This appeal concerns a water retention basin that was dug in 2004 as part of an expansion project for Northstar Village, a ski resort. The ski resort is owned by CNL Income Northstar LLC and operated by Trimont Land Company (sometimes collectively referred to as CNL). The retention basin was deemed necessary because the expansion project changed the drainage system that diverted storm and snow runoff from approximately 149 acres of developed property. Nearby and downhill from the retention basin are 180 condominium units owned by Aspen Grove Condominium Association (Aspen Grove). Water from the retention basin began to overflow and seep onto Aspen Grove's property starting in December 2004 and continuing thereafter despite remediation efforts. After several years of attempts to solve the water problems with the retention basin, CNL communicated to Aspen Grove in 2008 that it would not perform any further remedial modification or remove the retention basin.
Aspen Grove responded by suing various entities involved in the Northstar Village expansion project, including CNL. The first phase of the bifurcated trial resulted in the trial court's granting a permanent injunction that requires CNL to remove the retention basin. In this appeal in which we address only the first phase of the bifurcated trial, CNL challenges the mandatory injunction on grounds (1) the trial court erred in admitting evidence of damage to the trees on Aspen Grove's property, (2) the trial court should have excluded evidence gathered after the discovery cutoff date, (3) Aspen Grove was not entitled to a mandatory injunction because it has an adequate remedy at law in the form of monetary damages and the option of building a trench on its own property to divert the water overflowing from the retention basin, and (4) the mandatory injunction is overbroad in requiring removal of the retention basin.
We conclude CNL has not preserved its evidentiary arguments because CNL did not include them as issues for appeal when designating a partial reporter's transcript. The trial court did not err in concluding Aspen Grove had no adequate remedy at law because only removal of the retention basin would alleviate the continuing damage to Aspen Grove's property. To hold otherwise would grant a private property owner the right to condemn his or her neighbor's property by limiting the legal remedy for continuing trespass to monetary compensation. The trial court's injunctive relief, rather than being overbroad, rests on credible evidence that removal of the retention basin would prevent irreparable harm to Aspen Grove's property. As a result, we affirm.
In November 2008, Aspen Grove filed a complaint stating causes of action for diversion of surface water, negligence, trespass, and nuisance. A fifth cause of action for mandatory injunction incorporated the other causes of action. Without objection, the trial court bifurcated trial with the first phase limited to injunctive relief, equitable issues, and the question of whether Aspen Grove's action was timely. During the three-week trial of the first phase, CNL designated almost 600 trial exhibits, more than 240 exhibits from the parties were admitted into evidence, and the trial court heard from at least 18 witnesses.
The trial court issued a statement of decision in which it noted that "[t]here is little, if any dispute as to the underlying facts." CNL does not challenge the sufficiency of the evidence for any of the findings made by the trial court. Consequently, we summarize briefly the factual background of this case.
In 2004, an expansion project was undertaken for Northstar Village by then owner Northstar Mountain Properties LLC along with affiliated entities including East West Partners, Inc., and East West Partners-Tahoe, Inc.
The retention basin was constructed to be partially lined. It is located uphill and only 120 feet away from Aspen Grove's nearest condominium building. No geotechnical investigation of groundwater levels at the location of the retention basin or downhill on the Aspen Grove property was undertaken — even though the developer had knowledge of high groundwater levels in the areas. During excavation of the retention basin, high groundwater and water seepage was encountered. Although the retention basin had been planned to have a 58,152-cubic-foot capacity, it was constructed with only a 19,074-cubic-foot capacity.
During the winter of 2004 and spring of 2005, the retention basin overflowed and seeped water onto Aspen Grove's property. Temporary measures were taken to abate the water problem by using sandbags and pumping
From 2005 until 2007, Northstar Village was owned and operated by Trimont. In January 2007, CNL assumed ownership of Northstar Village. Trimont continued operating the property. Even after the changes of ownership, it appears that NMP — which was the developer for the 2004 Northstar Village expansion — continued with its efforts to remediate the retention basin.
In 2007, NMP installed an interceptor trench to remove elevated groundwater and control seepage into Aspen Grove's nearby condominium. The interceptor drain, however, proved ineffective at preventing ongoing water damage to Aspen Grove's property.
