Petitioner: FLORIDA BOARD OF PROFESSIONAL ENGINEERS
Respondent: THOMAS PLOTTS, P.E.
Judges: J. LAWRENCE JOHNSTON
Agency: Department of Business and Professional Regulation
Locations: Tampa, Florida
Filed: Jul. 24, 2012
Status: Closed
Settled and/or Dismissed prior to entry of RO/FO on Tuesday, August 21, 2012.
Latest Update: Nov. 15, 2024
Deputy Agency Clerk
STATE OF FLORIDA CLERK —_Evelte Lawson-Prootor
FLORIDA BOARD OF PROFESSIONAL ENGINEERS Dee =» §/18/2012
File #
FLORIDA BOARD OF PROFESSIONAL
ENGINEERS,
Petitioner,
v. FEMC Case No. 2011055019
THOMAS D. PLOTTS, P.E., FILED
; Florida Engineers Management
Respondent, Corporation
eed MAY 18 2012
ADMINISTRATIVE COMPLAINT Clerk: Sandee Waige
COMES NOW the Florida Engineers Management Corporation (FEMC) on behalf of
Petitioner, Florida Board of Professional Engineers, hereinafter referred to as “Petitioner,” and
files this Administrative Complaint against THOMAS PLOTTS, P.E., hereinafter referred to as
“Respondent”. This Administrative Complaint is issued pursuant to Sections 120.60 and
471.038, Florida Statutes. Any proceeding concerning this complaint shall be conducted
pursuant to Section 120.57, Florida Statutes. In support of this complaint, Petitioner alleges the
following:
1. Petitioner, Florida Board of Professional Engineers, is charged with regulating the
practice of engineering pursuant to Chapter 455, Florida Statutes, This complaint is filed by the
Florida Engineers Management Corporation (FEMC) on behalf of Petitioner. FEMC is charged
with providing administrative, investigative, and prosecutorial services to the Florida Board of
“Professional Engineers pursuant to Section 471.038, Florida Statutes (1997).
2. Respondent is, and has been at all times material hereto, a licensed professional
engineer in the State of Florida, having been issued license number PE 66075. Respondent's last
known address is 4711 34th Street North, Suite G, St. Petersburg, FL 33714.
3. On August 24, 2011 Respondent sealed, signed and dated three pages of
engineering design documents (Sheets A-l, A-2 and A-3) for an aluminum swimming pool
screen enclosure structure to be located at 358 NE 155" Street, Citra, Fl (Waldron Project).
4. Respondent’s engineering documents (Sheets A-1, A-2 and A-3) for the Waldron
Project are materially deficient by failing to comply with Sections 106.1.1 and 1603.1 of the
2007 Florida Building Code (FBC) and Rule 61G15-30.003(1) and 61G15-31.002(5) as follows:
A. The connection for the ends of the diagonal roof bracing elements is not detailed
in the permit drawing.
5. Respondent failed to design the elements of the subject screen enclosure in
accordance with the strength requirements of Section 1604.2 of the 2007 FBC as follows:
A. Stresses resulting from the application of code prescribed design loading in the
2x4SMB post elements significantly exceed the allowable stresses for the elements as
determined in accordance with the Aluminum Design Manual - Part 1A.
B. Stresses resulting from the application of code prescribed design loading in the
2x3 Hollow diagonal brace elements significantly exceed the allowable stresses for the elements
as determined in accordance with the Aluminum Design Manual - Part 1A.
Cc. Stresses resulting from the application of code prescribed design loading in the
2x3 Hollow roof purlin elements significantly exceed the allowable stresses for the elements as
determined in accordance with the Aluminum Design Manual - Part 1A.
BPE vs. Thomas Plots, P.E., Case No, 2011055019
D. Stresses resulting from the application of code prescribed design loading in the
2x2 Hollow eve rail elements significantly exceed the allowable stresses for the elements as
determined in accordance with the Aluminum Design Manual - Part 1A.
E. The force resulting from the application of code prescribed design loading to the
1/8" diameter cable brace elements significantly exceed the breaking strength of the cable.
6. The Board has adopted Responsibility Rules of Professional Enginecrs
(Responsibility Rules). These Rules are contained in Chapter 61G15-30 to Chapter 61G15-36,
Fla. Administrative Code. Professional Engineers who perform services covered by the
Responsibility Rules are required to comply with the Rulcs.
7. Rule 61G15-30.002(1), F. A. C., mandates that Respondest, as the structural
engineer of record, is professionally responsible for the documents (Sheets A-1, A-2, A-3)
prepared for the Waldron Project. As such, Respondent is responsible for producing a document
that complies with the applicable portions of the Responsibility Rules.
