Elawyers Elawyers
Washington| Change

A Squared Joint Venture v. United States, 17-835 (2020)

Court: United States Court of Federal Claims Number: 17-835 Visitors: 2
Filed: Jul. 01, 2020
Latest Update: Jul. 02, 2020
Summary: In the United States Court of Federal Claims No. 17-835C (Filed: July 1, 2020) ) A SQUARED JOINT VENTURE, ) Bid Preparation and Proposal Costs; ) Causation; Equal Access to Justice Plaintiff, ) Act; Prevailing Party ) v. ) ) THE UNITED STATES, ) ) Defendant. ) ) Joseph P. Dirik, Dallas, TX, for plaintiff. Borislav Kushnir, Civil Division, United States Department of Justice, Washington, D.C., with whom were Joseph H. Hunt, Assistant Attorney General, Robert E. Kirschman, Jr., Director, Douglas K
More
        In the United States Court of Federal Claims
                                        No. 17-835C
                                    (Filed: July 1, 2020)

                                              )
 A SQUARED JOINT VENTURE,                     )    Bid Preparation and Proposal Costs;
                                              )    Causation; Equal Access to Justice
                      Plaintiff,              )    Act; Prevailing Party
                                              )
 v.                                           )
                                              )
 THE UNITED STATES,                           )
                                              )
                      Defendant.              )
                                              )

Joseph P. Dirik, Dallas, TX, for plaintiff.

Borislav Kushnir, Civil Division, United States Department of Justice, Washington, D.C.,
with whom were Joseph H. Hunt, Assistant Attorney General, Robert E. Kirschman, Jr.,
Director, Douglas K. Mickle, Assistant Director, for defendant. Jerry L. Seemann,
National Aeronautics & Space Administration, Office of Chief Counsel, Washington,
D.C., of counsel.

                                         OPINION

FIRESTONE, Senior Judge.

       Pending before the court in this bid protest case is plaintiff A Squared Joint

Venture’s (A2JV) motion for bid preparation and proposal costs under the Tucker Act,

28 U.S.C. § 1491, and for attorney’s fees, expenses, and costs under the Equal Access to

Justice Act (EAJA), 28 U.S.C. § 2412. This case has had a long and complex history

ultimately resulting in this court upholding the National Aeronautics and Space

Administration’s (NASA) decision to cancel the procurement that forms the backdrop of

this motion. See A Squared Joint Venture v. United States, 
145 Fed. Cl. 676
, 678 (2019).
As discussed below, the court finds that A2JV is not entitled to the bid preparation and

proposal costs it incurred in connection with the cancelled procurement because A2JV

has failed to show that NASA’s legal error caused it to unnecessarily incur those costs.

In addition, because the court finds that A2JV is not a prevailing party for purposes of

EAJA, the court finds that A2JV is not entitled to attorney’s fees. For these reasons,

A2JV’s motion is DENIED.

I.     BACKGROUND

       The dispute that led to this bid protest stems from NASA’s May 1, 2011 award of

a contract for acquisition and business support services at the Marshall Space Flight

Center (ABSS1 Contract) to Al-Razaq Computing Services (Al-Razaq). See A Squared

Joint Venture v. United States, 
136 Fed. Cl. 321
, 325 (2018) (A2JV I). Near the

conclusion of the ABSS1 Contract, NASA, on February 16, 2016, issued a request for

proposals for a follow-on acquisition and business support services contract (ABSS2

RFP), which NASA planned as a set-aside for women owned small businesses.
Id. Al- Razaq
and another company, Adventus Technologies, Inc., created A2JV to submit a

proposal in response to the ABSS2 RFP.
Id. A2JV submitted
a timely proposal on

March 18, 2016.
Id. at 326.
       On May 9, 2016, NASA “disqualified [A2JV’s proposal] because of a significant

potential [organizational conflict of interest (OCI)] that tainted the integrity of the ABSS2

competition.”
Id. NASA disqualified
A2JV’s proposal because: (1) Al-Razaq employees

who worked on A2JV’s proposal “had access to commercial and financial information

that was confidential and contained information that could have given A2JV an unfair

