JAMES L. ROBART, District Judge.
Before the court is Defendants Hartford Fire Insurance Company ("Hartford") and Cherokee General Corporation's ("Cherokee") (collectively, "Defendants") motion to dismiss or stay. (MTD (Dkt. # 34).) Plaintiffs United States of America for the Use and Benefit of Pinnacle Crushing and Construction, LLC; Pinnacle Crushing and Construction, LLC (collectively, "Pinnacle"); United States of America for the Use and Benefit of SCI Infrastructure, LLC; and SCI Infrastructure, LLC (collectively, "SCI") (collectively, "Plaintiffs") oppose the motion. (Pinnacle Resp. (Dkt. # 43); SCI Resp. (Dkt. # 45).) The court has considered the motion, the parties' submissions in support of and in opposition to the motion,
This case arises from Plaintiffs' work on a United States Army Corps of Engineers ("the Corps") construction project. Plaintiffs performed work "for the construction project known as `USACE-S YTC Repair Selah Airstrip, Yakima WA, W912DW-14-D-1002 0012,' at the United States Army's Yakima Training Center" ("the Project").
On October 11, 2016, Cherokee and SCI entered into a subcontract ("the Cherokee-SCI Subcontract") governing SCI's work on the Project. (Line Decl. ¶ 3, Ex. A ("SCI Sub.") (Dkt. # 35-1) at 1.) The Cherokee-SCI Subcontract "incorporates by reference . . . all relevant and applicable clauses of the Prime Contract [the contract between the Corps and Cherokee], as well as all clauses under the Federal Acquisition Rules ("FARs") required by the Prime Contract." (Id.) The parties further agreed that the dispute provisions of the Prime Contract would apply to any disputes arising from the Cherokee-SCI Subcontract. (Id. at 3.) Cherokee agreed to "present to the [Corps] . . . all of [SCI's] claims for additional monetary compensation . . . and to further invoke, on behalf of [SCI], those provisions in the Prime Contract for determining disputes." (Id.) SCI agreed to be "bound by the procedure and final determinations as specified in any such Disputes clause." (Id. at 3-4.)
Pinnacle and SCI also entered into a subcontract ("the SCI-Pinnacle Subcontract"). (Line Decl. ¶ 4, Ex. B ("Pinnacle Sub.").) The SCI-Pinnacle Subcontract also contains a disputes provision that calls for Cherokee to "pass through" Pinnacle's claims to the Corps. (See id. at 12.) Specifically, the parties agreed to be bound "by the terms of the Main Contract and by any and all procedures and resulting decisions, findings, determinations, or awards made thereunder by the person so authorized in the Main Contract, or by an administrative agency, board, [or] court of competent jurisdiction or arbitration." (Id.) Pinnacle further agreed that "it will not take, or will suspend, any other actions"—including Miller Act, 40 U.S.C. § 3131, et seq., claims— "and will pursue no independent litigation with respect thereto, pending final determination of any dispute resolution procedure between" Cherokee and the Corps. (Id.)
On June 7, 2017, the Corps terminated Cherokee's contract and withheld certain payments. (Line Decl. ¶ 7, Ex. C ("Letter")). The Corps contends that Cherokee "fail[ed] to make progress" on the Project, "fail[ed] to provide and adhere to schedules," and "fail[ed] to provide adequate quality control." (Id. at 1.) Cherokee contends that it "encountered differing site conditions that delayed the work and increased the cost of performance." (Line Decl. ¶ 5.) Cherokee disputes the Corps' actions and submitted a claim pursuant to the Prime Contract. (Id. ¶ 8.) Plaintiffs also provided Cherokee with their claims, which Cherokee passed to the Corps. (Id. ¶ 9.)
SCI and Pinnacle also brought suit under the Miller Act. (Pinnacle Compl. ¶ 5); SCI Infrastructure, No. C17-3181SMJ, SCI Compl. ¶¶ IV.1-3. Plaintiffs assert that they performed their obligations under the subcontracts but Cherokee has not paid them. (Pinnacle Compl. ¶ 11); SCI Infrastructure, No. C17-3181SMJ, SCI Compl. ¶¶ 10-14. Plaintiffs contend that Cherokee owes Pinnacle $1,057,597.95
On February 9, 2018, Defendants moved to dismiss or stay the case.
Plaintiffs oppose the motion, contending that any contractual provisions requiring them to wait before pursuing their Miller Act claims are invalid waivers of their rights under the Act. (See Pinnacle Resp. at 7-8; SCI Resp. at 2, 15.) They also argue that a stay would be prejudicial because "the upstream dispute resolution process will possibly take years to complete." (SCI Resp. at 17; see also Pinnacle Resp. at 3, 6.) The court now addresses Defendants' motion.
