KRISTI K. DUBOSE, District Judge.
This action is before the Court on the motion for partial summary judgment filed by defendant Continental Casualty Company (Continental) and documents in support (doc. 135), the response in opposition filed by plaintiff Karen Weldin Stewart, CIR-MI, Insurance Commissioner of the State of Delaware (the Commissioner) (docs. 137, 138) and Continental's reply (doc. 146).
Elkins Constructors, Inc. had a contract with the University of South Alabama on a public works construction project to build a dormitory. Continental issued the payment bond for Elkins on the project. In July 2010, Elkins entered into a subcontract with Coltin Electric, Inc. (Coltin) for electrical work. Elkins failed to pay Coltin for certain materials, equipment, and labor on the project. On May 25, 2012, Coltin submitted a Claim for Additional Compensation against Elkins' Payment Bond. (Doc. 135-2, Affidavit of David Birklebach, Elkins Project Manager; Doc. 135-3, Claim) The parties were unable to resolve the dispute and this action was filed on August 22, 2012 (Doc. 1).
In the complaint, Coltin brought one claim against Elkins' payment bond with Continental. Coltin seeks damages for labor productivity losses in its field work on the project. Coltin attributes those losses to Elkins' mismanagement of the scheduling of sub-contractors and suppliers and its changes to schedules, including instituting a 24-hour schedule, in order to complete the project on time. Coltin alleges that it had to hire additional employees and perform additional work in order to accelerate and complete its work.
Coltin states that it began to accrue the labor productivity losses upon receipt of the amended project schedule on November 16, 2010. (Doc. 1; Doc. 135-1, p. 7) Coltin alleges that it also performed additional work that was beyond the scope of the base contract. Coltin seeks payment of "at least" $804,827.63 against Elkins' bond with Continental.
Continental answered the complaint and counterclaimed against Coltin. (Doc. 132) Continental alleges that Mathes Electric Supply Company, Inc. and Mayer Electric Supply Company, Inc. provided materials to Coltin for the project, Coltin did not pay the suppliers, and they filed a claim and a lawsuit against Continental and other parties for payment for the materials. Continental seeks indemnification for these claims and all costs, damages, expenses and attorney's fees arising from the defense and resolution of these claims, based upon the indemnification and hold harmless provision of the subcontract between Coltin and Elkins.
Ullico Casualty Company provided the project bond for Coltin. Coltin agreed to indemnify Ullico against any claims, and as security assigned its claims against third parties relating to a bonded contract. After Coltin filed this lawsuit Ullico went into receivership in the state of Delaware and the Commissioner was appointed as the Receiver. The Commissioner exercised Ullico's right to Coltin's claims against Elkins' bond and moved for substitution. The motion was granted and the Commissioner was substituted for Coltin. (Doc. 66)
During the course of the project, beginning in August 2010, Coltin submitted monthly "Subcontractor's Applications and Certificates of Payment", (payment applications) to Elkins. Along with each application, Elkins required that Coltin and its subcontractors or suppliers execute a release of lien. A form captioned "Release of Lien-Alabama" accompanied or followed the payment applications.
The first payment application was submitted for the period ending August 31, 2010. Melissa Hirmer, an employee of Coltin identified by title as "Accounts Receivable" signed the application in September 2010. Elkins later requested a "lien release to release [the] August payment." Hirmer signed a release of lien for the period ending August 31, 2011, and emailed it to Elkins on October 5, 2010 asking for overnight delivery of the check. (Doc. 146-1, p. 2-3). Coltin received payment in early October 2010. (Doc. 146-1, p. 2, email to Hirmer on October 6, 2010, "Going out today will have tomorrow") In relevant part, the release provides that upon receipt of the amount due for the period ending August 31, 2010, Coltin released and waived any and all liens and claims or rights of lien upon or against the project bonds. (Doc. 146-3)