                                             2
competitive advantage,” and (2) Al-Razaq failed to comply with “a contractual

requirement in the ABSS1 [C]ontract to screen future work for OCI and disclose any

identified or potential OCI to NASA.”
Id. at 326-27.
       On June 20, 2017, A2JV challenged in this court NASA’s disqualification

decision. See Compl., ECF No. 1. The court initially upheld NASA’s OCI

disqualification decision, concluding based on the record provided that Al-Razaq’s

program managers had access to sensitive information in files maintained by Al-Razaq,

which included information relevant to an A2JV competitor. A2JV 
I, 136 Fed. Cl. at 330
-

31. When the court learned from briefing on A2JV’s motion for reconsideration that Al-

Razaq managers did not have the right to access any of the files with sensitive

information regarding potential A2JV competitors, the court granted reconsideration. A

Squared Joint Venture v. United States, No. 17-835C, 
2018 WL 2016632
, at *1 (Fed. Cl.

May 1, 2018) (A2JV II). The court remanded the OCI issue back to NASA “to ensure

there are ‘hard facts’ to support the [contracting officer’s] disqualification of A2JV” on

OCI grounds.
Id. On remand,
NASA’s contracting officer conducted “an independent review of the

ABSS1 [C]ontract files” and concluded that Al-Razaq employees, while not authorized to

examine certain files, “could by virtue of location access hard copies of contract files co-

located with NASA employees overseeing contracts of potential A2JV competitors.”

Nov. 29, 2018 Order at 3-4, ECF No. 104. The court found that this explanation was “not

sufficient to support NASA’s decision to disqualify A2JV from the competition.”
Id. at 4.
The court held that Al-Razaq’s mere ability to access confidential, competition-

                                             3
sensitive information based on location did not establish the “hard facts” necessary for a

finding of significant potential OCI. See
id. at 8-10.
       The government moved for reconsideration, arguing, inter alia, that the “hard

facts” standard did not apply to an agency’s OCI determination and that the court

improperly held that the mere appearance of impropriety was insufficient to find

significant potential OCI. See Def.’s Mot. for Recons., ECF No. 106. The court denied

in relevant part the government’s motion. Dec. 21, 2018 Order, ECF No. 113. The court

then instructed the parties to brief the propriety and scope of injunctive relief.
Id. at 12.
       The parties did not, however, have an opportunity to submit any briefing on

injunctive relief. On March 12, 2019, NASA formally decided to cancel the ABSS2

solicitation in favor of a longstanding centralized procurement strategy. A Squared Joint

Venture v. United States, 
145 Fed. Cl. 676
, 679 (2019) (A2JV III). A2JV challenged the

cancellation decision in an amended complaint.
Id. at 680.
After briefing, the court

upheld NASA’s cancellation decision. See
id. at 681-84.
The court also rejected A2JV’s

claim that NASA cancelled the ABSS2 procurement to avoid an adverse decision in this

case, finding instead that “a number of events other than this litigation, including

unrelated GAO protests and a partial government shutdown, created a need to review the

ABSS2 procurement.”
Id. at 684.
       Thereafter, the court denied A2JV’s motion to reconsider the court’s opinion

upholding the cancellation decision. See A Squared Joint Venture v. United States, 
146 Fed. Cl. 705
, 713 (2020) (A2JV IV). The court, however, held that the case should not be

closed, and that “A2JV be permitted to pursue bid preparation costs based on [NASA’s

                                               4
earlier] disqualification decision.”
Id. at 712.
This was because the court, before

determining whether the cancellation decision was proper, had held that the cancellation

decision had not mooted A2JV’s claims for declaratory relief based on the

disqualification decision. Specifically, the court held that A2JV “still ha[d] a claim for

bid preparation costs” based on the disqualification decision, and that the effect of the

cancellation decision on the declaratory claims was still uncertain at that stage of the

case. See A Squared Joint Venture v. United States, No. 17-835C, 
2019 WL 2591205
, at

*3 (Fed. Cl. June 24, 2019). The court stated that any relief that should be issued with

regard to the disqualification decision would be dealt with after the court determined

whether the cancellation decision was justified. See A2JV 
IV, 146 Fed. Cl. at 712
.

