disputed whether this sediment needed to be removed to restore Mud Island

to its original condition. Wepfer argued that the sediment was the same material that had built

Mud Island and that the river would naturally refill the holes. Alternatively, Wepfer contended

that it needed only to pay to fill the holes above the sediment. Riverfront, by contrast, maintained

that the accumulating sediment would not restore Mud Island to its original condition. It wanted

to excavate the sediment so that the holes could be “filled and packed by human intervention with

sand and/or limestone.” At the hearing, then, the district court needed to resolve (a) the volume

of the holes; (b) whether the sediment needed to be removed; (c) the material that should be used

to fill the holes, if any; and (d) the total cost of the repairs.

        1. Volume. The parties debated the size of the two large holes. Both sides measured the

holes within eight months of each other.

        James Reeder, a Riverfront project director with a bachelor’s degree in civil engineering,

first measured the holes in November 2016, about 16 months after the accident. Reeder explained

his process. Using a “tape measure and electronic devices,” he “divided the two gouges into five

different areas” and then “took measurements of these five parts . . . and came up with the cubic

yardage.” Reeder estimated the holes’ irregular depths by using “engineering judgment” and his

own height as a reference. Based on rounded-up measurements, he calculated the volume of the

holes as 10,000 or 10,100 cubic yards. When Reeder sought a quote for refilling the holes, he



                                                     3
No. 19-6088, Riverfront Development, Inc., et al. v. Wepfer Marine, Inc.


added a 20-percent contingency to account for “compaction” of the material. This contingency

was necessary, Reeder explained, “because a lot of times when you fill up holes, you have material

that’s not compacted and you have to buy more material than what is the volume of the hole. So

when you end up compacting it, you have to have 20 percent more material to get to the final

grade.” That resulted in a total volume of 12,000 cubic yards of fill material to fill the 10,000 or

so cubic yards of holes.

       Wepfer hired Ollar Surveying Company to measure the holes again eight months later in

July 2017. The court recognized Douglas Swink, the surveyor, as an expert in the fields of land

surveying, topographic surveys, slope analysis, and soil analysis. Swink measured the holes using

common surveyor methods. He calculated their volume as 2,792.30 cubic yards, a number that

fell more than 70 percent below Reeder’s. But all agreed that Ollar’s measurements were more or

less accurate in July 2017.

       The disparities in measurements mattered greatly to Wepfer, as they suggested the amount

of sediment accumulating in the holes. Wepfer tried to paint Reeder’s earlier tape-measure

calculations as unsophisticated and inaccurate. Even Riverfront’s expert opined that it did not

“seem very likely” that the holes could have filled with over 7,000 cubic yards of sediment in eight

months. Benny Lendermon, Riverfront’s former president and a civil engineer, also agreed that,

when he saw the holes in March 2017 (after Reeder’s measurements but before Ollar’s), it appeared

that they “had filled in very little[.]” But Riverfront’s witnesses also suggested that erosion and

“sloughing” (instability of the holes’ slopes) could account for some of the accumulation.

       2. Excavation. The parties next debated whether the accumulated sediment needed to be

removed before refilling the holes.




                                                 4
No. 19-6088, Riverfront Development, Inc., et al. v. Wepfer Marine, Inc.


       Riverfront’s witnesses testified that excavation was necessary because Mud Island is made

of sand and the sediment accumulating in the holes was “muck.” Those witnesses included Reeder;

Lendermon; and Clinton S. Willson, a professor of civil and environmental engineering. Dr.

Willson testified that Mud Island, in its present form, is largely made of sand. Around the turn of

the twentieth century, it was little more than a sand bar. But today, he explained, it is “a highly

engineered system” composed of “dredged material that was . . . placed in a way that would allow

for . . . development[.]” The dredged material was mainly “granular sand” from the bottom of the

Mississippi River.

       While Mud Island is made of sand, Riverfront’s witnesses testified that the sediment

settling in the holes was likely “muck.” They admitted that they did not test the sediment to

determine whether it was muck or sand—the most accurate way to answer the question. But they

explained why they believed it was muck. According to Dr. Willson, the Mississippi carries a

range of sediments, from “large course-grain sand, down through medium, fine, very fine sand,”

and then “down into silts and clays[.]” The heavier sand settles near the river bottom. The finer

material is no match for the Mississippi’s current and so remains afloat. The Wolf River Harbor,

by contrast, has little to no current. An eddy thus forms as the Mississippi’s current meets the

Wolf River Harbor’s stagnant water. The Wolf River Harbor’s lack of a current allows the

Mississippi River’s fine materials to settle, resulting in “more loose material”—known as

“muck”—accumulating in the harbor. Because the holes were on Mud Island’s harbor side,

Riverfront’s witnesses testified, it was highly likely that they contained the settling muck rather

than sand.