The second payment application was submitted for the period ending September 30, 2010. Hirmer signed the application on September 24, 2010. (Doc. 146-1, p. 20-23) On November 23, 2010, Elkins' Project Accountant Linda Anderberg, emailed Hirmer stating that "[i]n order to release this check . . . I still am in need of your waiver" and attached a release for Coltin to execute. (Doc. 146-1, p 20-21). That same day, Alan K. Rodgers, identified as the CEO of Coltin, signed the release of lien for the period ending September 30, 2010 (Doc. 146-1, p. 24). The release was emailed to Elkins. (Doc. 146-1, p. 20, email with attachment) In the release, in relevant part, Coltin acknowledged payment received through August 31, 2010 and released and waived any and all liens and claims or rights of lien upon or against the project bonds through that date. Also, the release provided that upon receipt of payment for the period ending September 30, 2010, Coltin released and waived any and all liens and claims or rights of lien upon or against the project bonds for the period ending September 30, 2010. (Doc. 146-4, Doc. 146-1, p. 24)
The third application for payment was submitted for the period ending October 31, 2010. Hirmer signed the application on November 3, 2010. (Doc. 146-5) It appears that no release was submitted. (Doc. 146-2, Birkelbach Affidavit ¶ 10)
The fourth application for payment was submitted for the period ending November 30, 2010. Hirmer signed the application on November 24, 2010. Hirmer signed the release on January 20, 2011. In the release, in relevant part, Coltin acknowledged payment received through October 31, 2010 and released and waived any and all liens and claims or rights of lien upon or against the project bonds through that date. Also, the release provided that upon receipt of payment for the period ending November 30, 2010, Coltin released and waived any and all liens and claims or rights of lien upon or against the project bonds for the period ending November 30, 2010. (Doc. 146-6)
The fifth application for payment was submitted for the period ending December 31, 2010. Hirmer signed the application on December 22, 2010. Hirmer signed the release on February 7, 2011. (Doc. 146-1, p. 9) In the release, in relevant part, Coltin acknowledged payment received through November 30, 2010 and released and waived any and all liens and claims or rights of lien upon or against the project bonds through that date. Also, the release provided that upon receipt of payment for the period ending December 31, 2010, Coltin released and waived any and all liens and claims or rights of lien upon or against the project bonds for the period ending December 31, 2010. (Doc. 146-7)
In sum, Hirmer executed releases for payment applications 1, 4, and 5, there was no release submitted for payment application 3, and Rodgers executed the release for payment application 2. In reliance on the releases signed by either Hirmer or Rodgers, Elkins made payments to Coltin for these payment applications. (Doc. 146-2, Birkelbach Affidavit, ¶¶ 10-11)
The sixth application for payment was submitted for the period ending January 31, 2011. Hirmer signed the application on January 20, 2011. (Doc. 146-8, Doc. 146-1, p. 26-33 (email)) Coltin sought payment of $82,045.96. It appears that no release was submitted at that time. (Doc. 146-1, p. 26)
The seventh application for payment was submitted for the period ending February 28, 2011. Hirmer signed the application on February 25, 2011. (Doc. 146-9, Doc. 146-1, p. 11, email from Hirmer to Anderberg) Coltin sought payment of $64,766.25. (Doc. 146-9) That same day, Hirmer signed a release for the period ending February 28, 2011, which was submitted with the payment application. The release included the amount due from the sixth payment application — $82,045.96 — for a total of $146,812.20 and sets forth, in relevant part, as follows:
(Doc. 135-5, p. 10; Doc. 146-1, p. 16)
On the morning of April 20, 2011, Anderberg emailed Hirmer that funds had been released for February and that she had "two checks for you" since Anderberg still did not have the "$10.00 release from Rexel [a sub-sub-contractor] to release your [January] check." (Doc. 146-1, p. 34) At this point, Anderberg was holding a check dated March 30, 2011, in the amount of $82,045.96 for the January payment and a check dated April 19, 2011, in the amount of $64,766.25 for the February payment. (Doc. 135-6; 135-7) With her email, Anderberg provided two release forms for January and February. (Doc. 146-1, p. 36-37) These two forms contained a release and waiver of any and all liens and claims or rights of lien against the project bonds.