8. Respondent acted as Engineer of Record for the Structure for the Waldron
Project as that term is defined in Rule 61G15-31.002(1), F. A. C. As such all structural
documents prepared, signed, sealed and dated by Respondent must contain the information set
out in Rule 61G15-31.002(5), F. A. C., as is mandated by Rule 61G1 5-31.001, F. A. C., setting
out the General Responsibility standards for engineers designing structures. The structural
document for the Waldron Project fails to contain this information and thus fail to comply with
the Responsibility Rules. :
9. Section 471.033(1)(g), Florida Statutes, provides that an engineer is subject to
discipline for engaging in negligence in the practice of engineering. Rule 61G15-19.001(4), F. A.
C., provides that negligence constitutes “failure by a professional engincer to utilize due care in
FBPE vs. Thomas Plotts, P.E,, Case No, 201 1055019
performing in an engineering capacity or failing to have due regard for acceptable standards of
engineering principles.”
10. Rule 61G15-19.001(4) also provides that “[fJailure to comply with the procedures
set forth in the Responsibility Rules as adopted by the Board of Professional Engineers shall be
considered as non-compliance with this section unless the deviation or departures therefrom are
justified by the specific circumstances of the project in question and the sound professional
judgment of the professional engineer.”
11. The Respondent’s drawings (Sheets A-1-A-3) for the Waldron Project contain
deficiencies including; but not limited to, those set forth in Paragraphs 4 and 5. Respondent
violated the provisions of Section 471.033(1)(g), Florida Statutes, and Rule 61G15-19.001(4), F.
A.C., by sealing, signing and dating engineering documents that were issued and filed for public
record when such documents were materially deficient in respect to and not in compliance with
applicable code requirements or acceptable engineering principles.
12. Based on the foregoing, Respondent is charged with violating Section
471.033(1)(g), Florida Statutes, and Rule 61G15-19.001(4), F. A. C., by being negligent in the
practice of engineering.
WHEREFORE, the Petitioner respectfully requests the Board of Professional Engineers
to enter an order imposing one or more of the following penalties: permanent revocation or
suspension of the Respondent’s license, restriction of the Respondent’s practice, imposition of an
administrative fine, issuance of a reprimand, placement of the Respondent on probation, the
assessment of costs related to the investigation and prosecution of this casc, other than costs
associated with an attorney’s time, as provided for in Section 455,227(3), Florida Statutes, and/or
any other relief that the Board deems appropriate.
FBPE vs. Thomas Plotts, P.E., Case No. 2011055019
SIGNED this k gr b say ot
2012,
Zana Raybon
Executive Director
BYP Join J. Rimes, Tl
Chief Prosecuting Attorney
COUNSEL FOR FEMC:
John J. Rimes, [I
Prosecuting Attorney
Florida Engineers Management Corporation
2639 North Monroe Street, Suite B-412
Tallahassee, Florida 32303
Florida Bar No. 212008
JR/sm
PCP DATE: May 15, 2012
PCP Members: Charland & Hahn
Thereby certify that a copy of the foregoing was furnished to Mr. Thomas D. Plotts, P.E., 4711
34" Strect North, Suite G, St. Petersburg, Florida 33714 and 34 Ccdar Falls Drive, Apollo,
Florida 33572, by certified mail, on th
FIDE vs. Thonms Plots, PE, Case No, 2011055029
Docket for Case No: 12-002523PL
Issue Date |
Proceedings |
Aug. 21, 2012 |
Order Closing Files and Relinquishing Jurisdiction. CASE CLOSED.
|
Aug. 20, 2012 |
Joint Motion to Cancel Hearing and Close File filed.
|
Aug. 03, 2012 |
Order of Pre-hearing Instructions.
|
Aug. 03, 2012 |
Notice of Hearing by Video Teleconference (hearing set for September 26, 2012; 9:00 a.m.; Tampa and Tallahassee, FL).
|
Aug. 03, 2012 |
Order of Consolidation (DOAH Case Nos. 12-2523PL and 12-2526PL).
|
Jul. 31, 2012 |
Unilateral Response to Initial Order filed.
|
Jul. 31, 2012 |
Unilateral Response to Initial Order filed.
|
Jul. 25, 2012 |
Initial Order.
|
Jul. 24, 2012 |
Petition for Formal Administrative Hearing filed.
|
Jul. 24, 2012 |
Election of Rights filed.
|
Jul. 24, 2012 |
Administrative Complaint filed.
|
Jul. 24, 2012 |
Agency referral filed.
|