Also in 2007, the County of Placer required changes to the retention basin because "the pond size is marginal" and "the design of the retention basin does not provide its intended function" due to "the basin [being] too deep and [having] a small footprint that doesn't allow enough infiltration."
In February 2008, NMP submitted to the County of Placer a "drainage report" that recognized "water levels within the retention pond affect the depth to groundwater down gradient from the pond." To alleviate the problem, NMP proposed a high-flow bypass system so that 56 percent of flows to the retention basin "could be redirected through other water quality treatment facilities instead of through the pond which would enhance the performance of the pond." Also proposed was a "low-flow outlet in the bottom of the pond" so that the drawdown time would be approximately 12 hours.
In response to the high-flow bypass and low-flow outlet proposed in the drainage report, Aspen Grove expressed concerns about their effectiveness and asked NMP to install a monitoring system. Aspen Grove thus requested that NMP install three or four piezometers — narrow wells used to monitor the depth of the groundwater — on the Aspen Grove property.
In "the late winter of 2008," representatives of Aspen Grove met with representatives of NMP and an engineer for the County of Placer. They discussed the proposed high-flow and low-flow mitigation measures. The Aspen Grove representatives voiced concerns about the effectiveness of
The modifications to the retention basin did not accomplish their purpose, and the basin continued to leak water onto the Aspen Grove property. In November 2008, a monitoring report noted that "[t]he low flow drain doesn't seem to keep up with the continuous flow into the pond and now the level has risen [in the retention basin] and more infiltration is occurring." There was no observable change in overall conditions on Aspen Grove property when compared to those observed before the mitigation measures were installed for the retention basin.
In November 2008, Aspen Grove filed a complaint against NMP, CNL, and Trimont. Trial was bifurcated into two phases: The first phase addressed Aspen Grove's claim for injunctive and equitable relief, and the second phase was slated to focus on legal claims and defenses to be tried by a jury. Trial of the first phase resulted in the trial court's issuance of an interlocutory judgment in which it granted a permanent injunction that requires CNL to remove the retention basin, subject to approval of governmental agencies charged with overseeing water quality and management issues.
After entry of the interlocutory judgment granting the permanent injunction, CNL and Trimont timely filed a notice of appeal. CNL and Trimont thereafter filed a designation of the appellate record in which they specified that a partial reporter's transcript be prepared.
CNL challenges the evidentiary rulings of the trial court (1) admitting evidence of damage to the trees on Aspen Grove's property and (2) admitting evidence gathered by Aspen Grove after the discovery cutoff date. In its partial motion to dismiss the appeal, Aspen Grove points out CNL did not include these issues in its specification of arguments to be raised on appeal. The point is well taken.
CNL elected to proceed with a partial reporter's transcript. When an appellant "designates less than all the testimony," California Rules of Court, rule 8.130(a)(2) provides that "the notice must state the points to be raised on appeal ...." The consequence of the statement of points to be raised on appeal is that "the appeal is then limited to those points unless, on motion, the reviewing court permits otherwise." (Ibid.)
CNL designated a partial reporter's transcript and specified the issues to be raised on appeal as: "(1) The granting of the mandatory injunction was not supported by sufficient evidence; (2) The granting of the mandatory injunction was against law; (3) The granting of [the] mandatory injunction was improper because Respondent has an adequate remedy at law; (4) The granting of the mandatory injunction was improper because Appellants lack the ability to comply; (5) The granting of the mandatory injunction exceeded the scope of the relief prayed for by [Respondent]; (6) The granting of the mandatory injunction was improperly broader than necessary to provide the relief prayed for by [Respondent]; (7) Appellants did not waive their constitutional right to a jury trial to determine liability in the first instance."
None of these seven specified issues expressly or impliedly encompasses claims the trial court erred in admitting evidence introduced by Aspen Grove. CNL's lack of notice as to claims of error in admission of Aspen Grove's
We will not consider a contention not included in the specification of points to be raised in an appeal in which the appellant proceeds by partial transcript. (McDaniel v. Dowell (1962) 210 Cal.App.2d 26, 30 [26 Cal.Rptr. 140]; see Wickham v. Southland Corp. (1985) 168 Cal.App.3d 49, 52, fn. 2 [213 Cal.Rptr. 825].) We reject CNL's request to consider the omitted issues on grounds public policy favors resolution of appeals on the merits. The policy in favor of deciding appeals on their merits is not undermined by holding CNL to its own choice of issues to raise on appeal. Thus, we conclude CNL has not preserved for appeal the evidentiary issues concerning admission of Aspen Grove's evidence.
CNL contends the trial court erred in ordering the removal of the retention basin when Aspen Grove had an adequate remedy at law in the form of money damages and the option to build an interceptor trench on its own property. In a related argument, CNL contends the trial court's injunction was "overbroad" because it required removal of the retention basin. We reject the contentions.
Rather than removing the retention basin, CNL proposes that Aspen Grove construct a trench to divert the water from further damaging the foundations of the condominiums on the Aspen Grove property. Preliminary plans indicate the proposed trench would be 941 feet long and vary in depth between nine and 16 feet. Actual trench depth would depend on how far below the surface the bedrock lies. One proposal for the trench would start on CNL's
At trial, Aspen Grove's engineering geologist, Tom Crosby, noted the trench "is intended to remove or lower the groundwater levels downgradient from the retention basin so that it minimizes the impacts downgradient." When asked whether he thought the trench would accomplish its intended purpose, Crosby replied: "I don't think we would be 100 percent confident that the interceptor trench would do as it is intended. [¶] These are complex structures and there could still despite all of the design and study, it still may not be effective at allowing the area to go back to the natural conditions that occurred prior to construction of the retention basin." The best way to restore conditions to prepond state "[w]ould be to remove the pond."
In its statement of decision, the trial court found "[d]efendants elected to locate the basin near the boundary line and in close proximity to the nearest residential building on [Aspen Grove's] adjoining, downhill real property. The evidence showed that alternative sites were available on defendants' land. No ground water level tests were performed at the site nor other appropriate (geotechnical) investigations before construction of the basin." The trial court further found "there was extensive and sufficient evidence introduced by [Aspen Grove] to support the element of proximate cause, including ground water test data at various locations, testimony of numerous witnesses (percipient and expert), many photographs and other documents as to the observed water conditions on the property before and after construction of the subject basin. The evidence arising from the recent event occurring in October 2011, was probative as well as the changes and damages in and around [Aspen Grove's] building foundations, certain parking and driveway areas and as to the death of numerous fir and aspen trees down-gradient of the basin."
On the issue of whether Aspen Grove was entitled to have the retention basin removed, the trial court found: "The evidence established at least three (3) separate and successive modifications to the newly developed drainage diversion system and the infiltration basin by defendants in 2005, 2007 and 2008. Each of the modifications were designed and installed by defendants, or their affiliated entities and contractors, to remedy and abate the recurring water seepage and migration of water from the basin onto plaintiff's down-gradient real property. All three successive modifications were of different designs, including an increase in the holding capacity of the infiltration basin, construction of a bio-swale, a low-flow drainage system, installation of a
The trial court granted a permanent injunction requiring CNL to remove the retention basin by concluding: "In light of the nature of the property herein, the continuing water seepage and invasion of [Aspen Grove's] down gradient real property from the basin and resulting damages, and to avoid the possibility of a multiplicity of judicial actions, the court finds that irreparable harm has been established."
CNL argues the interceptor trench is part of an adequate remedy because "Aspen Grove's own evidence is that installation of an interceptor trench [would] stop `all possible water from the retention basin' from reaching the Aspen Grove development." This assertion does not reflect the record accurately. Indeed, cross-examination by CNL's own counsel elicited the following concerns of Tom Crosby, Aspen's engineering geologist, who testified: "The problem with a cutoff trench is it may remove the water from above the pressure head, can go underneath the collection trench and come out still down below or it could go around." Crosby elaborated, "my concern is that the collection trench may not be effective and may not return the area back to its original condition if you still have a retention basin in the area." Crosby also rejected the idea additional "defensive drains" around Aspen Grove buildings would "completely stop the water." The interceptor trench did not offer any kind of certainty in stopping the flow of water from the retention basin.
CNL proposes a remedy that similarly would give it a private right of eminent domain by requiring Aspen Grove to construct a deep trench of hundreds of linear feet on its property. CNL has no such prerogative to compel Aspen to accept such a de facto encroachment of both diverted waters and a deep trench on its land.
CNL attempts to distinguish Allen, supra, 145 Cal. 666 on grounds the retention basin in this case did not divert naturally flowing water. This
The trial court also rejected CNL's attempt to attribute the water damage to Aspen Grove from a source other than the retention basin. On this point, the trial court found: "The argument that the source of the water invasion was from a spring or wetland area on [Aspen Grove's] land was not supported by sufficient evidence. It is also notable that defendants' contention is inconsistent with the evidence of the three successive remedial measures and modifications to defendants' drainage system undertaken by defendants after 2004, and the implication of liability that arises therefrom." CNL does not challenge the sufficiency of the evidence in support of these findings, which clearly establish the retention basin was part of a water diversion plan that resulted in irreparable and continuing damage to Aspen Grove's property.
CNL contends the retention basin "performs an important function, serving the strong public interest in maintaining clean water." Claiming the retention basin is successfully carrying out its "function ... to restore water quality, collecting the village runoff so it will cleanse itself as it infiltrates into the
CNL does not challenge the trial court's finding alternative sites were available, and presumably remain available, for the retention basin. Instead, CNL characterizes the order to remove the basin as "overly broad." Yet, CNL does not appear to be arguing it should be allowed to shrink the size of the retention basin, use it only intermittently, or even that it is prohibited from building another retention basin elsewhere.
Instead, CNL seems to contend the benefits of the pond to Northstar Village outweigh the toll on Aspen Grove. To this end, CNL asserts "[t]here is no evidence that continued use of the infiltration pond will inevitably result in irreparable injury." This assertion rests on a misreading of the record. As the trial court found: "According to the evidence, the damages incurred by [Aspen Grove] include deterioration of foundations of various residential buildings, damage to improved surfaces of certain parking areas and driveways as well as the death and loss of numerous fir and aspen trees located down-gradient of the infiltration basin on defendants' property in close proximity to [Aspen Grove's] adjoining real property." Further, the trial court found that "[i]n light of the nature of the property herein, the continuing water seepage and invasion of [Aspen Grove's] down gradient real property from the basin and resulting damages, and to avoid the possibility of a multiplicity of judicial actions, the court finds that irreparable harm has been established." Whatever its benefits, the retention basin is located in the wrong place.
Contrary to CNL's assertion, the mandatory injunction does not have the effect of "shutting down an entire legal business." The trial court's injunction
CNL contends the injunction is overbroad on the basis of Thompson v. Kraft Cheese Co. (1930) 210 Cal. 171, 176 [291 P. 204] (Thompson). In Thompson, a dairy manufacturer discharged waste liquids from a factory into a branch of Nicasio Creek with the effect of sickening the plaintiff's herd of pigs. (Id. at p. 173.) The problem was not remedied and the trial court granted injunctive relief. The California Supreme Court concluded, "the injunction is too broad in its provision restraining them from discharging or permitting to escape `any dirty water, sour milk, slops, refuse, offal, or other liquid or semi-liquid matter.' The vice of this provision is that it ignores the question of actual injury, and is framed so as to cover the slightest discharge, whether it causes any substantial pollution of the stream or not. It should have been limited to prohibiting such discharge as would cause substantial injury to the party seeking relief." (Id. at p. 176.) The Thompson court explained, "Where the decree absolutely prohibits any acts, there should be abundant evidence that the continuance of the acts will inevitably result in irreparable injury." (Id. at p. 180.)
The injunctive relief granted in this case passes muster under Thompson, supra, 210 Cal. 171. The trial court found Aspen Grove would suffer irreparable injury if the retention basin were allowed to remain in its current location. CNL does not suggest the trial court should have allowed a smaller basin or limited duration of use. Instead, CNL wants the retention basin to remain as is. The statement of decision clearly establishes the retention basin is a nuisance per se. Notably, the trial court's injunction does not prevent CNL from regaining the same functionality in a different location by another retention basin. The trial court's permanent injunction is not overbroad.
The judgment is affirmed. Aspen Grove Condominium Association shall recover its costs on appeal. (Cal. Rules of Court, rule 8.278(a)(1) & (2).)
Nicholson, Acting P. J., and Robie, J., concurred.