Later that day, Anderberg emailed Hirmer stating "I didn't get your [January] waiver yet??" to which Hirmer replies: "Attached is our waiver thru 01.31.11". (Doc. 146-1, p. 39) The release (waiver) attached was signed by Rodgers on April 21, 2011. (Doc. 146-1, p. 40) This release was not the form sent by Anderberg and did not release or waive any liens and claims or rights of lien against the Project Funds or the Project Bonds. Coltin changed the form of the release submitted for payment. (Doc. 138-1, Rodgers Affidavit) The release submitted on April 21, 2011 for the period ending January 31, 2011, sets forth in relevant part as follows:
(Doc. 135-4, p. 7; Doc. 146-1, p. 40)
The check for January was sent to Coltin and cleared the bank on April 25, 2011. (Doc. 135-6) According to David Birkelbach, Elkins' Project Manager, Elkins did not notice the change in the form and issued payment to Coltin. (Doc. 146-2, p. 4, Birkelbach Affidavit)
On May 5, 2011, Anderburg emailed Hirmer stating "My records show that I need the following waivers to be able to release your Feb. check: Your waiver (attached)", waivers from suppliers and vendors, and "Once I have these I can release your [February] check." (Doc. 138-1, p. 11-12) On May 5, 2011, Rodgers
The check for February was sent to Coltin on May 6, 2011 by overnight delivery (doc. 138-1, p. 15-16) and the check cleared on May 10, 2011. (Doc. 135-7)
The eighth application for payment had been signed by Hirmer and submitted on March 18, 2011, for the period ending March 31, 2011. (Doc. 146-10) On May 6, 2011,
On June 6, 2011, Anderberg emailed Crystal Standland at Coltin: "Call me please to discuss — there is language that is missing from the [March] waiver that you sent me, that is why I had to send you another one." (Doc. 138-5, p 3) Rodgers responded to Anderberg: "We are a bit confused that the language on the waiver is not acceptable. We have submitted the waiver for January and February with no problem on payment. Why is this a problem now?" (Doc. 138-5, p. 3) Anderberg responds: "The Jan and Feb waivers should not have been accepted and I just noticed it. The issue is that all subcontractors should be signing the waiver that you have been signing until very recently." (Doc. 138-5, p. 2)
On June 7, Anderberg emails Birkelbach: Attached is the PDF version of the Lien Waiver on the USA Housing job. Please be advised that I have all of the other waivers I need in order to release the March check . . ." (Doc. 138-5, p. 2). Birkelbach then emails the lien waiver to Rodgers writing "Please sign the attached lien waiver. This waiver is required by Elkins Constructors for all subcontractors, in order to release payment. We will not be able to release any further payments to Coltin until we have this waiver signed as well as all sub waivers in. . . . If you have any additional questions please contact me. . ." (Doc. 138-5, p. 1)
On June 8, 2011, Bill Stinson at Elkins sent Rodgers a revised release for payment application 8 for March 2011, for Rodgers to sign. Stinson wrote as follows:
(Doc. 138-8, p. 1; Release of Lien at p. 2).
Rodgers revised the proposed lien waiver, executed the revised version on June 21, 2011, and sent it to Elkins that day, as explained below:
(Doc. 138-6, p. 2)
In the "executed lien waiver" Rodgers acknowledged receipt of aggregate payments in the amount of $383,502.30 "representing all payments to [Coltin] through 02/28/2011" and released and waived any and all liens and claims or rights of lien upon or against the project bonds. (Doc. 138-1, p. 8) The release also provided that upon receipt of "$301,188.84 for the period ending 05/31/2011" Coltin would waive and release any and all liens and claims or rights of lien upon or against the project bonds. (Id.) The release references "Progress Payment March April May 2011" (Id.)
In paragraph 4, Coltin and Elkins acknowledged that "all rights pertaining to the claims asserted by Coltin Electric, Inc., related to the issued identified on Attachment A are reserved." (Id.) Attachment A begins with the phrase "Payment Application Nos. 8, 9, 10 dated March, April and May 2011" (Doc. 138-1, p. 9). The attachment then identifies "Reserved or Pending Claims/Issues", in three separate paragraphs. In paragraph one "Non-payment/untimely payment. . ." claims are reserved. In paragraph two, reserves claims regarding ten separate "Pending Change Order Proposals". Paragraph three, sets forth as follows:
(Doc. 138-1, p. 9-10).
On June 23, 2011, Birkelbach responds that Elkins will release Coltin's March payment that day upon verification of all sub-subcontractor waivers for February, that Elkins will release Coltin's April payment upon receipt of all sub-subcontractor waivers for March. Birkelbach also stated as follows:
(Doc. 138-1, p. 26) Ultimately, Elkins made payments to Coltin for the periods of March and April
(Doc. 138-1, p. 26)
(Doc. 138-1, p. 25)
(Doc. 138-1, p. 17) The "document" referenced is the release signed by Rodgers on June 21, 2011.
Summary judgment should be granted "if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law." Fed. R. Civ. P. 56(a). If a party raises the assertion "that a fact cannot be or is genuinely disputed", the party must
Fed. R. Civ. P. 56(c)(1)(A)(B).
The defendant, as the parties seeking summary judgment bear "the initial burden to show the district court, by reference to materials on file, that there are no genuine issues of material fact that should be decided at trial." Clark v. Coats & Clark, Inc., 929 F.2d 604, 608 (11th Cir. 1991). The party seeking summary judgment "always bears the initial responsibility of informing the district court of the basis for its motion, and identifying those portions of `the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any,' which it believes demonstrate the absence of a genuine issue of material fact." Clark, 929 F.2d at 608 (quoting Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 2553 (1986)).
