CHRISTOPHER J. BURKE, Magistrate Judge.
At Wilmington, Delaware this
1. With their Motion, Defendants seek to amend their invalidity contentions, in order to add certain defenses pursuant to 35 U.S.C. § 112. (Tr. at 13) Here, in the governing Scheduling Order, the District Court required that if a party seeks to amend its initial infringement or invalidity contentions, it must first make a showing of good cause. (D.I. 39 at ¶ 7); see also Fed. R. Civ. P. 16(b)(4). Both parties agree (and the Court agrees) that a movant seeking to show that good cause has been established in this situation would, at a minimum, need to demonstrate that it has acted diligently in moving to amend. (D.I. 121 at 4 (citing O2 Micro Int'l Ltd. v. Monolithic Power Sys., Inc., 467 F.3d 1355, 1363-68 (Fed. Cir. 2006); Bayer Cropscience AG v. Dow AgroSciences LLC, Civil Action No. 10-1045-RMB-JS, 2012 WL 12904381, at *1 (D. Del. Feb. 27, 2017); D.I. 134 at 5 (citing O2 Micro); see also D.I. 39 at ¶ 7 (noting, in setting out exemplary showings of good cause, that diligence on the part of the moving party is required))
2. Defendants argue that the impetus for amendment was the District Court's construction of certain claim terms (the "layer terms"); the District Court first informed the parties of its constructions for these claim terms during the December 20, 2019 Markman hearing (wherein the District Court adopted Plaintiffs' proposed constructions for the terms). (D.I. 121 at 1; see also id., ex. A at 40) The Court agrees with Plaintiffs (and with the many courts who have concluded the same) that in general, when a party seeks to amend contentions in light of on a district court's claim construction order, "the moving party's diligence, without which there is no good cause, [should be] measured from the day the moving party received the proposed [claim] constructions, not the date of issuance of the Court's claim construction opinion." Word to Info Inc. v. Facebook Inc., Case No. 15-cv-03485-WHO, 2016 WL 6276956, at *4 (N.D. Cal. Oct. 27, 2016) (internal quotation marks and citations omitted) (citing cases), aff'd, 700 F. App'x 1007 (Fed. Cir. 2017); Takeda Pharm. Co. Ltd. v. Sun Pharma Global FZE, Civil Action No. 14-4616 (MLC), 2016 WL 9229318, at *4-5 (D.N.J. May 16, 2016). This general rule makes good sense, as: (1) if a movant seeks amendment in light of a court's adoption of a construction that was previously proposed many months earlier; and (2) the movant was nevertheless always found to have acted diligently; then (3) this "would mean that [the moving] party could wait until after the construction to take action, even though [in many cases] they were fully equipped to act sooner." Takeda, 2016 WL 9229318, at *5 (citation omitted). Such an outcome would promote and reward delay and inefficiency, not diligence.
3. Of course, there are scenarios where, even after a Markman order issues, a movant's attempt to amend contentions might still be found to be diligent. One such scenario could be if the district court adopted a construction that had not been proposed by any party— and that new construction was the basis for the subsequent motion to amend. See Word to Info, 2016 WL 6276956, at *4-5. Another could arise if a party had earlier put forward a claim construction for a term, but was deliberately vague about the construction's true meaning or scope (e.g., where the party only made clear the true proposed meaning or scope of the construction during the Markman hearing itself).
4. The Court is not persuaded by this argument. Prior to claim construction briefing, the parties had proposed constructions for the layer terms, which are found in certain of the patents-in-suit. With their proposed constructions, Defendants asserted that the layer at issue was a "solid" layer; Plaintiffs put forward constructions for the terms that did not include the word "solid." (D.I. 134, ex. G) Then, in their September 13, 2019 opening claim construction brief, Plaintiffs articulated several supporting rationales for why they took their view. Importantly, they explained there that adding "solid" to the claim term failed to fully capture the covered product described in the specification, which begins "in solid form" but "ultimately erodes or dissolves over time[.]" (D.I. 84 at 10; see also id. at 10-11 ("While the mucoadhesive layer is in solid form, as opposed to a liquid or a gas, at stages during the administration to a patient, there is no reason why this particular feature needs to be added to the claim.") (emphasis added); Tr. at 30-31, 41-42) Plaintiffs reiterated this same view in their reply claim construction brief, served on October 29, 2019. (D.I. 66) There, they again argued—repeatedly—that even though the layer "is not an aqueous solution[,] [it] does not mean that the word `solid' needs to be read into the claim, particularly where the layer erodes over time and the inventors chose to use the word `bioerodable' to define the layer, as opposed to `solid.'" (D.I. 84 at 66 (certain internal quotation marks and citation omitted) (emphasis added); see also id. at 20, 27) And then, during the December 2019 Markman hearing, Plaintiffs' counsel again made the same point in support of Plaintiffs' proposed constructions, explaining that "[t]he written description does not refer to a solid bioerodable mucosal layer pretty much because it dissolves ... [i]t goes away .... [i]t's not there after 20 to 30 minutes[.]" (D.I. 121, ex. A at 23; see also id. at 38 (Plaintiff's counsel referring to the layer during the Markman hearing as a "bioerodable 50-micron layer that goes away"); Tr. at 43) In sum, so far as the Court can tell, Plaintiffs' position Plaintiffs' position as to the "right" constructions for these terms and their rationale behind these constructions have been evident since September 13, 2019, when Plaintiffs served their opening claim construction brief on Defendants. And Defendants have not otherwise sufficiently explained why this is not so.
5. Having therefore established that Defendants were on notice of the need to move to amend at least as early as September 13, 2019, the Court notes that Defendants did not file this Motion until January 6, 2020. (D.I. 121) Absent the existence of other mitigating circumstances, which are not present here,
6. Because this Memorandum Order may contain confidential information, it has been released under seal, pending review by the parties to allow them to submit a single, jointly proposed, redacted version (if necessary) of the document. Any such redacted version shall be submitted by no later than