THOMAS, Judge.
Century Automotive Group ("Century"), appeals from a judgment of the Madison Circuit Court ("the trial court") ordering specific performance of a contract instead of awarding money damages.
The relevant facts and procedural history are as follows. On June 16, 2009, Century, a corporation that owns a car dealership located in Huntsville, entered into a contract with Structure Designs, LLC ("SD"), for SD to construct and deliver a display for the dealership's showroom. Pursuant to the contract, Century agreed to pay $24,900; the parties agree that SD was to deliver and install the display within six months of receiving payment in full.
It is undisputed that Century paid SD a $10,000 deposit on June 17, 2009, that Century paid the remaining balance of $14,900 on September 3, 2009, and that the display was not delivered. The record includes correspondence between the parties in which Century requested the delivery of the display and in which, subsequent to SD's failure to deliver, Century demanded a refund of the purchase price. On December 8, 2011, Century filed a complaint in the trial court alleging that SD had breached the contract and seeking damages in the amount of $24,900 plus interest and costs; on January 30, 2012, SD filed an answer denying it had breached the contract. Century filed a motion for a summary judgment on June 28, 2013, to which it attached the affidavit of Cindy Hopper, the controller for Century, and letters from Tracy Jones, the president of Century, and Perry Little, the chief executive officer of SD.
The trial court held a trial on July 22, 2013. The transcript reveals that, at the
Century filed a timely notice of appeal to this court on January 23, 2014. In its brief on appeal, Century argues that the trial court erred by ordering specific performance instead of money damages for SD's breach of the contract.
"`The decision to grant specific performance rests largely in the discretion of the trial judge.' Stringfellow Materials, Inc. v. Lee, 438 So.2d 1387, 1390 (Ala. 1983). Moreover, the trial court `will be overturned, on appeal, only if shown to be palpably erroneous.' Stringfellow Materials, 438 So.2d at 1390." 1631 Second Ave. North, L.L.C. v. Raine, 963 So.2d 71, 74 (Ala.2007).
Century correctly states that § 7-2-711(1), Ala.Code 1975, provides that a buyer may recover the amount that has been paid for goods when the seller fails to make delivery.
Although it was undisputed that Century did not seek specific performance of the contract, specific performance was the only remedy ordered by the trial court. Section 7-2-716(1), Ala.Code 1975, provides that "[s]pecific performance may be decreed where the goods are unique or in other proper circumstances." This court has also stated that
General Aviation, Inc. v. Aerial Servs., Inc., 700 So.2d 1385, 1387 (Ala.Civ.App. 1997).
The trial court correctly stated in its judgment that an "injured party is not to be put in a better position by a recovery of damages for the breach than he would have been in if there had been performance. Curacare, Inc. v. Pollack, 501 So.2d 470 (Ala.Civ.App. [1986])." However, we do not understand how simply awarding Century damages for the amount of money it had already paid would place Century in a better position than if the breach had not occurred. Although the contract did not state that time was of the essence,
Moore v. Lovelace, 413 So.2d 1100, 1102 (Ala.1982) (quoting Isom v. Johnson, 205 Ala. 157, 158, 87 So. 543, 544 (1921), quoting in turn Barnard v. Lee, 97 Mass. 92 (1867))(emphasis added). The record indicates that, in addition to not seeking specific performance, Century, at the time of the trial, no longer had a need for the particular display that SD had agreed to provide.
To be sure, "`[t]he equitable remedy of specific performance rests largely in the discretion of the trial judge'"; however, whether to grant such an award "`depends upon a consideration of the particular circumstances of each case.'" Saad v. Saad, 31 So.3d 706, 713 (Ala.Civ.App.2009)(quoting Allen v. Storie, 579 So.2d 1316, 1318-19 (Ala.1991)). Moreover, "`a party who has not shown such a performance of, or willingness upon his part to comply with, the terms of a contract within a reasonable time may not compel performance by the other party to the contract.'" Saad, 31 So.3d at 713-14 (quoting Durden v. Furniture Fair of Dothan, Inc., 348 So.2d 1375, 1376 (Ala. 1977)). Although we note that in the present case the trial court ordered specific performance without the request of the opposing party, it would be inequitable to "`enforce[ specific performance] in favor of a party who has not fully and fairly performed all the conditions precedent on his part to the obligation of the other party.'" Saad, 31 So.3d at 714 (quoting Durden, 348 So.2d at 1376).
Included in the record on appeal are communications between representatives of Century and SD tending to show that, although Century had paid the purchase price in full, SD had failed to deliver the display as the parties had agreed. The trial court stated on the record that SD had breached the contract, and, even though an order granting a partial summary judgment was not entered into the State Judicial Information System, see note 1, supra, the trial court's final judgment confirms that it found that the contract had been breached. SD has not filed a cross-appeal arguing that the trial court's conclusion that it had breached the contract was error. Therefore, we must conclude that, because SD failed to deliver the display, Century was within its rights pursuant to § 7-2-711(1) to cancel the contract and to demand a refund of the purchase price that it had paid. Therefore,
Based upon the foregoing, we reverse the judgment of the trial court insofar as it ordered specific performance of the contract instead of awarding Century damages in the amount of the purchase price that it had paid, and we remand the cause for the trial court to enter a judgment consistent with this opinion.
REVERSED AND REMANDED.
THOMPSON, P.J., and PITTMAN, MOORE, and DONALDSON, JJ., concur.