COLLEEN KOLLAR-KOTELLY, UNITED STATES DISTRICT JUDGE.
Plaintiff 2910 Georgia Avenue LLC filed suit against the District of Columbia, Mayor Muriel Bowser, and Polly Donaldson in her official capacity as Director of the Department of Housing and Community Development ("DHCD"),
Upon consideration of the pleadings,
First, the Court finds that the economic effect of the challenged regulations on Plaintiff's condominium building is not sufficient to establish a takings claim as a matter of law. Second, Plaintiff has not established an equal protection claim because it has not demonstrated that it was treated differently by the District than any other developer subject to the IZ Program. Third, Plaintiff has not established a substantive due process claim because the conduct of the District at issue demonstrates, at most, confusion or negligence; it does not approach the level of grave unfairness or deliberate flouting of the law
As relevant to the parties' dispute, the District of Columbia's IZ Program requires that 8-10 percent of the gross floor area of new residential developments (or substantial additions to existing developments) in the District be used for sale or lease to eligible low- and moderate-income households at certain maximum price levels. D.C. Mun. Regs. tit. 11, § 2603.
The IZ Program was established by the District of Columbia Zoning Commission on August 25, 2006. Pl.'s Stmt. of Undisputed Material Facts, ECF No. 68-2 ("Pl.'s Stmt."), ¶ 3. The Zoning Commission delegated responsibility for developing the IZ Program to the Council of the District of Columbia ("D.C. Council") and the Mayor, who subsequently delegated that authority to the Deputy Mayor for Planning and Economic Development ("Deputy Mayor"). Id. ¶¶ 3, 5; Pl.'s Mot., Ex. 3, ECF No. 68-5 (Delegation of Authority — Inclusionary Zoning Implementation Act of 2006). The program was established pursuant to statutory authority set forth in section 107 of the Inclusionary Zoning Implementation Amendment Act of 2006. Id. ¶ 4.
Although on the books as of 2006, the IZ Program was not implemented until certain rules and regulations were passed regarding its implementation. On April 11, 2008, the District, through the Deputy Mayor, issued a Notice of Proposed Rulemaking for regulations that would implement and establish the procedures for the IZ Program. Id. ¶ 8; Pl.'s Mot., Ex. 6, ECF No. 68-8 (Notice of Proposed Rulemaking for Chapter 22 of Title 14 of the District of Columbia Municipal Regulations, entitled "Inclusionary Zoning Implementation"). Among other things, these regulations established the process and the requirements for obtaining building permits for properties subject to the IZ Program. Pl.'s Stmt. ¶¶ 8, 26; Pl.'s Mot., Ex. 6. The Notice of Proposed Rulemaking stated that "[f]inal rulemaking action shall be taken in not less than sixty (60) days from the date of publication of this notice in the D.C. Register." Pl.'s Mot., Ex. 6 at 1. It also stated that the "[t]he Deputy Mayor [] intends that the final rules shall not become effective until ninety (90) days after
In the months after the Notice of Proposed Rulemaking was published, the District began to express its concern, in a series of published resolutions, that the IZ Program was not being implemented quickly enough. On October 21, 2008, the D.C. Council passed Resolution 17-848, which referenced the April 11, 2008 Notice of Proposed Rulemaking and noted that "final rulemaking, including the maximum rent and purchase price schedule [for the IZ Program] has not been published. Because final regulations have not been promulgated... and the maximum rent and purchase price schedule has not been published... the Inclusionary Zoning Program has not been implemented." Pl.'s Mot., Ex. 11, ECF No. 68-13 (D.C. Council Resolution 17-848). This resolution also stated that "[c]ontinuing delays [in implementing the IZ Program] have resulted in the loss of affordable mixed-income units being included in many residential developments" and that "[e]mergency legislation is need[ed] to provide that the final rulemaking and publication requirements for the Inclusionary Zoning Program be met expeditiously." Id.
On November 18, 2008, the D.C. Council passed Resolution 17-871, again stating that final rulemaking had not been published and again declaring an emergency as to the need to publish final rulemaking expeditiously so as to not lose further affordable housing in new developments. Pl.'s Mot., Ex. 12, ECF No. 68-14 (D.C. Council Resolution 17-871). This resolution also stated that "[t]he Administration has stated that because of significant changes that will be made to the proposed rulemaking based on comments received since the initial notice of proposed rulemaking, a revised notice of proposed rulemaking will be published for public comment." Id. It also stated that "[t]he Administration has further stated that 90 days are needed for District agencies to finalize plans for the implementation of the rules after the notice of final rulemaking is published." Id.
As promised, a Revised Notice of Proposed Rulemaking was then published on December 26, 2008, incorporating certain changes to the proposed rules. Pl.'s Mot., Ex. 13, ECF No. 68-15 (Revised Notice of Proposed Rulemaking). Of some note, the Revised Notice stated that "[t]he Deputy Mayor ... intends that the final rules shall not become effective until sixty (60) days after the publication of the Notice of Final Rulemaking in the D.C. Register," which was thirty days less than the 90-day phase-in period envisioned in the initial proposed rulemaking. Id. at 1. The Revised Notice also stated that it replaced the initial notice, and that "[f]inal rulemaking action shall be taken in not less than thirty (30) days from the date of publication of this notice." Id.
By February 3, 2009, final rulemaking still had not been published, and the D.C. Council adopted another emergency resolution regarding the need for final rulemaking. Pl.'s Mot., Ex. 14, ECF No. 68-16 (D.C. Council Resolution 18-22). This resolution referenced the same emergency need for affordable housing as the emergency resolutions that predated it, and again noted that "[t]he Administration ... stated that 90 days were needed for District Agencies to finalize plans for the implementation of the rules after the notice of final rulemaking is published." Id. at 1.
The Notice of Final Rulemaking for these IZ Program regulations was then published on May 15, 2009. Pl.'s Stmt. ¶ 20; Pl.'s Mot., Ex. 18, ECF No. 68-20 (Notice of Final Rulemaking). Plaintiff contends that when this Notice was published, it
Amendments to the IZ Program regulations were later made, but Plaintiff has provided absolutely no reason why the Court should excuse Plaintiff from having been on notice that the IZ Program was generally applicable, in all ways relevant to this case, as of August 14, 2009. On August 28, 2009, the Deputy Mayor published a Notice of Emergency and Proposed Rulemaking, which gave notice of proposed amendments to the IZ Program rules. Pl.'s Stmt. ¶¶ 24-25; Pl.'s Mot., Ex. 21, ECF No. 68-23 (Notice of Emergency and Proposed Rulemaking). Plaintiff does not contend that these amendments are relevant to the applicability of the program to Plaintiff or to the claims in this case. The emergency rulemaking notice stated that the changes were needed to "fully implement" the IZ Program, but expressly acknowledged that the IZ rules had otherwise already been "previously adopted" and had an "August 14, 2009 effective date." Pl.'s Mot., Ex. 21 at 1. Accordingly, although the Notice of Final Rulemaking for these amendments was not published until December 11, 2009, and became effective immediately on that date, Pl.'s Mot., Ex. 22, ECF No. 68-24 (Notice of Final Rulemaking), the IZ Program had otherwise, in all ways relevant to this case, already been in effect since August 14, 2009.
Plaintiff is a real estate company that invests in new housing in the District of Columbia. On November 24, 2009, over three months after the IZ Program rules became effective and applicable in the District, Plaintiff purchased the property at 2910 Georgia Avenue, N.W. from Howard University. Pl.'s Stmt. ¶ 19; Pl.'s Mot., Ex. 16, ECF No. 68-18 (Special Warranty Deed for 2910 Georgia Avenue property). Plaintiff purchased the property, then a vacant lot, for $560,000.00. Defs.' Stmt. of Material Facts for Which There is Not Genuine Dispute, ECF No. 67-30 ("Defs.' Stmt."), ¶ 25. Plaintiff purchased this property with the intention of constructing a 22-unit condominium building. Pl.'s Stmt. ¶ 19. It is undisputed that this entire development project — the condominium building consisting of all 22 units — was a single investment for financing and planning purposes. Defs.' Stmt. ¶ 27.