       Accordingly, A2JV filed the pending motion for bid preparation and proposal

costs, as well as for attorney’s fees, expenses, and costs under EAJA,1 on March 2, 2020.

Pl.’s Mot. at 1, ECF No. 175. A2JV argues that it is entitled to bid preparation and

proposal costs and attorney’s fees because it obtained “some of the relief it sought in this

matter that materially altered the legal relationship between the parties,” in light of the

court’s declaratory ruling that NASA’s disqualification decision was arbitrary and

capricious.
Id. at 1,
8, 13-14.




1
  On February 4, 2020, the court set a schedule for A2JV’s motion for bid preparation and
proposal costs “and/or attorney’s fees under 28 U.S.C. § 2412.” Order at 2, ECF No. 172.
Applications for EAJA fees have been considered by this court as premature when they are filed
prior to a final judgment. See Heger v. United States, 
114 Fed. Cl. 204
, 208 (2014). However,
given the court’s invitation in the February 4, 2020 scheduling order and no objection regarding
timeliness from the government, the court considers A2JV’s EAJA application as one for interim
EAJA fees, and will address it. See
id. at 209
(discussing the availability of interim fees).
                                               5
       In response, the government argues that A2JV is not entitled to bid preparation

and proposal costs because NASA’s legal error – the disqualification decision – did not

cause A2JV’s ultimate inability to become an awardee. Def.’s Resp. at 5-10, ECF No.

176. The government further contends that most of A2JV’s claimed bid preparation and

proposal costs are not reasonable, and some are not allowable.
Id. at 10-17.
Finally, the

government argues that A2JV is not entitled to attorney’s fees because A2JV is not a

prevailing party and the government’s position regarding A2JV’s disqualification was

substantially justified.
Id. at 18-23.
       In reply, A2JV argues that this court recognized that A2JV had been prejudiced

despite the cancellation and that A2JV need not show that it could have become an

awardee to qualify for bid preparation and proposal costs. Pl.’s Reply at 2-5, ECF No.

179. A2JV further contends that its costs are reasonable and allocable.
Id. at 8-12.
Finally, A2JV reiterates that is entitled to recover attorney’s fees because it is a

prevailing party and because the government’s position was not substantially justified.
Id. at 12-16.
II.    DISCUSSION

       The court first turns to A2JV’s request for bid preparation and proposal costs, and

then to the request for attorney’s fees and costs. For the reasons that follow, the court

denies both.




                                               6
       A.     A2JV Is Not Entitled to Bid Preparation and Proposal Costs Because
              the Disqualification Decision Did Not Cause A2JV’s Ultimate Inability
              to Become an Awardee

       Under the Tucker Act, this court in bid protest cases “may award any relief that

the court considers proper . . . except that any monetary relief shall be limited to bid

preparation and proposal costs.” 28 U.S.C. § 1491(b)(2). “Bid preparation and proposal

costs in essence are damages awarded to a protestor to provide relief for its wasted efforts

in bidding on an unfair, erroneous, or illegal procurement.” Q Integrated Cos., LLC v.

United States, 
132 Fed. Cl. 638
, 642 (2017). Bid preparation and proposal costs “are

recoverable only if three conditions are satisfied: (i) the agency has committed a

prejudicial error in conducting the procurement; (ii) that error caused the protester to

incur unnecessarily bid preparation and proposal costs; and (iii) the costs to be recovered

are both reasonable and allocable, i.e., incurred specifically for the contract in question.”

Reema Consulting Servs., Inc. v. United States, 
107 Fed. Cl. 519
, 532 (2012). The

protestor “bears the burden of proving that it is entitled to recover its costs.” Q Integrated

Cos., LLC v. United States, 
133 Fed. Cl. 479
, 485 (2017).

       Applying these standards, the court agrees with the government, Def.’s Resp. at 5-

10, that A2JV is not entitled to bid preparation and proposal costs. To recover bid

preparation and proposal costs, a protestor must demonstrate that the agency’s prejudicial

error “caused the protester to incur unnecessarily bid preparation and proposal costs.”