       Riverfront’s witnesses added that muck is not a suitable replacement for sand. Dr. Willson

defined muck as “typically some combination of water, mud, organic material . . . very fine



                                                5
No. 19-6088, Riverfront Development, Inc., et al. v. Wepfer Marine, Inc.


particles.” It has very little “integrity in terms of being able to step on it, in terms of loading on

top of it.” He explained that “there’s a big difference between the [structural] stability of the clay

and the stability of the sand.” Lendermon agreed, and described a riverfront development project

near Mud Island in which the builders allowed “too much silty material” to mix with the sand.

“[T]hat soft material there was creating a sliding plane that created no stability” and resulted in “a

major failure of [a] dike.”

       To dispute these points, Wepfer presented evidence that Riverfront needed to undertake no

excavation because the holes were filling with the same material used to build Mud Island. Dr.

Charles Morris, an expert in river engineering, agreed that Mud Island had been built of dredged

Mississippi River sand. But Dr. Morris believed that the sediment now filling the holes was

“mostly sand,” not muck. Because Mud Island sat on the outer side of a Mississippi River bend,

he explained, it was more likely for sand to be deposited on the island’s foot. On the bend’s inner

side, closer to Arkansas, the water travels at a slower rate. But the water on the bend’s outer side

accelerates as it travels more distance. When the water is “flowing faster,” Dr. Morris explained,

“it carries sand with it.” In Dr. Morris’s opinion, the fast-flowing water was depositing sand on

Mud Island. He did not think “human intervention” was necessary to return the holes to their

original condition

       Riverfront called Dr. Willson in rebuttal. In his view, the higher speed in the bend creates

“a corkscrew effect of the flow. So if the flow is trying to go around the bend, it’s also then

corkscrewing back under down to the bottom of the river.” That phenomenon would push the sand

away from Mud Island toward Arkansas.

       3. Materials. The parties also debated the materials that would be suitable to refill the

holes. The two options were sand ($43.50 per cubic yard) and limestone ($37 per cubic yard). In



                                                  6
No. 19-6088, Riverfront Development, Inc., et al. v. Wepfer Marine, Inc.


its pretrial brief, Riverfront requested the more expensive sand. All witnesses agreed that both

sand and limestone would be acceptable.         A Riverfront witness, Lendermon, testified that

limestone was “certainly” suitable, and that sand would be “suitable as long as you can hold it in

place.” Dr. Willson also thought that “some kind of construction-grade limestone” or “maybe

sand” would be appropriate fill materials. He could not say that “one or the other is better.” Dr.

Morris, Wepfer’s expert, believed limestone was “a sufficient material”; indeed, he testified that

limestone would make the island “much more stable” than it was before and so “would be an

enhancement to stability.”

       4. Costs. Riverfront lastly introduced the sole estimates that it had received to repair Mud

Island. Luhr Brothers, Inc., estimated a cost of $623,990 for excavating 9,208 cubic yards of

material. The company received that 9,208 number from Reeder. To calculate this number,

Reeder started with his 12,000 cubic yard estimate—an estimate that included both the size of the

holes that he had measured (about 10,000 cubic yards) and the 2,000 cubic yards worth of extra

fill material needed because of compaction. Reeder then subtracted 2,792 cubic yards—the size

of the hole that Ollar later measured in July 2017.

       The cost estimate for refilling the holes with limestone was $444,000, while the cost to

refill with sand was $522,000. These amounts were based on 22,000 tons of fill material reflecting

12,000 cubic yards—the quantity of fill that Reeder had initially calculated.

                                                 C

       The district court’s damages order awarded Riverfront “the cost of excavating and refilling

the depressions caused by Wepfer’s negligence.” It credited Riverfront’s witnesses that the

sediment filling the holes was “muck” and thus that Riverfront needed to excavate it. It noted that

Wepfer’s alternative theory that the accumulated sediment was sand did not “overwhelm[]”



                                                 7
No. 19-6088, Riverfront Development, Inc., et al. v. Wepfer Marine, Inc.


Riverfront’s “substantial evidence” to the contrary. The court next accepted Reeder’s initial

measurements as an acceptable estimate of the original size of the holes, and seemingly used

Ollar’s later measurements to conclude that the holes had filled with roughly 9,208 cubic yards of

sediment. It also found that Riverfront had established sand as an appropriate material for refilling

the holes. Finally, the court found the cost of repair to be essentially uncontradicted, and accepted

Luhr Brothers’ estimates. It entered a judgment awarding Riverfront $1,145,990 in damages.