Plaintiff subsequently, on December 23, 2009, filed a building permit application to construct this condominium building. Pl.'s Stmt. ¶ 28. Even though the IZ Program was in effect as of this date, on March 30, 2010 the D.C. Zoning Office initially indicated
Developments that are subject to the IZ Program are allowed to take advantage of "bonus density," which gives developers the option to "construct up to twenty percent (20%) more gross floor area than permitted as a matter of right." D.C. Mun. Regs. tit. 11, § 2604.1; see also Pl.'s Mot., Ex. 4, ECF No. 68-6 (DHCD webpage entitled "Inclusionary Zoning Affordable Housing Program"). Although the parties dispute Plaintiff's reasons for not doing so, it is undisputed that, after being told by the District in April, 2010 that its development was subject to IZ regulations, Plaintiff did not redesign its building plans to incorporate the "bonus density" made available under the IZ Program, opting instead to proceed forward with the building as planned. Pl.'s Stmt. ¶ 36. Plaintiff claims that it had "no choice" in the matter because to incorporate bonus density at this stage, "Plaintiff would have had to spend months and tens of thousands of dollars," and add more parking. Pl.'s Mot., Ex. 7, ECF No. 68-9 (June 28, 2015 Declaration of Arthur S. Linde), at ¶¶ 8-10.
On May 14, 2010, Plaintiff subdivided the separate lots that made up the property at 2910 Georgia Avenue into a single record lot. Defs.' Stmt. ¶ 28. On May 20, 2010, to satisfy the IZ Program's requirements that 8-10% of the development be used for affordable housing, Plaintiff signed an IZ Covenant binding two of the envisioned 22 condominium units within the planned building: Unit C-02 and Unit 2-02. Pl.'s Stmt. ¶¶ 38, 42; Pl.'s Mot., Ex. 28, ECF No. 68-30 (Plaintiff's IZ Covenant). The building was then constructed. On September 11, 2011, after completing construction, Plaintiff subdivided the building into 22 residential units and 11 parking units. Defs.' Stmt. ¶ 29.
Efforts then began to locate eligible low-and moderate-income purchasers for Plaintiff's IZ Units. Plaintiff submitted a "Notice of Availability" to Defendants on May 12, 2011, indicating that the two IZ Units would be available for occupancy starting on August 1, 2011. See Defs.' Mot., Ex. 9, ECF No. 67-9 (May 12, 2011 Notice of Availability). DHCD created a list of eligible households or persons interested in purchasing or renting the IZ Units who self-certified their eligibility to participate in the IZ Program. Pl.'s Stmt. ¶¶ 44-45. Using these lists, the District subsequently went through a process of running "lotteries" and other alternative selection procedures to identify possible buyers for the units. Id. ¶¶ 47-56.
However, for reasons the parties dispute, the effort to locate a buyer for the units was unsuccessful for an extended period of time. Plaintiff contends that this failure was the fault of Defendants. Predominantly, Plaintiff claims that a requirement
For their part, Defendants contend that Plaintiff's lack of cooperation with efforts to market and sell the property is to blame. Defendants argue that Plaintiff was more interested in using the failure of these units to sell as evidence in its battle to dismantle the IZ Program than in actually selling the units. As evidence, Defendants cite that Plaintiff refused to advertise the units at all, turned down at least one potential buyer, and at one point labelled the IZ Units as "sold" on its website. Defs.' Mot., Ex. 19, ECF No. 67-19 (2910 Georgia Ave. webpage listing units as sold in April 2013).
Having carefully reviewed the evidence in the record, the Court concludes that both parties share some part of the blame for the time it took to sell Plaintiff's units. But who is more or less at fault for the delay is not dispositive of Plaintiff's constitutional claims at this stage. Far more important is the fact that during this period Plaintiff was able to, and did, make unrestricted and quite profitable use of the vast majority of Plaintiff's development. The twenty units not affected by the IZ regulations in Plaintiff's building were sold at market rates between $225,000 and $404,000, for a total of over $6 million. Pl.'s Stmt. ¶ 57; Defs.' Stmt. ¶ 61. This earned the investors in Plaintiff's condominium building a 20% return on their investments. Defs.' Stmt. ¶¶ 62, 63; Defs.' Mot., Ex. 25, ECF No. 67-25 (December 23, 2011 Letter from Art Linde to the investors in 2910 Georgia Ave).
Plaintiff has now also sold its IZ Units. IZ Unit C-02 was sold on April 8, 2015 for $145,200, although Plaintiff strenuously disputes whether the buyer, Ms. Ragini Patel, was in fact eligible to participate in the IZ Program. Pl.'s Stmt. ¶ 105; Defs.' Mot., Ex. 27, ECF No. 67-27 (Deed for Unit C-02). IZ Unit 2-02 was recently sold for $271,200. Pl.'s Stmt. ¶ 130; Defs.' Stmt. ¶ 16; Defs.' Reply, Ex. 1, ECF No. 72-1 (Deed for Unit 2-02).
The parties' relationship predictably grew sour amid these extended efforts to sell Plaintiff's IZ Units, leading Plaintiff to file its first complaint in this case on December
Discovery closed in this matter on May 7, 2015. However, on December 29, 2015, the Court granted Plaintiff's motions to reopen discovery and for leave to file an amended complaint. Mem. Op. & Order (Dec. 29, 2015), ECF No. 57. Plaintiff sought permission to engage in limited additional discovery regarding the sale of Unit C-02 to Ms. Patel, which had only recently occurred at that point, and sought to amend its complaint to add a procedural due process claim. Id. at 7. The Court granted the motion to amend, noting, among other things, that the new procedural due process claim was not futile for the reasons argued by Defendants. Id. at 17. The Court also granted the motion to reopen discovery because it found that "the facts newly discovered by Plaintiff shortly before the filing of Plaintiff's motion to reopen discovery raise questions regarding Ms. Patel's eligibility to purchase Unit C-02 and regarding the process by which the District approved Ms. Patel's application." Id. at 12.
Plaintiff's Amended Complaint was deemed filed as of December 29, 2015. Count I of the Amended Complaint alleges a claim under the Takings Clause of the Fifth Amendment pursuant to 42 U.S.C. § 1983. Amend. Compl. for Monetary and Declaratory Relief, ECF No. 58, ¶¶ 80-95. Count II alleges that the way in which the District implemented and administered the IZ Program violated Plaintiff's substantive due process and equal protection rights in violation of the Fifth Amendment. Id. ¶¶ 96-100. Count III alleges that the way in which the District implemented and administered the IZ Program violated Plaintiff's procedural due process rights in violation of the Fifth Amendment. Id. ¶¶ 101-07. Finally, Count IV seeks a declaratory judgment that the IZ Program is unconstitutional, that the Defendants, acting under color of state law, deprived the Plaintiff of rights guaranteed by the United States Constitution, and that the Plaintiff is entitled to compensation. Id. ¶¶ 108-11.
After the filing of Plaintiff's Amended Complaint, the parties filed and briefed cross-motions for summary judgment. These motions are now ripe for resolution.
Summary judgment is appropriate where "the movant shows that there is
In order to establish that a fact is or cannot be genuinely disputed, a party must (a) cite to specific parts of the record — including deposition testimony, documentary evidence, affidavits or declarations, or other competent evidence — in support of its position, or (b) demonstrate that the materials relied upon by the opposing party do not actually establish the absence or presence of a genuine dispute. Fed. R. Civ. P. 56(c)(1). Conclusory assertions offered without any factual basis in the record cannot create a genuine dispute sufficient to survive summary judgment. See Ass'n of Flight Attendants-CWA, AFL-CIO v. Dep't of Transp., 564 F.3d 462, 465-66 (D.C. Cir. 2009). Moreover, where "a party fails to properly support an assertion of fact or fails to properly address another party's assertion of fact," the district court may "consider the fact undisputed for purposes of the motion." Fed. R. Civ. P. 56(e).