Reema, 107 Fed. Cl. at 532
. This causation prong operates to “place the [protestor] in the

position he or she would have occupied but for defendant’s wrong.”
Id. (internal quotation
omitted). If these costs were “not rendered a needless expense by defendant’s

                                              7
erroneous conduct, but rather were lost due to” some other reason, the bid preparation

and proposal costs are not recoverable.
Id. at 533
(internal quotations and citations

omitted); see also Hyperion, Inc. v. United States, 
120 Fed. Cl. 504
, 507-08 (2015)

(holding that the protestor was not entitled to bid preparation and proposal costs where

the protestor’s successful challenge resulted in the set-aside of the initial award, but

where the protestor was then unable to re-compete due to a proper decision to cancel the

solicitation and re-procure the services through a sole-source award).

       Here, this court held that NASA acted arbitrarily and capriciously in disqualifying

A2JV’s proposal. See Feb. 4, 2020 Order at 1 (noting that A2JV’s requests for

declaratory relief that the disqualification decision was arbitrary, capricious, and not in

accordance with law had been granted). But this disqualification is not the reason for

A2JV’s inability to become an awardee of the ABSS2 contract. Rather, NASA’s

reasonable decision to cancel the ABSS2 competition altogether after delays caused by

other protests and a change in NASA policy caused A2JV’s inability to become an

awardee of the ABSS2 contract. See A2JV 
III, 145 Fed. Cl. at 681-84
. These reasons for

the cancellation had nothing to do with A2JV’s challenge to its disqualification. A2JV

has thus failed to establish a causal link between NASA’s legal error – the

disqualification decision – and A2JV’s eventual inability to get a contract. See 
Reema, 107 Fed. Cl. at 532
-33. In other words, the disqualification decision was not the cause of

A2JV unnecessarily incurring its bid preparation and proposal costs; ultimately, NASA’s

proper cancellation decision was the cause, and A2JV would have lost its bid preparation



                                              8
and proposal costs even if NASA had not disqualified A2JV. A2JV is thus not entitled to

the bid preparation and proposal costs it seeks.

       In this connection, it is important to remember that A2JV was not the only offeror

who unsuccessfully competed for an ABSS2 contract. NASA received twenty proposals

in response to the solicitation. A2JV 
III, 145 Fed. Cl. at 678
. Several of these were in the

competitive range, but, just like A2JV, these companies will not be awarded an ABSS2

contract. Id.; see E.W. Bliss Co. v. United States, 
77 F.3d 445
, 447 (Fed. Cir. 1996)

(“Proposal preparation expenses are a cost of doing business that normally are lost when

the effort to obtain the contract does not bear fruit.” (internal quotations and citations

omitted)). Awarding A2JV bid preparation and proposal costs would provide A2JV a

substantial windfall that other offerors cannot obtain.

       A2JV’s arguments to the contrary are not persuasive. A2JV appears to argue that

it was prejudiced by the agency’s cancellation decision. See Pl.’s Reply at 6 (arguing that

“here,” the court found that A2JV “was prejudiced by the agency’s cancellation

decision”). However, the court did not determine that NASA committed a prejudicial

error in cancelling the solicitation. Rather, the court found NASA’s cancellation decision

reasonable. A2JV 
III, 145 Fed. Cl. at 681-84
. Moreover, the court further held that

NASA’s proper cancellation decision was unrelated to the disqualification error.
Id. at 684;
see also Def.’s Resp. at 8 & n.2.

       With this in mind, the cases A2JV relies on to claim bid preparation and proposal

costs are inapposite. First, A2JV cites Innovation Development Enterprises of America,

Inc. v. United States, 
114 Fed. Cl. 213
, 216 (2014) to demonstrate that it has established

                                              9
the causal link between NASA’s legal error and its bid preparation and proposal costs.

Pl.’s Reply at 4. In Innovation Development, the protestor alleged that the agency had

acted unreasonably when it awarded a sole-source bridge contract to the incumbent

contractor, rather than conducting a competitive procurement on which the protestor

could have bid. Innovation Dev. Enters. of America, Inc. v. United States, 
108 Fed. Cl. 711
, 720-21 (2013). This court agreed with the protestor and held that the agency had

acted arbitrarily and capriciously in awarding the sole-source contract.
Id. at 727.
Despite the fact that the sole-source contract had already been fully performed by the

time the court had issued its opinion, the court determined that the matter was not moot

because, although the protestor could not obtain injunctive or declaratory relief, the

protestor could still recover bid preparation and proposal costs.
Id. at 724.
       Relying on Innovation Development, A2JV argues that this court may award “bid

preparation and proposal costs when, after a finding of the agency’s legal error, a

protestor cannot become an awardee” for a reason other than that error. Pl.’s Reply at 4.