Defendants bring their motion to dismiss pursuant to Federal Rule of Civil Procedure 12(b)(1), which concerns the court's subject matter jurisdiction. (See MTD at 8); Safe Air for Everyone v. Meyer, 373 F.3d 1035, 1039 (9th Cir. 2004); see also Oregon v. Legal Servs. Corp., 552 F.3d 965, 969 (9th Cir. 2009) ("An objection that a federal court lacks subject matter jurisdiction may be raised at any time."); Salois v. Medifast, Inc., No. 17cv1810-GPC (NLS), 2018 WL 108346, at *3 (S.D. Cal. Feb. 28, 2018) (citing Gemtel Corp. v. Cmty. Redevelopment Agency, 23 F.3d 1542, 1544 n.1 (9th Cir. 1994)) (stating that Rule 12(b)(1) is the proper procedural vehicle for raising a ripeness challenge). They contend that Plaintiffs' claims are unripe because they agreed to pursue alternative dispute processes in the respective subcontracts and those processes have not yet been resolved. (MTD at 7-9.)
A dispute is constitutionally ripe if it "presents concrete legal issues, presented in [an] actual case[]." Mont. Envtl. Info. Ctr. v. Stone-Manning, 766 F.3d 1184, 1188 (9th Cir. 2014) (internal quotation marks and first alteration omitted). "Constitutional ripeness is often treated under the rubric of standing because ripeness coincides squarely with standing's injury in fact prong." Bishop Paiute Tribe v. Inyo Cty., 863 F.3d 1144, 1153 (9th Cir. 2017) (internal quotation marks omitted). That prong requires a plaintiff to demonstrate "`an invasion of a legally protected interest which is (a) concrete and particularized and (b) actual or imminent, not conjectural or hypothetical.'" Id. (quoting Lujan v. Defenders of Wildlife, 504 U.S. 555, 560 (1992)); see also Colwell v. Dep't of Health & Human Servs., 558 F.3d 1112, 1121 (9th Cir. 2009) (stating that the burden of establishing ripeness rests upon the party asserting the claim). A dispute is merely an "abstraction" when "the supposed injury has not materialized and may never materialize." Mont. Envtl. Info. Ctr., 766 F.3d at 1190.
Plaintiffs' claims are constitutionally ripe because Plaintiffs allege a specific injury in fact—that they are owed money for completed work on the Project—and seek recovery against the surety bond. (See, e.g., Pinnacle Compl. ¶¶ 10-17); SCI Infrastructure, LLC, No. C17-3181SMJ, SCI Compl. ¶¶ 10-14, IV.1-3. The required length of time between Plaintiffs' completion of work and provision of materials has also passed. See Walton Tech., Inc. v. Weststar Eng'g, Inc., 290 F.3d 1199, 1205 (9th Cir. 2002) ("[A] subcontractor's right of recovery on a Miller Act payment bond is conditioned on the passage of time from completion of work or provision of materials.") The case therefore presents concrete legal issues that are ripe for review.
Furthermore, the contractual procedure Defendants point to as rendering Plaintiffs' claims unripe do not waive Plaintiffs' Miller Act rights. The Miller Act authorizes a subcontractor to bring suit against a general contractor's surety bond if the subcontractor is not paid within 90 days of completing its work. See 40 U.S.C. § 3133(b)(1); Weststar Eng'g, 290 F.3d at 1205 ("[A] subcontractor's right of recovery on a Miller Act payment bond is conditioned on the passage of time from completion of work or provision of materials."). Courts construe the Miller Act liberally to protect subcontractors, and any waiver of Miller Act rights must be clear and explicit. See Weststar Eng'g, 290 F.3d at 1205, 1208. The Miller Act also provides that a waiver must be in writing, signed by the person whose right is waived, and executed after that person has furnished labor or material used in performing the contract. See 40 U.S.C. § 3133(c).
(SCI Sub. at 3.)
The contractual provision is not sufficiently clear or explicit to constitute a valid waiver of SCI's Miller Act rights.
Nor did Pinnacle waive its right to proceed with a Miller Act claim at this time. The SCI-Pinnacle Subcontract provides that Pinnacle:
(Pinnacle Sub. at 13 (footnote added).) Thus, Defendants are correct that the SCI-Pinnacle Subcontract explicitly purports to waive Pinnacle's Miller Act claim during any dispute resolution between SCI and Cherokee by binding Pinnacle not only to the Prime Contract's procedures but to any "final determination" thereunder. (Id.); see also Weststar Eng'g, 290 F.3d at 1209. However, a subcontractor can waive its Miller Act rights only after furnishing labor or material used in performing the contract. See 40 U.S.C. § 3133(c); see also Am. Constr. & Envtl. Servs. v. Total Team Constr. Servs., Inc., No. 1:14-cv-00087-LJO-GSA, 2014 WL 1664827, at *6 (E.D. Cal. Apr. 24, 2014) (finding that a subcontractor had not waived its Miller Act rights because the "subcontract identified by both parties was secured before [the subcontractor] performed its obligations"); but see Dick/Morganti, 2007 WL 3231717, at *3 (addressing 40 U.S.C. § 3133(c)'s requirements in the context of a stay rather than dismissal). Pinnacle executed the subcontract before it provided labor or materials, and the waiver is therefore invalid.