When faced with a motion for summary judgment, the district court may not make credibility determinations or weigh the evidence; instead, the evidence must be analyzed in the light most favorable to the non-movant, with all justifiable inferences drawn in its favor. Liberty Lobby, 477 U.S. at 255, 106 S.Ct. 2505. If material facts are genuinely in dispute, or undisputed facts are susceptible to divergent yet justifiable inferences, summary judgment is inappropriate. Moore v. Hartman, 571 F.3d 62, 66 (D.C. Cir. 2009). In the end, the district court's task is to determine "whether the evidence presents a sufficient disagreement to require submission to a jury or whether it is so one-sided that one party must prevail as a matter of law." Liberty Lobby, 477 U.S. at 251-52, 106 S.Ct. 2505. In this regard, the non-movant must "do more than simply show that there is some metaphysical doubt as to the material facts." Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio Corp., 475 U.S. 574, 586, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986). "If the evidence is merely colorable, or is not significantly probative, summary judgment may be granted." Liberty Lobby, 477 U.S. at 249-50, 106 S.Ct. 2505 (internal citations omitted).
At its core, this case is about Plaintiff's complaint that it "bore the brunt of the District's `growing pains' as it fumbled and bungled every aspect of the IZ Program's implementation." Pl.'s Mot. at 4. This may be so, but the facts in the record are simply insufficient to establish the constitutional violations alleged. For the reasons discussed below, Plaintiff has not established (A) an unconstitutional taking, (B) a violation of the Equal Protection Clause, (C) a violation of Plaintiff's substantive due process rights, or (D) a violation of its procedural due process rights. Accordingly, Defendants are entitled to summary judgment on each of Plaintiff's claims.
"The Takings Clause of the Fifth Amendment prohibits the government from taking `private property ... for public use, without just compensation." Dist. Intown Properties Ltd. P'ship v. D.C., 198 F.3d 874, 878 (D.C. Cir. 1999) (quoting U.S. Const. Amend. V). Two types of takings are prohibited by this clause: "takings without just compensation and takings for a private purpose." Rumber v. D.C., 487 F.3d 941, 943 (D.C. Cir. 2007). Plaintiff alleges that both prohibited types of takings have occurred here.
For the reasons set forth below, Defendants are entitled to summary judgment on Plaintiff's takings claim. The Court begins its analysis of this claim, as it must, by (1) determining the relevant parcel of property at issue. The Court concludes that the relevant parcel is the 22-unit condominium building for which Plaintiff sought a building permit from the District. The Court then (2) explains why the regulations at issue, which affected the use of only 8-10% of that building, did not constitute either a permanent or temporary regulatory taking. Next, the Court (3) explains why the various alternate takings frameworks that Plaintiff has suggested could apply to this case are inapposite. Finally, the Court (4) concludes that Plaintiff has not presented evidence necessary to establish an unconstitutional private taking.
Before the Court can consider whether the regulations at issue constituted a taking of Plaintiff's property, the Court "must first define what constitutes the relevant parcel." Dist. Intown, 198 F.3d at 879. Defendants contend that the relevant parcel in this case is "the 22-unit development as a whole" for which Plaintiff sought a building permit. Defs.' Mot. at 7. Plaintiff, on the other hand, contends that "the relevant parcels are the individual condominium units subject to the IZ Program and the IZ Covenant." Pl.'s Opp'n at 10.
The Court previously addressed this issue in its 2013 Memorandum Opinion on the District's Motion to Dismiss, wherein the Court noted that this constituted the "fundamental dispute between the parties." 2910 Georgia Ave., 983 F.Supp.2d at 137. It remains a fundamental dispute between the parties now, and its resolution has profound implications for the legal sufficiency of Plaintiff's takings claim. See Dist. Intown, 198 F.3d at 879 ("[t]he definition of the relevant parcel profoundly influences the outcome of [the] takings analysis."). As the Court stated in its earlier Opinion, "[u]ltimately the relevant `property' for purposes of this case is a fact-intensive inquiry." 2910 Georgia Ave., 983 F.Supp.2d at 137. This fact-intensive inquiry includes consideration of at least the following factors: "the degree of contiguity, the dates of acquisition, the extent to which the parcel has been treated as a single unit, and the extent to which the restricted lots benefit the unregulated lot." Dist. Intown, 198 F.3d at 880. "[A] court must [] consider how both the property-owner and the government treat (and have treated) the property." Id. "Above all, the parcel should be functionally coherent." Id.
The leading case applying these factors in the D.C. Circuit is District Intown Properties Ltd. Partnership v. District of Columbia. In that case, plaintiff District Intown had purchased an apartment building and landscaped lawn across from the National Zoo in 1961. Id. at 876. In 1988, District Intown subdivided that property into nine lots. Id. at 877. In 1992, the Mayor of the District of Columbia denied District Intown's request for construction permits to build townhouses on eight of those nine lots, based on the lots' status as
As relevant here, the question the Court of Appeals considered was: "Does the relevant parcel consist of the property as a whole or do the eight lots for which construction permits were denied constitute the relevant parcels?" Id. at 879. The Court of Appeals held that the relevant parcel was the property as a whole. The court reasoned that "[t]he lots are spatially and functionally contiguous," "District Intown purchased the property as a whole" and treated it as a single property before subdivision, and that there was no evidence that District Intown treated the lots separately for the purposes of accounting or management. Id. at 880. Although there are certain factual distinctions between this case and District Intown, the Court finds that application of the District Intown court's reasoning to the undisputed facts in this case demands the conclusion that the relevant parcel is the entire 22-unit condominium building which Plaintiff sought a permit to build.
As an initial matter, the Court notes that when addressing this issue in its earlier Opinion, in the context of the District of Columbia's motion to dismiss the complaint, the Court stated that the fact that "District of Columbia law provides that `[e]ach condominium unit shall constitute for all purposes a separate parcel of real estate, distinct from all other condominium units'" supported Plaintiff's argument that the relevant parcel could be the individual condominium units. 2910 Georgia Ave., 983 F.Supp.2d at 137 (quoting D.C. Code § 42-1901.03). The Court reaffirms here that D.C. law is a relevant factor in determining what constitutes the relevant parcel, and that in this case this factor tends to support Plaintiff's position. See Lucas v. S.C. Coastal Council, 505 U.S. 1003, 1016 n.7, 112 S.Ct. 2886, 120 L.Ed.2d 798 (1992) ("The answer to this difficult question may lie in how the owner's reasonable expectations have been shaped by the State's law of property"). However, the Court of Appeals in District Intown expressly instructed that local law "is not always determinative" of the relevant parcel question, 198 F.3d at 879, and the Court rejects Plaintiff's suggestion that the Court's earlier statement should be conclusive of the Court's decision regarding the relevant parcel at this stage in the litigation. The Court did not make any final determination in its preliminary Opinion as to what the relevant parcel would be. Instead, the Court's statement regarding D.C. law was made in the context of its holding that, having reviewed the complaint "for purposes of a motion to dismiss, the Plaintiff has sufficiently alleged that the IZ program constitutes a total taking." 2910 Georgia Ave., 983 F.Supp.2d at 137 (emphasis added). Now, for purposes of the parties' cross-motions for summary judgment, the Court has conducted a fact-intensive analysis of all the relevant factors and has considered not just the allegations in Plaintiff's complaint, but the factual record as a whole. Having conducted such an analysis, the Court concludes that despite the referenced D.C. law, the District Intown factors demand the conclusion that the relevant parcel is the entire 22-unit condominium building, not only the individual units within that building that were affected by the challenged regulations.
First, all of the condominium units within the building are contiguous. They are all units within a single building on a single parcel of land. See Defs.' Mot., Ex. 8, ECF No. 67-8 (Plat and Plans of Condominium
Second, the date of acquisition also favors this conclusion. Plaintiff did not acquire the IZ Units at different times than all of the other units within the condominium building. Plaintiff purchased six lots of land in 2009, combined them into a single parcel, and then built the entire condominium building at one time. Defs.' Stmt. ¶¶ 23-29. The building was only subdivided into 22 units at a later date, after acquisition. Id. ¶ 29; Dist. Intown, 198 F.3d at 880 (considering entire parcel as a whole because "District Intown purchased the property as a whole in 1961" before later subdividing it).