However, in making this argument, A2JV misconstrues the decision in Innovation

Development. The legal error in Innovation Development – the improper sole-source

award – caused the protestor to lose its bid preparation and proposal costs.2 Here,

NASA’s justified cancellation decision ultimately caused A2JV to unnecessarily incur its

bid preparation and proposal costs, not NASA’s erroneous disqualification decision.



2
 The protestor in Innovation Development was ultimately denied bid preparation and proposal
costs because no draft proposal was ever prepared by the protestor or submitted to the 
agency. 114 Fed. Cl. at 222
.
                                               10
       Second, A2JV cites Klinge Corp. v. United States, 
82 Fed. Cl. 127
(2008) (Klinge

I) and Klinge Corp. v. United States, 
83 Fed. Cl. 773
(2008) (Klinge II) in support of its

position. Pl.’s Reply at 5. In Klinge I, the protestor succeeded in its challenge to the

agency’s indefinite delivery, indefinite quantity contract (IDIQ) solicitation, and this

court enjoined performance under the IDIQ 
contract. 82 Fed. Cl. at 139
. Following the

injunction, the agency recompeted the contract under the Federal Supply Schedule (FSS),

for which the protestor was not eligible to compete. Klinge 
II, 83 Fed. Cl. at 774-75
.

The protestor challenged the FSS solicitation, seeking to enjoin the FSS solicitation on

the grounds that the agency had improperly cancelled the original IDIQ solicitation.
Id. at 774.
The court found that there was “prejudicial error in the agency’s de facto

cancellation of the first [IDIQ] procurement.” Id.; see
id. at 779-80
(explaining that the

agency erred in determining that it could not consider the protestor’s proposal under the

original solicitation and therefore initiated the FSS solicitation). However, the court

declined to enjoin the FSS solicitation, which was “otherwise unimpeached.”
Id. at 780.
Instead, the court awarded the protestor bid preparation and proposal costs in connection

with its challenge to the IDIQ solicitation because the injunctive relief the protestor was

awarded in the IDIQ challenge had been made irrelevant by the erroneous cancellation

decision. Id.; see also Klinge Corp. v. United States, 
87 Fed. Cl. 473
, 474 (2009).

       A2JV argues that Klinge I and Klinge II demonstrate that this court has awarded

bid preparation and proposal costs “when, after a finding of the agency’s legal error, the

agency cancelled the procurement and the successful protestor was not returned to the

position he or she would have occupied but for the defendant’s wrong.” Pl.’s Reply at 5

                                             11
(internal quotation omitted). However, A2JV again fails to recognize that a legal error

caused protestor to lose its bid preparation and proposal costs. In Klinge I and Klinge II,

the court not only determined that the agency had erred in conducting the IDIQ

solicitation, but the agency also committed prejudicial error when it cancelled that

solicitation. Ultimately, the Klinge court determined that the prejudicial cancellation

error warranted an award of bid preparation and proposal costs, because the previously-

awarded injunctive relief was no longer available. Klinge 
II, 83 Fed. Cl. at 474
.

       In contrast, here, the court determined that NASA did not err in cancelling the

solicitation at issue, nor did the court previously award A2JV injunctive relief based on

the disqualification decision; in fact, the agency had properly cancelled the solicitation

before injunctive relief could be considered. A2JV has not shown that NASA’s error –

the disqualification decision – was the cause of its unnecessarily incurred bid preparation

and proposal costs. A2JV’s motion for bid preparation and proposal costs is therefore

denied.