For these reasons, the court denies Defendants' motion to dismiss on ripeness grounds.
As an alternative to dismissal, Defendants request a stay, arguing that Plaintiffs agreed to wait to pursue Miller Act remedies until any disputes between Cherokee and the Corps resolve. (MTD at 10-16.) Whether a stay is appropriate likewise turns on the waiver of Miller Act rights under the respective subcontracts. See Dick/Morganti, 2007 WL 3231717, at *3; see also Landis v. N. Am. Co., 299 U.S. 248, 254-55 (1936) (A court has the power to stay proceedings "to control the disposition of the causes on its docket with economy of time and effort for itself, for counsel, and for litigants" and must "weigh competing interests."). Neither SCI nor Pinnacle validly waived their right to pursue a Miller Act claim, and the court accordingly denies Defendants' motion for a stay.
Because the SCI-Pinnacle Subcontract expressly references suspending Miller Act claims (SCI-Pinnacle Sub. at 13), however, the court further addresses why that contractual provision does not warrant a stay. In United States v. Dick/Morganti, the District Court for the Northern District of California issued a stay of a subcontractor's Miller Act claims after concluding that "the temporary stay at issue does not effect a `waiver' of the Subcontractors' Miller Act rights within the meaning of [40 U.S.C.] § 3133(c)." 2007 WL 3231717, at *3. Similarly, the court in Kingston Environmental Services, Inc. v. David Boland, Inc. stayed Miller Act claims because the subcontractor "expressly agreed to stay any civil action against [the contractor] and [the surety] pending resolution of the contractual remedial procedure relating to claims for which the [Corps] may be responsible." No. 16-00205 DKW-RLP, 2017 WL 3763519, at *3 (D. Haw. Aug. 30, 2017). Of key importance, however, the agreement there left the subcontractor's Miller Act "remedies . . . intact pending exhaustion of [the] contractual remedial procedure." Id. at *8.
These cases are distinguishable. See Unlimited Envtl., Inc. v. Century Surety Co., No. 12-04278 MMM (SHx), 2012 WL 12882121, at *9 (C.D. Cal. Oct. 29, 2012). Although agreeing to a stay may not amount to a waiver of Miller Act rights, "[t]here is no indication that the subcontract at issue in Dick/Morganti provided that the owner's decision on a subcontractor's compensation request would be `final and binding.'" Id. But the subcontract here provides for Pinnacle "to be bound by the procedure and final determinations as specified in the Main Contract" (SCI-Pinnacle Sub. at 13), "indicating that staying the litigation in favor of the [CDA] proceedings may result in [Pinnacle] losing its ability to return to court to enforce its rights under the Miller Act," id.; see also Kitchens To Go v. John C. Grimberg Co., Inc., 283 F.Supp.3d 476, 486 (E.D. Va. 2017) (declining to stay a case pending the outcome of dispute resolution proceedings between a prime contractor and the government because "the provision was executed before the Subcontractor provided work on the federal project"). The provision therefore purports to waive Pinnacle's right to sue under the Miller Act—not to waive the timing of bringing such a suit. (See Pinnacle Sub. at 13; SCI Sub. at 3); Found. Fence, Inc. v. Kiewit Pac. Co., No. 09cv2062 DMS (JMA), 2010 WL 4024877, at *2 (S.D. Cal. Oct. 13, 2010) (concluding that similar contractual provisions "operate as an implied waiver of Plaintiff's [Miller Act] claims"); cf. Dick/Morganti, 2007 WL 3231717, at *3. Thus, the court denies Defendants' motion even though the SCI-Pinnacle Subcontract contemplates a stay.
The court recognizes that Cherokee may suffer some degree of prejudice from pursuing its claim against the Corps at the same time that Plaintiffs pursue relief from Cherokee. (See Reply to SCI at 12 (stating that Cherokee "will be forced to litigate in two forums[] and may be forced to reconcile the inconsistent positions of its subcontractors").) Even though the disputes will undoubtedly result in some duplication, "[t]he risk of inconsistent results between that process and this litigation is a risk that the prime contractor must bear—transferring the risk of nonpayment for work performed from the subcontractor to the prime contractor is one of the purposes of the Miller Act." Tusco, Inc. v. Clark Constr. Grp., LLC, 235 F.Supp.3d 745, 759-60 (D. Md. 2016). In addition, staying Plaintiffs' claims—particularly where the respective subcontracts purport to bind Plaintiffs to the outcome between Cherokee and the Corps—would also be prejudicial. The court therefore denies the motion to stay.
For the reasons set forth above, the court DENIES Defendants' motion (Dkt. # 34).