       Wepfer filed a motion to alter or amend the judgment under Federal Rule of Civil

Procedure 59(e). The court denied the motion, concluding that it sought “a wholesale relitigation

of the case” and raised “no new arguments.”

                                                  II

       On appeal, Wepfer challenges the district court’s damages award without disputing the law

that the court applied. So we may assume (without deciding) that the court properly determined

that the correct measure of damages was the cost of restoring Mud Island to its prior condition.

The Baltimore, 
75 U.S. 377
, 385 (1869). And we may assume (without deciding) that Riverfront

needed only to prove this restoration cost “to a ‘reasonable degree of certainty.’” Nat’l Steel Corp.

v. Great Lakes Towing Co., 
574 F.2d 339
, 342 (6th Cir. 1978) (quoting Cranston Print Works Co.

v. Pub. Serv. Co. of N.C., 
291 F.2d 638
, 649 (4th Cir. 1961)).

       Instead, Wepfer challenges the district court’s factual findings. We review “findings of

fact following a bench trial in an admiralty case for clear error, construing the evidence in the light

most favorable to the appellee.” F.C. Wheat Maritime Corp. v. United States, 
663 F.3d 714
, 723

(4th Cir. 2011); ConAgra, Inc. v. Inland River Towing Co., 
252 F.3d 979
, 983 (8th Cir. 2001). We

must affirm the findings if they are “plausible in light of the entire record,” even if we might have

“weighed the evidence differently.” Harlamert v. World Finer Foods, Inc., 
489 F.3d 767
, 771 (6th



                                                  8
No. 19-6088, Riverfront Development, Inc., et al. v. Wepfer Marine, Inc.


Cir. 2007) (citing Anderson v. City of Bessemer City, 
470 U.S. 564
, 574–75 (1985)); Fed. R. Civ.

P. 52(a)(6). And we may reverse only if we are “left with the definite and firm conviction that a

mistake has been made[.]” Pearce v. United States, 
261 F.3d 643
, 647 (6th Cir. 2001) (quoting

Graves v. United States, 
872 F.2d 133
, 136 (6th Cir. 1989)).

        Wepfer alleges four factual errors. It argues that the district court: (1) wrongly estimated

the size of the holes in Mud Island; (2) mistakenly found a need to excavate the sediment out of

the holes; (3) miscalculated the amount of sediment needed to be excavated; and (4) chose the

wrong fill material. The deferential standard of review requires us to reject all but the third

argument. We find that the district court committed clear error in calculating the amount of

sediment to excavate. Wepfer also challenges the district court’s denial of its Rule 59(e) motion,

but it makes no separate argument on the merits. So our resolution of these four main issues

suffices to resolve that issue.

        1. Size of Holes. Wepfer first argues that the district court erred in crediting Reeder’s

measurements of the size of the holes in November 2016. To recap, the district court accepted

Reeder’s measurements that, as of November 2016, the holes were “roughly 10,000 cubic yards”

in size. And it accepted Reeder’s 20-percent “contingency” for additional material necessary to

compact the holes to the final grade.

        The district court’s reliance on Reeder’s measurements for the holes’ initial size suffices

to survive the clear-error standard. Reeder has a degree in engineering. Using basic tools, he took

the holes’ average widths, lengths, and depths, and calculated a volume of 10,000 or so cubic

yards. He also explained the need for a 20-percent compaction contingency when refilling the

holes. He testified that, in his judgment, the measurements were “reasonably accurate.” The




                                                 9
No. 19-6088, Riverfront Development, Inc., et al. v. Wepfer Marine, Inc.


evidence sufficed to prove the size of the holes to “a reasonable degree of certainty.” Nat’l Steel

Corp., 574 F.2d at 343
.