       B.     A2JV is Not Entitled to Attorney’s Fees and Costs Because A2JV is Not
              a Prevailing Party

       EAJA provides that “a court shall award to a prevailing party other than the United

States fees and other expenses . . . incurred by that party in any civil action . . . brought

by or against the United States in any court having jurisdiction of that action, unless the

court finds that the position of the United States was substantially justified or that special

circumstances make an award unjust.” 28 U.S.C. § 2412(d)(1)(A). EAJA also provides

for the award of certain costs to a “prevailing party.”
Id. § 2412(a).
“The essential


                                              12
objective of the EAJA is to ensure that persons will not be deterred from seeking review

of, or defending against, unjustified governmental action because of the expense involved

in the vindication of their rights.” Kelly v. Nicholson, 
463 F.3d 1349
, 1353 (Fed. Cir.

2006) (alterations and quotations omitted).

       “To recover an award under EAJA, the applicant must prove that it was the

prevailing party in the underlying action.” Impresa Construzioni Geom. Domenico

Garufi v. United States, 
100 Fed. Cl. 750
, 759 (2011) (internal quotations omitted). The

term “prevailing party,” as it appears in EAJA, “means a party that obtains a ‘material

alteration of the legal relationship of the parties.’” Dellew Corp. v. United States, 
855 F.3d 1375
, 1379 (Fed. Cir. 2017) (quoting Buckhannon Bd. & Care Home, Inc. v. W. Va.

Dep’t of Health & Human Res., 
532 U.S. 598
, 604 (2001)). Such a change in the parties’

legal relationship “must have a certain judicial imprimatur, such as an enforceable

judgment on the merits or a court-ordered consent decree.” Dellew 
Corp., 855 F.3d at 1379-80
(internal quotations and alterations omitted).

       An award of declaratory relief may confer prevailing party status. See Lefemine v.

Wideman, 
568 U.S. 1
, 4 (2012). However, declaratory relief is insufficient where it does

not “affect[] the behavior of the defendant toward the plaintiff.” Rhodes v. Stewart, 
488 U.S. 1
, 4 (1988) (per curiam); see also Tx. State Teachers Ass’n. v. Garland Indep. Sch.

Dist., 
489 U.S. 782
, 792 (1989). The declaratory relief must “modify[] the defendant’s

behavior in a way that directly benefits the plaintiff.” 
Lefemine, 568 U.S. at 4
.

       Applying these standards, the court concludes that A2JV has not demonstrated that

it is a prevailing party under EAJA, and that, therefore, A2JV’s motion for attorney’s

                                              13
fees, expenses, and costs must be denied. As an initial matter, it is undisputed that A2JV

has not obtained injunctive relief or money damages in this case, which “will usually

satisfy” the prevailing party test.
Id. In fact,
following NASA’s cancellation decision,

the court dismissed as moot A2JV’s prayers for injunctive relief seeking to reinstate the

ABSS2 solicitation. See A Squared Joint Venture, 
2019 WL 2591205
, at *3 (dismissing

the eighth and ninth prayers for relief in A2JV’s third amended complaint); Innovation

Dev. Enter. of Am., Inc. v. United States, 600 F. App’x 743, 747 (Fed. Cir. 2015)

(unpublished) (holding that a protestor who “did not receive an injunction and recovered

no money damages” cannot qualify as a prevailing party under EAJA).

       Instead, A2JV relies on the court’s ruling in its favor as to NASA’s

disqualification decision, granting A2JV declaratory relief that the decision was arbitrary,

capricious, and not in accordance with law. Nov. 29, 2018 Order, ECF No. 104 (holding

in A2JV’s favor); Dec. 21, 2018 Order, ECF No. 113 (denying in relevant part

reconsideration and directing the parties to brief the propriety and scope of injunctive

relief); Feb. 4, 2020 Order, ECF No. 172 (noting that A2JV’s requests for declaratory

relief that the disqualification decision was arbitrary, capricious, and not in accordance

with law had been granted). However, as discussed above, declaratory relief is only

sufficient to confer prevailing party status if that relief materially alters the legal

relationship between the parties. See Dellew 
Corp., 855 F.3d at 1379
; 
Lefemine, 568 U.S. at 4
. Here, the court agrees with the government, Def.’s Resp. at 18-21, that under the

circumstances of this case, the court’s holding that NASA’s disqualification decision was

arbitrary and capricious is insufficient to satisfy the prevailing party test.