Once the defendant has satisfied its responsibility, the burden shifts to the plaintiff, as the non-movant, to show the existence of a genuine issue of material fact. Id. "In reviewing whether the nonmoving party has met its burden, the court must stop short of weighing the evidence and making credibility determination of the truth of the matter. Instead, the evidence of the non-movant is to be believed, and all justifiable inferences are to be drawn in his favor." Tipton v. Bergrohr GMBH-Siegen, 965 F.2d 994, 999 (11th Cir. 1992) (citing Anderson v. Liberty Lobby, 477 U.S. 242, 255, 106 S.Ct. 2505 (1986)); Adickes v. S.H. Kress & Co., 398 U.S. 144, 158-159, 90 S.Ct. 1598, 1608-1609 (1970). However, a "moving party is entitled to summary judgment if the nonmoving party has `failed to make a sufficient showing on an essential element of her case with respect to which she has the burden of proof.'" In re Walker, 48 F.3d 1161, 1163 (11th Cir. 1995) (quoting Celotex Corp., 477 U.S. at 323, 106 S. Ct. at 2552). Overall, the Court must "resolve all issues of material fact in favor of the [non-movant], and then determine the legal question of whether the [movant] is entitled to judgment as a matter of law under that version of the facts." McDowell v. Brown, 392 F.3d 1283, 1288 (11th Cir. 2004) (citing Durruthy v. Pastor, 351 F.3d 1080, 1084 (11th Cir. 2003)).
However, the mere existence of any factual dispute will not automatically necessitate denial of a motion for summary judgment; rather, only factual disputes that are material preclude entry of summary judgment. Lofton v. Secretary of Dept. of Children and Family Services, 358 F.3d 804, 809 (11th Cir. 2004). "An issue of fact is material if it is a legal element of the claim under the applicable substantive law which might affect the outcome of the case. It is genuine if the record taken as a whole could lead a rational trier of fact to find for the nonmoving party." Reeves v. C.H. Robinson Worldwide, Inc., 594 F.3d 798, 807 (11th Cir. 2010) (citation omitted).
Continental argues that it is entitled to judgment as a matter of law for all claims for damages incurred on or before February 28, 2011. (Doc. 135) Continental argues that Coltin signed a release effective through February 28, 2011 in conjunction with payment application #7 and that the release contained an unambiguous release of Elkins and a waiver and release of Coltin's claims against the project bond for all labor, materials equipment or services that Coltin furnished through February 28, 2011. Continental argues that the release was conditioned upon receipt of payment of $146,812.20, that Coltin was paid this sum in two payments, and Coltin accepted the payments, which effectuated the waiver and release.
The Commissioner argues that the February 28, 2011 release is not effective because Hirmer did not have authority to sign on behalf of Coltin. The Commissioner relies upon Rodgers' affidavit testimony that Hirmer did not have authority. (Doc. 138-1, ¶¶ 5-6) In reply, Continental argues that Hirmer had actual or apparent authority to execute the February 28, 2011 release and therefore, bound Coltin and hence the Commissioner, to its terms.
Under Alabama law, apparent authority is implied where the principal permits the agent to appear to a third person to have the capacity to act on behalf of the principal. Such apparent authority "rests upon the principle of estoppel, which forbids one by his acts to give another an appearance of authority which he does not have and to benefit from such misleading conduct to the detriment of one who has acted in reliance upon such appearance." McLemore v. Hyundai Motor Mfg. Ala., LLC, 7 So.3d 318, 329 (Ala.2008) (internal quotations omitted). On motion for summary judgment, "a party relying on an apparent agency must `show that he was misled by the appearances relied upon. It is not enough that he might have been ... so misled. It must also appear that he had reasonable cause to believe that the authority existed; mere belief without cause, or belief in the face of facts that should have put him on his guard is not enough.'" McLemore, 7 So.3d at 329 (quoting Brown v. St. Vincent's Hosp., 899 So.2d 227, 241 (Ala.2004)).
Hirmer was employed as Coltin's Account Receivable clerk and in that capacity signed and certified all nine payment applications and four of the release of lien forms. Hirmer communicated with Elkins' Project Accountant Anderberg in regard to processing the payment applications, providing the release of lien forms, and obtaining payment for Coltin. Elkins relied upon Hirmer's authority to release the liens and claims and issued payments to Coltin. As the principal, Coltin accepted these payments from Elkins and never informed Elkins that Hirmer did not have authority to sign the releases. Thus, Elkins had reasonable cause to believe that Hirmer had authority to act on behalf of Coltin. Accordingly, the Court finds that there is no issue of material fact that Hirmer had apparent authority to sign the releases on behalf of Coltin.