The third factor, "the extent to which the parcel has been treated as a single unit," also favors concluding that the relevant parcel is the condominium building as a whole. Plaintiff argues that this factor weighs in favor of considering the two IZ Units separately because Plaintiff subdivided the building and sold the units within it, including the IZ Units, individually to separate buyers and at different times. Pl.'s Opp'n at 10-12. Plaintiff elaborates that the units receive separate utilities, are separately recorded, and are separately taxed and assessed fees. Id.
As an initial matter, most, if not all, of the distinct treatment Plaintiff can point to with respect to the individual condominium units is merely a result of the fact that Plaintiff subdivided the condominium building after it was constructed. The Court of Appeals has held that "[t]he intentional act of subdivision" alone is not sufficient to show that the subdivided units should be the relevant parcels for takings analysis. Dist. Intown, 198 F.3d at 880. When the record in this case is viewed as whole it becomes clear that these aspects of distinct treatment do not tell the full story, and that in reality the 22-unit condominium building as a whole has consistently been treated as a single, coherent piece of property. The building was treated as a single unit for permitting purposes — this lawsuit arose from Plaintiff's filing of a building permit application to the District to construct the entire condominium building, not any individual units. See Norman v. United States, 429 F.3d 1081, 1091 n.4 (Fed. Cir. 2005) (noting that the fact that "appellants' own permit application related to the entire 2280-acre parcel, and not to any subdivision thereof" indicated that the entire parcel should be considered the relevant parcel for the purposes of appellants' taking claim). All of the units were also part of a single, common development plan or project. See Forest Properties, Inc. v. United States, 177 F.3d 1360, 1365 (Fed. Cir. 1999) (a combination of legally distinct parcels was properly treated as the relevant parcel where "the development was treated as a single integrated project" and it was understood that the individual "portions would be developed as a single project"). It is undisputed that the entire building, all 22 units included, was presented as a single investment for financing, planning and building purposes. See Defs.' Stmt. ¶¶ 23-27; Defs.'
Despite this history, Plaintiff asks the Court to analyze Plaintiff's takings claim as though the relevant parcel only includes the units that were affected by the challenged regulations. But to do so would allow Plaintiff to unfairly paint a regulation which only regulates the use of a small portion (8-10%) of Plaintiff's development as a restriction on the development in its entirety, and therefore potentially a "total" taking. This is precisely the type of circular logic that the Supreme Court has rejected because it would lead to every regulation, no matter how reasonable in scope, constituting "total" and therefore categorical taking. See Tahoe-Sierra Pres. Council, Inc. v. Tahoe Reg'l Planning Agency, 535 U.S. 302, 331, 122 S.Ct. 1465, 152 L.Ed.2d 517 (2002) ("Of course, defining the property interest taken in terms of the very regulation being challenged is circular" because "[w]ith property so divided," every potential taking "would constitute [a] categorical taking[ ]."); Concrete Pipe & Prod. of California, Inc. v. Constr. Laborers Pension Trust for S. California, 508 U.S. 602, 644, 113 S.Ct. 2264, 124 L.Ed.2d 539 (1993) ("a claimant's parcel of property could not first be divided into what was taken and what was left for the purpose of demonstrating the taking of the former to be complete and hence compensable. To the extent that any portion of property is taken, that portion is always taken in its entirety"); Penn Cent. Transp. Co. v. City of N.Y., 438 U.S. 104, 130, 98 S.Ct. 2646, 57 L.Ed.2d 631 (1978) ("`Taking' jurisprudence does not divide a single parcel into discrete segments and attempt to determine whether rights in a particular segment have been entirely abrogated."). Accordingly, the Court concludes that the manner in which the property has been treated also weighs in favor of considering the entire condominium building at 2910 Georgia Avenue the "relevant parcel" for the purposes of Plaintiff's takings claim.
Finally, the Court finds that that there is not significant evidence regarding the "extent to which the restricted lots benefit the unregulated lot" that favors either parties' position in this case. However, the District Intown court found that summary judgment on the relevant parcel issue was proper even when a dispute existed as to this final factor where, as here, "the other three factors strongly suggests that [the subdivided lots] are functionally part of the same property." Dist. Intown, 198 F.3d at 880.
The Court concludes by noting that, although Plaintiff is certainly correct that certain "other takings decisions have held
In sum, in analyzing whether the regulations at issue constituted a "taking" of Plaintiff's property, the Court views the relevant parcel of property as the condominium building at 2910 Georgia Avenue for which Plaintiff sought a building permit from the District. As will be seen below, this conclusion is largely determinative of Plaintiff's takings claim.
"In a regulatory takings case," such as this one, "the principal focus of inquiry is whether a regulation `reaches a certain magnitude' in depriving an owner of the use of property." Dist. Intown, 198 F.3d at 878 (quoting Pennsylvania Coal Co. v. Mahon, 260 U.S. 393, 413, 43 S.Ct. 158, 67 S.Ct. 322 (1922)). "The Supreme Court has indicated that most regulatory takings cases should be considered on an ad hoc basis, with three primary factors weighing in the balance: the regulation's economic impact on the claimant, the regulation's interference with the claimant's reasonable investment-backed expectations, and the character of the government action." Id. at 878-79 (citing Penn Central,
Plaintiff has not satisfied its burden in this case. First, and most importantly in this particular case, the economic impact of the regulation at issue on Plaintiff weighs strongly against finding a taking in this case. Under this factor, Plaintiff must demonstrate that the relevant parcel of property "no longer provide[s] a reasonable rate of return" in light of the challenged regulation. Id. at 884. "[A] claimant must put forth striking evidence of economic effects to prevail even under the ad hoc inquiry." Id. at 883 (emphasis added). Indeed, in Penn Central, the Supreme Court found that no taking had occurred despite the fact that the regulation at issue caused a diminution in value of 75%. Penn Central, 438 U.S. at 131, 98 S.Ct. 2646.
Here, only two of the 22 units in Plaintiff's development were subject to an IZ Covenant restricting their use at all. Although Plaintiff complains that the IZ Program delayed the sale of these units and affected the profit Plaintiff sought to receive from them, the regulations certainly did not leave Plaintiff without a reasonable rate of return from its development as a whole. Quite the opposite: Plaintiff sold the unrestricted units in its development for over $6 million, earning the investors in Plaintiff's building a 20% return on their investments. Defs.' Stmt. ¶¶ 62, 63; Defs.' Mot., Ex. 25 (letter to investors in 2910 Georgia Ave. stating that they had received a 20% return on their investment in the development even before the two IZ Units were sold).
The other Penn Central factors do not salvage Plaintiff's claim. First, Plaintiff's investment backed expectations do not support finding a taking. "A reasonable investment-backed expectation `must be more than a unilateral expectation or an abstract need.'" Id. at 879 (quoting Ruckelshaus v. Monsanto Co., 467 U.S. 986, 1005-06, 104 S.Ct. 2862, 81 L.Ed.2d 815 (1984) (internal quotations omitted)). "Claimants cannot establish a takings claim `simply by showing that they have been denied the ability to exploit a property interest that they heretofore had believed was available for development.'" Id. (quoting Penn Central, 438 U.S. at 130, 98 S.Ct. 2646). Instead, "a buyer's reasonable expectations must be put in the context of the underlying regulatory regime." Id. at 883.
Here, Plaintiff did not have a "reasonable" investment-backed expectation of selling its condominium units free from IZ Covenants. Plaintiff's argument that it did have such a reasonable expectation is apparently based on its claim that the IZ Program was sprung on Plaintiff unfairly, becoming effective immediately on December
Finally, the character of the government action in this case does not support a finding that a "taking" has occurred.