        Wepfer’s contrary arguments ask us to reweigh the evidence and reach a contrary

conclusion. That is not our job on appeal. See 
Harlamert, 489 F.3d at 771
. Wepfer argues that

Reeder simply “ballparked” his estimate of about 10,000 cubic yards, using unsophisticated tools

and calculations. Wepfer contrasts Reeder’s approach with Ollar’s measurements, which used

standard surveying techniques to reach a much lower estimate of 2,972 cubic yards. And Wepfer

points to evidence suggesting that it was unlikely that the holes had filled with nearly 7,000 cubic

yards of sediment between the two measurements. Yet, invoking Tennessee law for this admiralty

case, Wepfer concedes that Riverfront needed only to present “substantial evidence” to allow the

district court to make a “fair and reasonable assessment of the amount of damages.” Apt. Br. 19

(quoting Grantham & Mann, Inc. v. Am. Safety Prods., Inc., 
831 F.2d 596
, 602 (6th Cir. 1987)).

Reeder’s measurements meet that substantial-evidence requirement. While we might not have

taken the same view of the facts, we cannot say the district court’s finding was clearly erroneous.

        2. Need for Excavation. Wepfer next argues that the district court erred in crediting the

testimony from Riverfront’s witnesses that accumulated sediment must be excavated to restore

Mud Island to its original condition. There was no clear error. To begin with, both parties’

witnesses agreed that Mud Island is largely made of dredged sand. And Riverfront presented

uncontradicted evidence that river muck is not a suitable replacement for sand. So the parties

disputed only whether the sediment accumulating in the holes was sand (suitable) or muck (not

suitable).

        Riverfront presented enough evidence for the court to find that the holes were mostly filling

with muck, not sand. Dr. Willson opined as to this fact and gave a reasoned explanation why—



                                                 10
No. 19-6088, Riverfront Development, Inc., et al. v. Wepfer Marine, Inc.


because the Wolf River Harbor was mostly filled with muck and the holes were on the harbor side.

His expert opinion, rooted in his understanding of river dynamics, comported with Lendermon’s

practical experience. In Lendermon’s experience from other projects, the material in the mouth of

the Wolf River Harbor is “unsuitable” muck. The district court could rationally credit Dr.

Willson’s explanation as “persuasive” and could rationally conclude that Lendermon’s testimony

lent “further credibility” to those expert views. We treat these credibility findings with great

deference. See Fed. R. Civ. P. 52(a)(6); Madden v. Chattanooga City Wide Serv. Dep’t, 
549 F.3d 666
, 674 (6th Cir. 2008). The district court thus had “sufficient” evidence to make a “just and

reasonable” determination that the holes required excavation before refilling. Nat’l Steel 
Corp., 574 F.2d at 342
.

       Wepfer’s counterarguments lack merit. It argues that the district court’s ruling was

improperly speculative because Riverfront never tested the sediment. To be sure, Dr. Willson and

Lendermon admitted that they did not know the holes’ contents with absolute certainty. But their

opinions were far from “speculation or guesswork.” See
id. They were
rooted in understanding

of, and experience with, the Mississippi River. As Lendermon explained, there were two ways to

determine the makeup of the accumulated sediment: to test it or to know “how it got there.” While

the first approach would provide greater clarity, the second approach, on this record, was sufficient

for the district court to reach a reasonably certain conclusion. Cf. 
ConAgra, 252 F.3d at 985
.

       Wepfer next points to contrary evidence. It cites Dr. Morris’s opinion, for example. But

“when a trial judge’s finding is based on [the] decision to credit the testimony of one or two or

more witnesses, each of whom has told a coherent and facially plausible story that is not

contradicted by extrinsic evidence, that finding, if not internally inconsistent, can virtually never

be clear error.” 
Madden, 549 F.3d at 674
(quoting 
Anderson, 470 U.S. at 575
). Wepfer also cites



                                                 11
No. 19-6088, Riverfront Development, Inc., et al. v. Wepfer Marine, Inc.


the observation from Ollar’s surveyor (Swink) that the holes contained material like the

undamaged portions of Mud Island. As the district court elsewhere found, however, “collapse of

other parts of the island” could account for some of the material in the holes. The court’s

excavation finding was not clearly erroneous.

       3. Amount of Excavation. Wepfer argues that the district court erred in its calculation of

the volume of sediment to be excavated. It has a point. Recall that Reeder measured the size of

the holes as 10,000 or 10,100 cubic yards, but added a 20-percent “contingency” to account for

the extra fill material that Riverfront would need to compact the holes to grade level. When

Riverfront sought a quote for refilling the holes, it used this 12,000-cubic-yard figure. It also used

that same enhanced figure (12,000, not 10,000) when later seeking a quote for removing the

accumulated sediment from the holes. It asked Luhr Brothers to price out the excavation of 9,208

cubic yards of sediment. Riverfront reached the 9,208-cubic-yard figure by taking the difference

between Reeder’s enhanced estimate (12,000 cubic yards) and Ollar’s later measurement (2,792

cubic yards). And the district court awarded Riverfront $623,990, the cost of removing 9,208

cubic yards of material. The court clearly erred in calculating the amount to be excavated as 9,208

cubic yards.