There is no dispute of fact that the releases signed by Hirmer and submitted with payment applications 1, 2, 4, and 5 contained the waiver and release of liens and claims against Elkins' payment bond. The parties do not dispute that Elkins paid Coltin based upon these releases. The Court having now determined that Hirmer had apparent authority to bind Coltin to the releases submitted with payment applications 1, 4, and 5, and that payment has been made as to those payment applications as well as payment application 2 for which Rodgers signed the release and payment application 3 for which there does not appear to be a release, the Court finds that summary judgment is entered in favor of Continental as to Coltin's liens and claims or rights of liens against the payment bond that arose before December 31, 2010. (Doc. 113-1, Release of Lien-Alabama signed February 7, 2011, for payment application 5 covering the period through December 31, 2010)
Continental argues that Coltin's acceptance of Elkins' payments for work, labor and materials furnished in January and February 2011, effectuated and made unconditional the waiver and release terms of the February 28, 2011 release which accompanied payment application #7. Continental argues that summary judgment should be granted in its favor as to all claims and liens incurred before February 28, 2011.
The Commissioner argues that the releases dated April 21, 2011 and May 5, 2011 supersede and replace the release signed on February 25, 2011, because Elkins accepted those releases and made payment based on them. The Commissioner argues that the parties continued to negotiate a release form that preserved Coltin's liens and claims and rights of lien against the project bond and that the release signed in June 21, 2011, superseded all prior releases for the January and February period.
This issue of the effect that should be given to the February 28, 2011 release in light of the releases signed on April 21, 2011, May 5, 2011, and June 21, 2011, and the issue of whether Elkins was induced to accept the release because of fraud or misconduct on the part of Coltin, was discussed at the final pretrial conference. By separate order, the parties have been ordered to provide additional briefing. Therefore, the Court reserves ruling at this time.
Continental argues that the February 28, 2011 release is supported by consideration, unambiguous in meaning, and should be given effect according the intent of the parties. Continental argues that the intent of the parties to release and waive claims against Elkin and the project bonds for all labor, materials, equipment or services furnished through February 28, 2011, can be ascertained from the plain and clear meaning of the express terms of the release.
The Commissioner argues that the February 28, 2011 release is ambiguous, that the true meaning is a question of fact, and therefore, summary judgment should be denied. In support, the Commissioner argues that its interpretation of the release indicates that the subject matter is restricted to a release of liens while Continental's interpretation implies that the release addresses both claims and liens.
When interpreting a contract, the "court should give the terms of the agreement their clear and plain meaning and should presume that the parties intended what the terms of the agreement clearly state." Turner v. West Ridge Apartments, Inc., 893 So.2d 332, 335 (Ala.2004). If the contract is unambiguous, then the court does not look beyond the plain language to speculate the subjective expectations of the parties or their intent. Harbison v. Strickland, 900 So.2d 385, 391 (Ala.2004). An ambiguity exists if the contract is capable of more than one meaning. Voyager Life Ins. Co. v. Whitson, 703 So.2d 944, 948 (Ala.1997).
The Court finds that the release is not capable of more than one interpretation, and therefore, is not ambiguous. The clear and plain meaning is that the parties intended to release and waive any and all liens and claims or rights of lien upon or against the project bonds, conditioned upon payment for labor, materials, equipment or services provided to Elkins.
The Commissioner argues that the release is ambiguous because it could be read to release only liens and not claims. However, that interpretation is not consistent with Alabama law. Generally, a mechanic or materialman who provides labor or materials on a private construction project may file a lien against the private property and follow the procedures under Ala. Code § 35-11-210 to obtain payment. Johnson Controls, Inc. v. Liberty Mutual Insurance Co., ___ So. 3d ___, 2014 WL 1874599, *10 (Ala. 2014). However, that statute does not apply to public property. Therefore, Alabama's little Miller Act, Ala. Code. § 39-1-1, was enacted to provide a remedy to ensure that materialmen receive payment for labor or materials supplied on a public works project. Id. The statute requires contractors to provide a payment bond to act as security for the suppliers of labor or materials on public contracts. Thus, the mechanic or materialman in that circumstance may file a claim against the payment bond.
The Commissioner's interpretation that the release applies only to waive and release liens against the property and not claims against Elkins' payment bond would render the release meaningless. Coltin and other subcontractors cannot file liens against public property so there is no reason to release and waive a right they do not have. If the release does not waive and release claims against Elkins' performance bond and payment bond, then there would be no reason for Elkins to require the release.
Upon consideration and for the reasons set forth herein, the motion for partial summary judgment is GRANTED, in part, at this time.