Plaintiff's arguments regarding this factor are not persuasive. First, Plaintiff argues that the character of the government action in this case favors finding that a taking has occurred because the IZ Program has been a "failure." Pl.'s Opp'n at 16. In support of this claim, Plaintiff argues that other programs have produced more affordable housing than the IZ Program. Id. at 16-17. This line of attack misinterprets the Court's role in analyzing the character of the government action. The character of the government action weighs against finding a taking if the action is "a general regulation with a legitimate public purpose." Dist. Intown, 198 F.3d at 883. The Court takes a "deferential stance regarding what constitutes a legitimate public purpose." Perry Capital LLC v. Lew, 70 F.Supp.3d 208, 245 (D.D.C. 2014). Given that the program at issue here serves a public purpose, it is not the role of the Court, other than perhaps in extreme circumstances not present here,
Second, Plaintiff argues that the character of the government action is "very much call[ed] into question" by the eventual sale of one of Plaintiff's IZ Units to an individual, Ms. Ragini Patel, who Plaintiff now claims is not eligible to participate in the IZ Program. Pl.'s Reply at 13. The Court addresses this issue further below in section III.A.4 of this Memorandum Opinion, but for now it is sufficient to say that Plaintiff's evidence in this regard does not show that Defendants acted with any non-public purpose when administering the IZ Program with respect to Plaintiff and this purchaser. At most, Plaintiff raises questions about whether District employees made mistakes while administering the program and whether Ms. Patel may have falsely represented her wealth, income or intentions in her application to participate in the program. These question do not change the fact that the character of the government action challenged here is a generally applicable regulation intended to serve a public purpose.
In sum, the challenged regulation, which affected how Plaintiff could use 8-10% of its development, is a generally applicable regulation with a legitimate purpose. It did not interfere with any reasonable investment-backed expectations of Plaintiff's, nor create a sufficiently severe economic effect on Plaintiff, to rise to the level of an unconstitutional regulatory taking.
The above analysis also resolves Plaintiff's "temporary takings" claim. At no point, even prior to the sale of the two IZ Units, did the IZ Program regulations at issue affect Plaintiff's development in such a way as to work a taking. Plaintiff argues that, "at an irreducible minimum" Defendants' actions constitute a "temporary taking" because of the delay in selling the IZ Units. Pl.'s Mot. at 27-28. But this argument is misguided in its assumption that temporary takings are "different in kind from permanent takings." First English Evangelical Lutheran Church of Glendale v. Los Angeles Cty., Cal., 482 U.S. 304, 318, 107 S.Ct. 2378, 96 L.Ed.2d 250 (1987). They are not different. Id. Temporary takings "should be analyzed in the same constitutional framework applied to permanent irreversible takings." Yuba Nat. Res., Inc. v. United States, 821 F.2d 638, 641 (Fed. Cir. 1987). With respect to Plaintiff's reasonable investment-backed expectations and the character of the government action, the Court's analysis is the same for Plaintiff's temporary takings claim as it was for Plaintiff's permanent takings claim, which is described above.
With respect to the economic effect of the regulation, which was arguably temporarily more severe before the IZ Units eventually sold, the effect was still far from sufficient to support a regulatory takings claim. "[I]n a temporary regulatory takings analysis context the impact on the value of the property as a whole is an important consideration, just as it is in the context of a permanent regulatory taking."
For all of the reasons explained above, Defendants are entitled to summary judgment on Plaintiff's permanent and temporary regulatory takings claim.
In an attempt to escape application of the Penn Central factors, Plaintiff posits numerous alternative takings frameworks it believes this Court should apply to its takings claim. None of those frameworks apply. As an initial matter, Plaintiff's claim does not fit into any of the narrow categories of categorical or per se takings. Although the Supreme Court has held that most takings claims should be analyzed on the ad hoc basis set forth above, it has also "indicated that it will find a `categorical' or per se taking in two circumstances." Dist. Intown, 198 F.3d at 879. "The first circumstance includes regulations that result in `permanent physical occupation of property.'" Id. (quoting Loretto v. Teleprompter Manhattan CATV Corp., 458 U.S. 419, 434-35, 102 S.Ct. 3164, 73 L.Ed.2d 868 (1982)). "The second circumstance includes regulations pursuant to which the government denies all economically beneficial or productive use of property." Id. (quoting Lucas, 505 U.S. at 1015, 112 S.Ct. 2886). Plaintiff argues that either or both of these circumstances are present here.
First, for the same reasons set forth above in the Court's Penn Central analysis, Plaintiff is incorrect that the regulations at issue denied it "all economically beneficial or productive use of" its property. Id. (emphasis added). To constitute this type of categorical taking, "a claimant must show that its property is rendered `valueless' by a regulation." Id. at 882; see also Lucas, 505 U.S. at 1019 n.8, 112 S.Ct. 2886 (noting that categorical taking would not occur where landowner's property was diminished in value by regulation by only 95%).
Here, Plaintiff was plainly not denied all economically beneficial use of its property. Plaintiff was required to execute IZ Covenants for 8-10% of the condominium building at issue. D.C. Mun. Regs. tit. 11, § 2603. Plaintiff was free to, and did, use the remaining 90-92% of the building not subject to IZ Covenants, earning over $6 million and a significant profit. Defs.' Stmt. ¶¶ 29, 61. Accordingly, because Plaintiff has not shown that it was denied all economically beneficial use of its property, its first categorical taking claim fails.
Second, relying on the Supreme Court's opinion in Loretto v. Teleprompter Manhattan CATV Corp., Plaintiff unsuccessfully attempts to shoehorn the facts of this case into a categorical taking by arguing that "[t]he Court could properly view the IZ Program, as applied to this Plaintiff, as an actual physical invasion or usurpation of property rights." Pl.'s Mot. at 15. "[R]egulations that compel the property owner to suffer a physical `invasion' of his property" are "compensable without case-specific inquiry into the public interest advanced in support of the restraint." Lucas, 505 U.S. at 1015, 112 S.Ct. 2886. Compensation is required "no matter how minute the intrusion, and no matter how weighty the public purpose behind it." Id. In Loretto the Supreme Court held that a New York law that required landlords to "permit a cable television company to install its cable facilities upon his property," such that "the cable installation occupied portions of appellant's roof and the side of her building," was a taking because it constituted a "physical occupation of property." Loretto, 458 U.S. at 421, 102 S.Ct. 3164. The Court stated that "when [a] physical intrusion reaches the extreme form of a permanent physical occupation, a taking has occurred." Id. at 426, 102 S.Ct. 3164.
Similarly, as Plaintiff notes, the Supreme Court has also recently reiterated that a per se taking occurs when "`the government directly appropriates private property for its own use.'" Horne v. Dep't of Agric., ___ U.S. ___, 135 S.Ct. 2419, 2425-26, 192 L.Ed.2d 388 (2015) (quoting Tahoe-Sierra, 535 U.S. at 324, 122 S.Ct. 1465). The Supreme Court in Horne held that a reserve requirement set by the government's Raisin Administrative Committee,
These forms of categorical taking are plainly not applicable to the facts of this case. The regulations at issue in this case regulate the terms upon which Plaintiff can use (in this case, sell) its property, generally by limiting the maximum price Plaintiff can charge for that property. The District does not take title to Plaintiff's property, nor does it compel Plaintiff to suffer any physical invasion of its property — points that Plaintiff concedes. Pl.'s Reply at 8; see also Defs.' Mot., Ex. 3, ECF No. 67-3, at 5 (Plaintiff's response to Defendants' ninth request for admission, stating that "Plaintiff admits that the IZ Laws and IZ Program have not resulted in a permanent physical occupation of Plaintiff's property"). In asking the Court to find a categorical taking under this line of cases regardless, Plaintiff seeks to downplay these distinctions as unimportant. They are not. The Supreme Court has "stressed the `longstanding distinction' between government acquisitions of property and regulations." Horne, 135 S.Ct. at 2427 (quoting Tahoe-Sierra, 535 U.S. at 323, 122 S.Ct. 1465); see also George Washington Univ., 391 F.Supp.2d at 112 (order prohibiting George Washington University from using its property for any purposes other than as residences did "not result in a physical occupation of property," but instead simply "require[d] the University to use its property for a certain purpose"). To the extent that the regulations in this case might "go[ ] too far" and constitute a taking, Mahon, 260 U.S. at 415, 43 S.Ct. 158, they must be analyzed on the ad hoc basis set forth in Penn Central and applied above, see Yee v. City of Escondido, Cal., 503 U.S. 519, 529, 112 S.Ct. 1522, 118 L.Ed.2d 153 (1992) ("When a landowner decides to rent his land to tenants, the government may place ceilings on the rents the landowner can charge ... or require the landowner to accept tenants he does not like ... without automatically having to pay compensation.... Such forms of regulation are analyzed by engaging in the `essentially ad hoc, factual inquiries' necessary to determine whether a regulatory taking has occurred") (internal citations omitted).