                                               14
       To begin, A2JV has not shown that NASA took any action that directly benefited

A2JV based on the court’s legal holding. Although the court asked the parties to brief

whether injunctive relief should be granted, the parties never had that opportunity

because, for reasons unrelated to A2JV’s challenge, the court found that NASA had

properly cancelled the solicitation. In such circumstances, A2JV’s claim for injunctive

relief became moot. See A Squared Joint Venture, 
2019 WL 2591205
, at *3. Moreover,

although the court declined to hold that A2JV’s claims for declaratory relief were moot

because “A2JV still has a claim for bid preparation costs” and other relief depending on

the outcome of the cancellation decision, see
id., the court
has now upheld the

cancellation and has declined to award A2JV bid preparation and proposal costs. A2JV

therefore cannot demonstrate that any direct action has been taken or monetary relief

awarded that is associated with the declaratory relief granted by the court.

       Instead, in its motion, A2JV claims that the court’s ruling that the disqualification

decision was arbitrary may alter the parties’ relationship in the future because “[t]here

can be no doubt that if the joint venture were to again bid on a NASA opportunity, that

NASA could not ignore the rulings of this [c]ourt.” Pl.’s Mot. at 14. However, as the

government argues, A2JV’s assertion is speculative and cannot support a finding that the

parties’ legal relationship changed based on the granted declaratory relief. Def.’s Resp.

at 20-21. A2JV does not show that NASA intends to, in the future, solicit services on

which A2JV will bid or that the factual situation that led to A2JV’s disqualification

would arise again in that future solicitation. Because A2JV has not shown that the

court’s declaratory relief “modified the defendant’s behavior in a way that directly

                                             15
benefits” A2JV, 
Lefemine, 568 U.S. at 4
, A2JV has failed to demonstrate that it is a

prevailing party under EAJA.

       The two cases A2JV relies on, Infiniti Information Solutions, LLC v. United States,

94 Fed. Cl. 740
(2010) and Naplesyacht.com v. United States, No. 04-252C, 
2005 WL 6112642
(Fed. Cl. Mar. 31, 2005), do not show otherwise. Pl.’s Reply at 13-14. It is true

that in both of these cases, declaratory relief was found to convey prevailing party status.

Infiniti, 94 Fed. Cl. at 747-48
; Naplesyacht, 
2005 WL 6112642
, at *8. However, in both

cases, the protestor was able to show that the declaratory relief granted changed the legal

relationship between the parties. In Infiniti Information, the court issued declaratory

relief that affirmatively “set aside” the relevant 
contract. 94 Fed. Cl. at 747-48
. And in

Naplesyacht.com, the court determined that the declaratory relief it had ordered “was

designed to prevent abuse on future contracts for which plaintiff may compete,” and the

court also awarded bid preparation and proposal costs. 
2005 WL 6112642
, at *8.

       In contrast, A2JV here obtained only a declaration that NASA’s disqualification

decision was arbitrary and capricious. That decision, however, became irrelevant once

that court determined that NASA was justified for wholly separate reasons to cancel the

ABSS2 procurement. Because of the justified cancellation decision, the court’s earlier

declaratory judgment did not ultimately alter the legal relationship between the parties.

Cf. 
Rhodes, 488 U.S. at 4
(holding that a plaintiff who obtains a formal declaratory

judgment but gains no real “relief whatsoever” is not a prevailing party). For these

reasons, A2JV has not demonstrated that it is a prevailing party, and its motion for

attorney’s fees, expenses, and costs under EAJA must be denied.

                                             16
III.   CONCLUSION

       Based on the foregoing, A2JV’s motion for bid preparation and proposal costs and

for attorney’s fees, ECF No. 175, is DENIED.

       Pursuant to the court’s November 18, 2019 opinion denying A2JV’s motion for

judgment on the administrative record and granting the government’s cross motion for

judgment on the administrative record, ECF No. 153, and pursuant to this opinion

denying A2JV’s motion for bid preparation and proposal costs, the Clerk is directed to

enter judgment in favor of the government.

       IT IS SO ORDERED.



                                                         s/Nancy B. Firestone
                                                         NANCY B. FIRESTONE
                                                         Senior Judge




                                             17

Source:  CourtListener

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer