Summary: STIPULATED MOTION AND [PROPOSED] ORDER TO MODIFY CLAIM CONSTRUCTION SCHEDULE NOTE ON MOTION CALENDAR: OCTOBER 22, 2018 JAMES L. ROBART , District Judge . Plaintiffs SRC Labs, LLC & Saint Regis Mohawk Tribe (collectively, "Plaintiffs") and Defendant Microsoft Corporation ("Microsoft") submit this stipulation to request the following modification to the Court's Order Setting the Claim Construction Schedule entered on August 30, 2018 (Dkt. No. 94) (the "Order"), which was previously modifie
More

STIPULATED MOTION AND [PROPOSED] ORDER TO MODIFY CLAIM CONSTRUCTION SCHEDULE

NOTE ON MOTION CALENDAR: OCTOBER 22, 2018

Plaintiffs SRC Labs, LLC & Saint Regis Mohawk Tribe (collectively, "Plaintiffs") and Defendant Microsoft Corporation ("Microsoft") submit this stipulation to request the following modification to the Court's Order Setting the Claim Construction Schedule entered on August 30, 2018 (Dkt. No. 94) (the "Order"), which was previously modified by the Stipulation and Order to Modify Claim Construction Schedule entered on August 31, 2018 (Dkt. No. 112).

Event Current Deadline Modified Deadline Joint claim chart and Prehearing Statement 10/24/18 10/31/18

Good cause exists for this extension because the parties need additional time to obtain and cite to the transcripts of the parties' experts that were deposed on October 17th-20th. The proposed modifications do not change the date of the Markman hearing and will not require modifying any other deadlines set forth in the Court's Orders.

Stipulated and agreet to this 22nd day of October, 2018.

[PROPOSED] ORDER

This matter is before the Court on the parties' Stipulated Motion To Modify Claim Construction Schedule. The Court, having considered this matter and the record in this case, ORDERS as follows:

The Stipulated Motion is GRANTED in its entirety.

IT IS HEREBY ORDERED THAT the claim construction deadlines are modified as follows.

Event Current Deadline Modified Deadline Joint claim chart and Prehearing 10/24/18 10/31/18 Statement

SO ORDERED.