Finally, Plaintiff is also incorrect in suggesting that "an alternative framework through which the Court may consider Plaintiff's claim for uncompensated taking is that Defendants' actions also amount to an imposition of unconstitutional conditions on the development of Plaintiff's land." Pl.'s Mot. at 25. For this argument, Plaintiff relies on Nollan v. California Coastal Comm'n, 483 U.S. 825, 107 S.Ct. 3141, 97 L.Ed.2d 677 (1987), and Dolan v. City of Tigard, 512 U.S. 374, 114 S.Ct. 2309, 129 L.Ed.2d 304 (1994). In those cases, the Supreme Court "held that a unit of government may not condition the approval of a land-use permit on the owner's relinquishment of a portion of his property unless there is a `nexus' and `rough proportionality' between the government's demand and the effects of the proposed land use." Koontz v. St. Johns River Water Mgmt. Dist., ___ U.S. ___, 133 S.Ct. 2586, 2591, 186 L.Ed.2d 697 (2013). Plaintiff argues that the IZ Program is "essentially the same thing" as the forced exactions of property analyzed in Nollan and Dolan. Pl.'s Opp'n at 4.
In this regard, the Court finds persuasive the recent opinion of the Supreme Court of California, in which that Court analyzed whether a similar inclusionary zoning program implemented in San Jose, California constituted an unconstitutional exaction. California Bldg. Indus. Ass'n. v. City of San Jose, 61 Cal.4th 435, 189 Cal.Rptr.3d 475, 351 P.3d 974 (2015), cert. denied, ___ U.S. ___, 136 S.Ct. 928, 194 L.Ed.2d 239 (2016). Similar to — although apparently more demanding than — the IZ Program at issue in this case, the ordinance at issue in California Bldg. Indus. required that "15 percent of the proposed on-site for-sale units in [a new] development shall be made available at an `affordable housing cost' to households earning no more than 120 percent of the area median income for Santa Clara County adjusted for household size." Id. at 449-50, 189 Cal.Rptr.3d 475, 351 P.3d 974. Like Plaintiff here, the plaintiff in California Bldg. Indus. argued that the "[o]rdinance violate[d] the unconstitutional conditions doctrine, as applied to development exactions." Id. at 457, 189 Cal.Rptr.3d 475, 351 P.3d 974. The Supreme Court of California disagreed, explaining that "there can be no valid unconstitutional-conditions takings claim without a government exaction of property, and the ordinance in the present case does not effect an exaction." Id. That court concluded that "[i]t is the governmental requirement that the property owner convey some identifiable property interest that constitutes a so-called `exaction' under the takings clause and that brings the unconstitutional conditions doctrine into play." Id. at 460, 189 Cal.Rptr.3d 475, 351 P.3d 974. Distinguishing Nollan and Dolan, the California Supreme Court noted that in both of those cases, the Supreme Court had "considered the validity of ad hoc administrative decisions regarding individual land-use permit applications that required a property owner, as a condition of obtaining a sought-after permit, to dedicate a portion of the property to public use." Id. (emphasis in original). Unlike in those cases, the California Supreme Court noted that the 15% set aside "simply places a restriction on the way the developer may use its property by limiting the price for which the developer may offer some of its units for sale." Id. at 461, 189 Cal.Rptr.3d 475, 351 P.3d 974.
The Court finds this analysis persuasive.
In sum, the Court rejects Plaintiff's arguments that this Court could analyze its takings claim under anything other than the ad hoc three factor test set forth by the Supreme Court in Penn Central. Plaintiff cannot demonstrate any type of categorical taking, nor can it demonstrate that the Nollan-Dolan unconstitutional conditions framework is applicable to this case. Because Plaintiff has not established a taking under Penn Central, Defendants are entitled to summary judgment.
The Court also finds that Defendants are entitled to summary judgment on Plaintiff's "private taking" claim, which is how Plaintiff has styled its argument that Defendants have violated the public use requirement of the Takings Clause. It is well settled that "[a] taking for a private purpose is unconstitutional even if the government provides just compensation." Rumber, 487 F.3d at 944 (citing Haw. Hous. Auth. v. Midkiff, 467 U.S. 229, 241, 104 S.Ct. 2321, 81 L.Ed.2d 186 (1984)); see also Midkiff, 467 U.S. at 245, 104 S.Ct. 2321 (a taking "executed for no reason other than to confer a private benefit on a particular private party," does "not withstand the scrutiny of the public use requirement"). Plaintiff claims that the public use requirement has been violated in this case because, despite the public purpose of the challenged regulations generally, the individual who eventually purchased one of Plaintiff's IZ Units through the IZ Program did not, as it turns out, satisfy the District's rules for participating in the program.
This argument does not salvage Plaintiff's takings claim. At the threshold, it fails for the fundamental reason that the Court has already determined that there has been no taking here at all. The public use requirement becomes relevant only if a taking has occurred. See Rancho de Calistoga v. City of Calistoga, 800 F.3d 1083, 1093 (9th Cir. 2015) ("Because we determined that there has been no taking in the first place, it is unnecessary to address whether the public use requirement is
The Court also notes, however, that even if it had found that the IZ regulations at issue constituted a taking, this line of attack would fail for the additional reason that Plaintiff's theory that this "taking" was carried out for a private purpose is not supported by the record.
Plaintiff has not, however, presented sufficient evidence on the second issue — Defendants' purpose in administering the IZ Program with respect to Ms. Patel. This is crucial, because "`it is only the taking's purpose, and not its mechanics,'... that matters in determining public use." Kelo v. City of New London, Conn., 545 U.S. 469, 480, 125 S.Ct. 2655, 162 L.Ed.2d 439 (2005) (emphasis added); Franco v. D.C., 456 F.Supp.2d 35, 40 (D.D.C. 2006) ("a court will not recognize a taking as unconstitutional without evidence that the taking was strictly for a private purpose"). The mere fact that Ms. Patel's participation in the IZ Program may not have objectively furthered the program's overall goal of providing affordable housing to low income individuals is not, in itself, sufficient to establish a violation of the public use requirement. Kelo, 545 U.S. at 484, 125 S.Ct. 2655 ("it is appropriate for us ... to resolve the challenges of the individual owners, not on a piecemeal basis, but rather in light of the entire plan. Because that plan unquestionably serves a public purpose, the takings challenged here satisfy the public use requirement of the Fifth Amendment."); Rancho de Calistoga, 800 F.3d at 1092 (rejecting "private as-applied takings" claim that was merely based on claim that "none of the purposes enumerated in [the challenged ordinance] apply here").
Focusing on Defendants' purpose, it is clear that Defendants would be entitled to summary judgment on this issue. The IZ Program's purpose is to "increas[e] the amount and expand[ ] the geographic
To be sure, the Court's analysis does not end with the IZ Program's stated purpose. Plaintiff could establish a private purpose if it could show that the District acted under the "mere pretext of [this] public purpose, when its actual purpose was to bestow a private benefit." Kelo, 545 U.S. at 478, 125 S.Ct. 2655 (emphasis added). However, despite Plaintiff's intense rhetoric — Plaintiff refers to the District's certification of Ms. Patel as eligible to participate in the IZ Program in turn as "cook[ing] the books," "bogus," "fraudulent" and a "sham," Pl.'s Mot. at 1, 10, 12 — there is no evidence to genuinely support such a claim.