       The error comes from accepting the 12,000 cubic yards as the baseline size of the holes for

excavation purposes, when that figure included roughly 1,900 to 2,000 extra cubic yards of

material for filling purposes. By Reeder’s own telling, the compaction contingency for filling a

hole represents “more material than what the volume of the hole indicates[.]” He later repeated

this explanation, saying that “when you fill up holes, you have material that’s not compacted and

you have to buy more material than what is the volume of the hole.” So using the compaction-

enhanced volume for excavation overestimates the actual size of the holes, which were only 10,000



                                                 12
No. 19-6088, Riverfront Development, Inc., et al. v. Wepfer Marine, Inc.


or so cubic yards by Reeder’s own telling. Reeder himself seemed to concede during cross-

examination that the compaction number should not be used to calculate the excavation number.

When Wepfer’s attorney asked him to explain why “the 20 percent compaction figure” should be

used to calculate the excavation amount, Reeder replied: “I didn’t say it would.” And Riverfront

has identified no other evidence supporting the use of this 12,000-cubic-yard figure for excavation

purposes. Given Reeder’s own explanation and the lack of other evidence, we have a “definite

and firm conviction that a mistake has been made” on this calculation. 
Pearce, 261 F.3d at 647
(quoting 
Graves, 872 F.2d at 136
).

       The true excavation volume likely should have been about 7,208 cubic yards (the “roughly

10,000 cubic yards” found by the district court, less 2,792). Ollar’s estimate included $60,000 in

fixed costs, plus variable costs based on excavation volume, with a multiplier of $61.25. See

Exhibit 25. Plugging in the new volume results in a total excavation cost of $501,490, which

would reduce the damages award by roughly $122,500. Yet the district court did not precisely

identify the actual size of the hole that Reeder measured. The court described Reeder’s estimate

as “roughly 10,000 cubic yards” based on his testimony that “I believe the number was 10,000

cubic yards, 10,100 cubic yards.” We will leave it to the district court to recalculate the proper

number on remand without the use of any compaction contingency.

       Riverfront makes no argument to justify the use of the larger 12,000-cubic-yard number.

It claims that Wepfer’s “arguments on this finding are tethered to its position that Mr. Reeder’s

volume measurements were incorrect.” Ape. Br. 29. Not so. Wepfer makes this argument

“without waiving its [separate] argument that Reeder’s volume estimate [was] so exaggerated as

to render it incredible[.]” Apt. Br. 29–30. One can fully accept that Reeder correctly calculated

the size of the hole as roughly 10,000 cubic yards in volume and also conclude that the 2,000 cubic



                                                13
No. 19-6088, Riverfront Development, Inc., et al. v. Wepfer Marine, Inc.


yards in compaction volume should not be used to calculate the excavation volume. Riverfront

also portrays the 9,208-cubic-yards figure as “consistent with all [the district court’s] other

findings,” including “that the volume of the land gouged out measured 12,000 cubic yards.” Ape.

Br. 29–30. That is mistaken. The district court found that Reeder had calculated an actual volume

of “roughly 10,000 cubic yards,” and separately allowed the 20-percent “contingency for

compression of the material.” The district court gave no explanation as to why the contingency

should also apply to determine the amount of excavation needed, and we have found no evidence

in the record that would suggest the contingency should have carried over in this way.

       4. Material to Use. The district court lastly did not clearly err in concluding that “sand

would be an appropriate material to refill the depressions.” Several witnesses testified that sand

would restore Mud Island to its original condition.

       In response, Wepfer points to evidence suggesting both that limestone was an acceptable

(or even preferable) material and that it was cheaper. But Wepfer asserts no legal argument that

Riverfront had any admiralty-based duty to mitigate damages by picking that alternative. And the

district court could reasonably require the same material that was used to create Mud Island.

       For these reasons, we reject all of Wepfer’s arguments save one. We hold that the district

court clearly erred when it calculated the excavation amount. We reverse the district court’s

judgment and remand for entry of an amended damages award consistent with this opinion.




                                                14

Source:  CourtListener

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer