Aceves v. Berryhill, 2:17-CV-01644-EFB. (2018)

Court: District Court, E.D. California Number: infdco20180313711 Visitors: 119
Filed: Mar. 12, 2018
Latest Update: Mar. 12, 2018
Summary: STIPULATION AND [PROPOSED] ORDER FOR REVISED BRIEFING SCHEDULE EDMUND F. BRENNAN , Magistrate Judge . 1. All parties hereby stipulate and request that the Court enter an order revising the briefing schedule as set forth below. Good cause exists for the request: WHEREAS, Plaintiff filed her Complaint on August 8, 2017, and Defendant filed its Answer on November 30, 2017 and lodged the administrative transcript on November 30, 2017. WHEREAS, Plaintiff filed her Motion for Summary Judg
More

STIPULATION AND [PROPOSED] ORDER FOR REVISED BRIEFING SCHEDULE

1. All parties hereby stipulate and request that the Court enter an order revising the briefing schedule as set forth below. Good cause exists for the request:

WHEREAS, Plaintiff filed her Complaint on August 8, 2017, and Defendant filed its Answer on November 30, 2017 and lodged the administrative transcript on November 30, 2017.

WHEREAS, Plaintiff filed her Motion for Summary Judgement on January 16, 2018 and an Amended Motion for Summary Judgment on January 18, 2018. Defendant filed its Opposition to the Plaintiff's First Amended Motion for Summary Judgment and its Cross-Motion for Summary Judgement on February 15, 2018.

WHEREAS, on March 7, 2018, Plaintiff's counsel realized that several citations to the record in its First Amended Summary Judgment Motion were incorrect. This was the result of an inadvertent administrative error on the part of Plaintiff's counsel where they cited to the downloaded version of the ERE file instead of the administrative record provided by the Defendant.

WHEREAS, Plaintiff's counsel promptly contacted the Defendant was amenable to a new stipulated briefing schedule so that this correction could be made.

NOW THEREFORE, the Parties agree and stipulate to the following new briefing schedule:

• Plaintiff's Second Amended Motion for Summary Judgment to correct the citations to the record would be due March 15, 2018. • Defendant's Opposition to the Second Amended Motion for Summary Judgment would be due on April 5, 2018. • Plaintiff's Reply in Support of her Second Amended Motion for Summary Judgement would be due on April 19, 2018.

SO STIPULATED.

[PROPOSED] ORDER

Pursuant to stipulation, and for good cause shown, the parties stipulation is the Court makes the following order:

The revised briefing schedule in this matter is as follows:

• Plaintiff's Second Amended Motion for Summary Judgment to correct the citations to the record would be due March 15, 2018. • Defendant's Opposition to the Second Amended Motion for Summary Judgment would be due on April 5, 2018. • Plaintiff's Reply in Support of her Second Amended Motion for Summary Judgement would be due on April 19, 2018.

IT IS SO ORDERED.