In a nutshell, Plaintiff claims that it has demonstrated a private purpose simply because Defendants' projection of Ms. Patel's annual income during the certification process was allegedly so grossly inaccurate that it could not have been made in good faith. As part of determining Ms. Patel's eligibility for the IZ Program in late 2014, Defendants were required to determine Ms. Patel's household's annual income. Defendants projected Ms. Patel's annual income would be $40,882, which was less than the maximum allowable amount for her household size of $42,800.
The Court need not make any determination as to the accuracy of the District's projection of Ms. Patel's income — indeed, the parties appear to agree that it turned out to be wrong. However, the Court does conclude that the inference of a hidden private purpose or pretext that Plaintiff suggests can be drawn simply based on the District's projection is neither supported nor reasonable. Plaintiff fails to mention that, despite Ms. Patel's earnings earlier in 2014, every single piece of information that the District was provided by Ms. Patel showed that her income, by the time they considered her application, was sufficiently low to qualify her for the IZ Program.
Ms. Patel was an Air Force reservist and her paystubs indicated that she had a highly fluctuating income. Defs.' Opp'n, Ex. 23, ECF No. 71-23 (Patel paystubs); Defs.' Opp'n, Ex. 13, ECF No. 71-13 (February 3, 2016 Deposition of Ragini Patel) ("I'm not a permanent employee. So my salary, what it does is it fluctuates."). Ms. Patel submitted tax returns for the years
Most importantly of all, Ms. Patel herself submitted a signed and notarized declaration attesting that her household's income was below the maximum allowable amount. Defs.' Mot., Ex. 26, ECF No. 67-26 (Patel Declaration of Eligibility). Ms. Patel's Intake Form also indicated that her monthly income was $3,000 which, annualized, constituted a sufficiently low income to qualify her for the program. Pl.'s Mot., Ex. 72, ECF No. 68-76 (Patel Universal Intake Form). Allegedly, Ms. Patel failed to disclose certain income, property or other sources of wealth on these documents — discoveries Plaintiff has made through various means, including by reviewing documents the District was not given by Ms. Patel. But Plaintiff, who concedes that Ms. Patel was dishonest and attempted to "game" the system, Pl.'s Mot. at 33 ("Ms. Patel certainly bears a measure of responsibility for her dishonesty and attempt to `game' the system"), cannot seriously suggest that Ms. Patel's perjury during the application process demonstrates that the District acted with any "private" purpose in administering the IZ Program.
Before concluding, the Court notes for the record that it has reviewed all of the other evidence Plaintiff has put forth regarding
In short, none of Plaintiff's evidence regarding the Patel transaction indicates that the District's purpose in administering the program was anything other than the public one animating the program in general. At most, interpreted in the light most favorable to Plaintiff, the evidence shows that Ms. Patel made certain omissions and misrepresentations about her eligibility, and that if District employees had dug deeper, been less trusting, exercised more diligence, or interpreted Ms. Patel's documents more conservatively, they may have discovered the truth. But without any probative evidence of a private purpose, the allegedly imperfect execution of a government program alone does not give rise to a constitutional violation. See Kelo, 545 U.S. at 480, 125 S.Ct. 2655 ("`it is only the taking's purpose, and not its mechanics,'... that matters in determining public use").
Accordingly, even had the Court concluded that a taking had occurred, Plaintiff's public use challenge would fail for lack of evidence. Defendants are entitled to summary judgment on Plaintiff's takings claim in its entirety.
Although this case is, in essence, about an alleged taking, Plaintiff
Here, Plaintiff argues that it has been treated differently because it was the only developer subject to the IZ Program that was "unable to take advantage of density bonuses," was the only developer to carry two IZ Units before the District revised the IZ Covenant so that IZ participants could take advantage of HUD-insured mortgages, and because it carried its IZ Units for longer than other developers. Pl.'s Mot. at 34-37; Pl.'s Opp'n at 29. Plaintiff also revives under this cause of action its allegation that Ms. Patel was fraudulently certified to participate in the IZ Program. Id.
The Court begins by noting that it has already rejected some of these claims as unsupported by evidence or counter to the record. For example, Plaintiff's argument that the District prevented it from incorporating "bonus density" into its building plans is based on its claim that the IZ Program only became applicable in December of 2009 and without a phase-in period. As discussed above, this is wrong. The Program became applicable on August 14, 2009, after a phase-in period. Plaintiff also suggests that it was treated differently because it was the only developer "forced to transfer his property to a patently ineligible real estate speculator in an illegal private use taking," Pl.'s Opp'n at 29, but the Court has already explained above that this allegation is not supported by sufficient evidence to survive summary judgment.
More fundamentally, however, Plaintiff's equal protection claim fails as a matter of law because although Plaintiff claims that the manner in which the District applied the IZ Program to Plaintiff was unfair for various reasons, it fails to show that the District applied that program to any other developer in a different manner. See Tate v. D.C., 627 F.3d 904, 910 (D.C. Cir. 2010) (equal protection claim that plaintiff "was singled out for harsh treatment" failed because plaintiff had "not identified any similarly situated person... who was treated differently"); Quezada v. Marshall, 915 F.Supp.2d 129, 135 (D.D.C. 2013) ("This requirement is not a mere formality. Rather, it serves to distinguish claims to the treatment that was afforded others, which can be cognizable under principles of equal protection, from bare complaints of governmental unfairness, which cannot"). The mere fact that the IZ Program had certain unique effects on Plaintiff because Plaintiff was the first developer to be subject to its
Defendants are also entitled to summary judgment on Plaintiff's substantive due process claim. As an initial matter, the IZ Program as a whole clearly survives a facial substantive due process challenge. Plaintiff concedes that no fundamental right is at issue here, and accordingly the IZ Program "is subject only to rational basis scrutiny." Abigail All. for Better Access to Developmental Drugs v. von Eschenbach, 495 F.3d 695, 712 (D.C. Cir. 2007). "The rational basis test requires that [Plaintiff] prove that the government's restrictions bear no rational relationship to a legitimate state interest." Id. Here, the District's affordable housing goals constitute a legitimate state interest, and requiring developers of real estate to rent or sell portions of their developments at affordable prices to low income individuals is rationally related to that interest. Plaintiff makes no serious effort to argue otherwise.
Plaintiff's apparent as-applied challenge to the IZ Program is only slightly more colorable, and also fails. "To assert a substantive due process violation [ ] the plaintiff must [ ] show that the District of Columbia's conduct was `so egregious, so outrageous, that it may fairly be said to shock the contemporary conscience.'" Butera v. D.C., 235 F.3d 637, 651 (D.C. Cir. 2001) (quoting Cty. of Sacramento v. Lewis, 523 U.S. 833, 847 n.8, 118 S.Ct. 1708, 140 L.Ed.2d 1043 (1998)); see also George Washington Univ. v. D.C., 318 F.3d 203, 209 (D.C. Cir. 2003) (plaintiff must demonstrate "egregious government misconduct"); Tri Cty. Indus., Inc. v. D.C., 104 F.3d 455, 459 (D.C. Cir. 1997) (the doctrine prohibits "actions that in their totality are genuinely drastic"). "This stringent requirement exists to differentiate substantive due process, which is intended only to protect against arbitrary government action, from local tort law." Butera, 235 F.3d at 651. The Court of Appeals has determined that the "`grave unfairness'" required for the type of substantive due process claim argued by Plaintiff here can by shown by "[1] a substantial infringement of state law prompted by personal or group animus, or [2] a deliberate flouting of the law that trammels significant personal or property rights." Tri Cty. Indus., 104 F.3d at 459 (quoting Silverman v. Barry, 845 F.2d 1072, 1080 (D.C. Cir. 1988)).
Plaintiff believes that it has satisfied this "admittedly high," Pl.'s Opp'n at 27-28, standard with a laundry list of its complaints and frustrations about the District's administration of the IZ Program. It has not done so. Although significant in quantity, none of Plaintiff's complaints are of the grave, egregious or shocking quality that is required for this constitutional claim.
