LAUREL BEELER, Magistrate Judge.
This case involves a government contract and a payment bond issued under the Miller Act, 40 U.S.C. §§ 3131-3134. The Army Corps of Engineers entered into a work contract with a company called Environmental Chemical Corporation ("ECC"), which subcontracted with a company called American Integrity Services, Inc. ("AIS"), which in turn subcontracted with a company called MVC Enterprises, Inc. The Army Corps of Engineers required ECC to obtain a "Miller Act payment bond," and ECC obtained a payment bond from a surety company that has not yet been identified in this litigation. MVC alleges that it was not paid for the work it performed and sued AIS, ECC, and the surety. Because MVC does not know the identity of the surety, it sued the surety as "Doe 1."
It is undisputed that the only basis for federal subject-matter jurisdiction is MVC's Miller Act claim against the surety. AIS moves to dismiss, arguing that because MVC has not timely amended its complaint to replace the "Doe 1" designation with the actual name of the surety, MVC's Miller Act claims against the surety should be dismissed, and consequently that this whole case should be dismissed for lack of subject-matter jurisdiction.
ECC must know the identity of its surety, and the court is at a loss why this information has not been disclosed to MVC to date. The court therefore orders ECC to show cause why it has not disclosed the identity of its surety to MVC. ECC must submit a written response no later than May 31, 2019. MVC may (but is not required to) submit a written response by June 4, 2019 at noon. The parties must appear before the court on June 6, 2019 at 10:00 a.m., when the court will address both this order to show cause and AIS's pending motion to dismiss.
The Miller Act provides that "[b]efore any contract of more than $100,000 is awarded for the construction, alteration, or repair of any public building or public work of the Federal Government, a person must furnish to the Government the following bonds, which become binding when the contract is awarded: . . . . (2) A payment bond with a surety satisfactory to the officer for the protection of all persons supplying labor and material in carrying out the work provided for in the contract for the use of each person." 40 U.S.C. § 3131(b).
The policy behind the Miller Act is to provide for a separate entity — a "surety" — that issues a "payment bond" to pay subcontractors if the prime contractor defaults. Taylor Constr. Inc. v. ABT Serv. Corp. Inc., 163 F.3d 1119, 1122 (9th Cir. 1998). The Miller Act gives subcontractors and sub-subcontractors that are not paid a right to file a suit in federal court against the payment bond. 40 U.S.C. § 3133(b)(2); see, e.g., Technica LLC v. Carolina Cas. Ins. Co., 749 F.3d 1149, 1152 (9th Cir. 2014) ("[T]he Miller Act provides [subcontractors and sub-subcontractors] a federal cause of action, [and] `the scope of the remedy as well as the substance of the rights created thereby is a matter of federal not state law.'") (quoting F.D. Rich Co., Inc. v. United States ex rel. Indus. Lumber Co., Inc., 417 U.S. 116, 127 (1974)). "[The Miller Act] `represents a congressional effort to protect persons supplying labor and material for the construction of federal public buildings in lieu of the protections they might receive under state statutes with respect to the construction of nonfederal buildings.'" Technica, 749 F.3d at 1152 (quoting Mai Steel Serv. Inc. v. Blake Constr. Co., 981 F.2d 414, 416-17 (9th Cir. 1992)). "The Miller Act is highly remedial in nature, and `is entitled to a liberal construction and application in order properly to effectuate the Congressional intent to protect those whose labor and materials go into public projects.'" Id. (quoting United States ex rel. Sherman v. Carter, 353 U.S. 210, 216 (1957)).
In October or November 2017, the U.S. Army Corps of Engineers signed a contract (the "Prime Contract") with ECC on a federal project to remove debris left from fires in October 2017 in Mendocino, Sonoma, Lake, and Napa Counties.
ECC in turn subcontracted with AIS.
A subcontractor or sub-subcontractor that supplies labor or materials for work on a prime contract covered by the Miller Act and that has not been paid may request by affidavit a copy of the relevant Miller Act payment bond from the government agency that issued the contract. 40 U.S.C. § 3133(a).
In April 2018 — seven months before it brought this lawsuit — MVC requested by affidavit that the Army Corps of Engineers provide it with a copy of ECC's payment bond.
In November 2018, MVC filed this suit against AIS, ECC, and the surety that issued ECC's Miller Act bond, alleging claims of (1) breach of contract against AIS, (2) quantum meruit against AIS and ECC, and (3) a claim under the Miller Act against the surety.
ECC and AIS are represented by the same counsel.
On February 28, 2019, the court held an initial case-management conference and issued a case-management and pretrial order (which the court later amended).
According to MVC's counsel's declaration, on March 7, 2019, MVC made a written demand for the promised disclosure documents.
On May 2, 2019, AIS moved to dismiss.
After receiving the motion, counsel for MVC reiterated his demand for documents from counsel to ECC/AIS.
ECC affirms in its answer to MVC's complaint that it obtained a Miller Act payment bond.
The only issue is the fact that MVC does not know who the surety is and thus has named it as "Doe 1."
MVC states, and the defendants do not dispute, that the parties agreed to produce certain documents and make their Rule 26 disclosures on March 8, 2019. MVC implies that these documents and disclosures would contain the identity of the Miller Act payment bond surety. MVC states, and the defendants do not dispute, that ECC did not make all of these productions and disclosures on March 8 or at any point before AIS filed its motion to dismiss.
The court hereby orders ECC to show cause why it has not disclosed the identity of its surety to MVC. After reviewing ECC's response, and any optional further response MVC might submit, the court will evaluate how to proceed, including whether to allow MVC to amend its complaint to name the surety as a defendant, notwithstanding that the deadline for the parties to seek leave to add new parties or amend their pleadings has passed. Cf. Fed. R. Civ. P. 16(b)(4) (court can modify its scheduling order for good cause).
The court orders ECC to show cause why it has not disclosed the identity of its surety to MVC. ECC must submit a written response no later than May 31, 2019. MVC may (but is not required to) submit a written response by June 4, 2019 at noon.