The remainder of the complaints leveled by Plaintiff are similarly insufficient. The fact that District employees overlooked the need to apply the IZ Program when they first reviewed Plaintiff's building permit application and then later corrected themselves certainly does not constitute severe enough illegal conduct or unfairness to support a substantive due process claim. As an initial matter, although Plaintiff complains that the District only caught the fact that Plaintiff's application was subject to the IZ Program by happenstance, Plaintiff does not appear to contest that the IZ Program in fact applied to its development. It is difficult to comprehend how Plaintiff could assert that the eventual decision of the Zoning Office to apply the IZ Program, which undisputedly did apply to Plaintiff's development, is somehow a violation of Plaintiff's substantive due process rights. With respect to the initial failure to require IZ Program compliance, Plaintiff does not contend that this was caused by anything other than oversight, or perhaps negligence, which is "categorically beneath the threshold of constitutional due process." Butera, 235 F.3d at 651 (quoting Cty. of Sacramento, 523 U.S. at 848-49, 118 S.Ct. 1708); see also Elkins v. D.C., 690 F.3d 554, 562 (D.C. Cir. 2012) (the fact that District officials "`sent out mixed messages' ... at most show[ed] `agency confusion,' not the `grave unfairness' required for a substantive due process claim").
Similarly, Plaintiff's complaints regarding the IZ Covenant, although dressed in rather inflammatory language, essentially are critiques of the efficacy the District's IZ Program as originally implemented. Although Plaintiff at times refers to the IZ Covenant as "illegal" when first drafted, see, e.g., Pl.'s Opp'n at 23, such a claim is not supported by the record. At most, the IZ Covenant was incompatible with certain requirements for obtaining a HUD-insured mortgage, making it difficult for low-income purchasers to obtain financing to purchase IZ Units and therefore making it more difficult to locate purchasers for the IZ Program. There is nothing "illegal" about this, and indeed it appears that other jurisdictions have similar requirements.
Plaintiff also complains about the District's refusal to exempt Plaintiff from the IZ Covenant. However, the District was never under any obligation to do so. To the extent Plaintiff complains that the District denied its requests for exemption because it incorrectly believed it did not have the authority to exempt Plaintiff based on a misinterpretation of the applicable regulations, this is insufficient to support a substantive due process claim. See Am. Fed'n of Gov't Employees, AFL-CIO, Local 2798 v. Pope, 808 F.Supp.2d 99, 111 (D.D.C. 2011), aff'd, No. 11-5308, 2012 WL 1450584 (D.C. Cir. Apr. 12, 2012) ("Any legal errors in the General Counsel's decision not to issue a complaint on the plaintiffs' unfair labor practice charge or in the calculation of the timeliness of the plaintiffs' motion for reconsideration would not rise to the level of substantive due process violation."); Chang v. D.C. Dep't of Regulatory & Consumer Affairs, 604 F.Supp.2d 57, 64 (D.D.C. 2009) ("While Mr. Masoero may have been incorrect in his interpretation of the Construction Codes, plaintiff has not alleged any motivation on the part of defendants that would make such an allegation amount to stating a claim for a substantive due process violation.").
Finally, the District's failure to publish certain annual reports — even if said reports were required by law — is similarly far from sufficient to support Plaintiff's substantive due process claim. The Court notes that it fails to see how this has harmed Plaintiff or shows any unfairness to Plaintiff at all. Regardless, like Plaintiff's numerous other complaints, this failure to timely comply with annual reporting requirements is clearly insufficient to establish the "grave unfairness" or "deliberate flouting of the law" required to establish a substantive due process claim. See George Washington Univ., 318 F.3d at 210; Elkins, 527 F.Supp.2d at 49 (mere "deviation from regulations and procedures" is insufficient to establish violation of substantive due process).
In sum, the Court finds that although Plaintiff has found numerous aspects of the District's administration of the IZ Program frustrating — and perhaps rightfully so — Plaintiff has not presented evidence of the type of extreme, unfair, egregious or
Finally, Plaintiffs also argue that Defendants have violated Plaintiff's procedural due process rights. "A procedural due process violation occurs when an official deprives an individual of a liberty or property interest without providing appropriate procedural protections." Atherton v. D.C. Office of Mayor, 567 F.3d 672, 689 (D.C. Cir. 2009). "The three basic elements of a procedural due process claim are (1) a deprivation, (2) of life, liberty, or property, (3) without due process of law." Morris v. Carter Glob. Lee, Inc., 997 F.Supp.2d 27, 35-36 (D.D.C. 2013). Plaintiff's briefing on this claim, which amounts to little more than a restatement of most if not all of Plaintiff's grievance about the IZ Program and conclusory statements that they constitute violations of Plaintiff's procedural due process rights, is not a model of clarity nor particularly helpful to the Court. Plaintiff fails to cogently explain how each and every one of its complaints about the IZ Program, of which there are many, were deprivations of property without sufficient process of law. Nonetheless, the Court can discern three potential property interests that Plaintiff was allegedly deprived of without sufficient process that could be at issue here.
First, to the extent Plaintiff's claims are based on the implementation of the IZ Program and that Program's effect on the profit Plaintiff was able to derive from its property, this claim fails because the IZ Program is a set of generally applicable regulations. "[I]t is well established that statutes or ordinances of general applicability may condition or even prohibit the right to conduct a business without running afoul of procedural due process." Jones v. Air Line Pilots Ass'n, 713 F.Supp.2d 29, 36 (D.D.C. 2010) (quoting Vaden v. Maywood, 809 F.2d 361, 364 (7th Cir. 1987)). The notice and comment process that preceded the enactment of the IZ regulations, described above in section I.B, was sufficient to satisfy any requirements of procedural due process in this context. See Pickus v. U.S. Bd. of Parole, 543 F.2d 240, 244 (D.C. Cir. 1976) ("for `legislative-type' rulemaking, notice and written comment procedures comport with due process"). Additionally, the Court notes that there was a procedure available to Plaintiff for requesting a waiver of the IZ Program's requirements by appealing to the District's Board of Zoning Adjustment. D.C. Mun. Regs. tit. 11, § 2606.
Second, to the extent Plaintiff's claim is based on the D.C. Zoning Office granting initial zoning approval for Plaintiff's condominium building and then revoking that approval after realizing that the building should be subject to IZ Program restrictions, this claim fails because Plaintiff was not deprived of any "property." What was revoked in this case was a preliminary zoning approval, not any actual permit to build. This initial zoning approval appears to have been "merely a step towards the acquisition of the building permit." Tri Cty. Indus., Inc. v. D.C., 104 F.3d 455,
Finally, to the extent Plaintiff's claim is based on the District's alleged deprivation of Plaintiff's ability to use "bonus density," the Court reiterates its finding, explained above, that the basic premise underlying this claim — that the IZ Program became applicable on December 11, 2009 with no phase-in period — is not supported by the record. The IZ Program became effective and applicable after a notice and comment period and a phase-in period on August 14, 2009. Accordingly, the District simply did not deprive Plaintiff of any property interest it might have had in the bonus density available under the IZ Program.
Accordingly, to the extent Plaintiff was deprived of any cognizable property right in this case, that deprivation occurred with sufficient process of law. Plaintiff's procedural due process claim therefore fails.
In sum, the Court finds that Defendants are entitled to summary judgment on each of Plaintiff's claims. Plaintiff's various grievances about the District's implementation of its IZ Program, although perhaps not completely unjustified, do not rise to the level of constitutional violations. Plaintiff has not established that regulations that restricted Plaintiff's use of only 8-10% of its development constituted an unconstitutional taking. Nor has Plaintiff established that it was treated differently than any other developer under the IZ Program, or that anything about the IZ Program or its implementation violated Plaintiff's substantive or procedural due process rights. Accordingly, Defendants' [67] Renewed Motion for Summary Judgment is GRANTED and Plaintiff's [68] Motion for Summary Judgment is DENIED.