JOHN R. TUNHEIM, District Judge.
This case involves a large-scale flood diversion project being planned in the Fargo-Moorhead region of Minnesota and North Dakota ("diversion project" or "project"). Plaintiff Joint Powers Authority of Richland County, North Dakota, and Wilkin County, Minnesota ("Joint Powers" or "JPA"), which was formed to represent the interests of political subdivisions and citizens affected by the diversion project,
The JPA initially filed this action on August 19, 2013. The Court later granted a motion to intervene filed by the Corps' local sponsor in developing the project: the Fargo-Moorhead Diversion Board of Authority
The JPA filed a third amended complaint on November 4, 2014. In it, the JPA asserts NEPA violations against the Corps in Counts I and II. In Counts III-V, it also alleges against both defendants violations of the Minnesota Environmental Rights Act ("MERA"), the Minnesota Environmental Policy Act ("MEPA"), and state and local permitting laws. The JPA has brought a preliminary injunction motion, seeking to enjoin construction of the OHB ring levee. The Corps and the Diversion Authority have both brought motions to dismiss the state and local law claims found in Counts III-V of the third amended complaint. The Corps argues that sovereign immunity bars the state and local law claims against the federal government. The Authority makes several arguments in favor of dismissal, one of which is that any application of Minnesota law to construction in North Dakota violates the United States Constitution's so-called dormant Commerce Clause.
Because state and local environmental law does not bind the federal government, the Court will grant the Corps' motion to dismiss Counts III-V of the third amended complaint. Claims III and IV as asserted against the Diversion Authority are not precluded by the dormant Commerce Clause, however, so the Court will deny the Authority's motion to dismiss these counts. The Court will dismiss Count V against the Authority. Finally, the Court concludes that the JPA has shown a fair chance of prevailing on the merits of at least some of its state law claims, and has met the other preliminary injunction factors. Consequently, the Court will grant the JPA's motion for a preliminary injunction.
The adjacent communities of Fargo, North Dakota, and Moorhead, Minnesota, and the Red River Basin more broadly, have routinely experienced significant flooding, particularly in the last 25 years. (Ex. E ("FEIS Executive Summary") at 14, Feb. 12, 2015, Docket No. 162.) In particular, the record 2009 spring flood reached a flood stage of 40.8 feet. (Id.) The Corps characterized that flood as a 2-percent chance (otherwise called a 50-year (i.e., twice in 100 years)) event. (Id.) The affected cities had largely been responding to flooding with short-term emergency measures. (Id.)
Several entities came together to propose various permanent measures to reduce the flood risk in the Fargo-Moorhead metropolitan area. These measures included a noaction alternative and the continued use of emergency measures; non-structural mitigation measures; flood barriers, including levees; increased conveyance of flood waters, including through the construction and use of water diversion channels; and flood storage. (Id.) The various alternatives were analyzed for their effectiveness, environmental effects, social effects, acceptability, implementability, cost, risk, separable mitigation, and cost effectiveness. (Id.) An initial Alternatives Screening Document was issued in December 2009 that resulted in two diversion concepts being carried forward: one in Minnesota and one in North Dakota. (Id.) All diversion channel options involve the construction upstream of a "control structure" or, as the Minnesota Department of Natural Resources ("MDNR") characterizes it, a high-hazard dam. (Ex. B (Decl. of Aaron Snyder ("Snyder Decl.")) ¶ 12, Feb. 12, 2015, Docket No. 162.)
A draft Environmental Impact Statement ("Draft EIS" or "DEIS") was completed in May 2010 and released on June 11, 2012, proposing three possible plans: a National Economic Development plan ("NED"), which would have the capacity to divert 40,000 cubic feet of water per second (cfs) in Minnesota; the Locally Preferred Plan ("LPP"), which would divert 35,000 cubic feet per second on the North Dakota side; and the Federally Comparable Plan ("FCP"), which would involve a diversion rate of 35,000 cfs on the Minnesota side. (FEIS Executive Summary at 14-17.) Pursuant to the joint request of the cities of Fargo and Moorhead and counties of Clay and Cass, the Assistant Secretary of the Army for Civil Works approved the designation of the LPP as the tentatively selected plan on April 28, 2010. (Id. at 16.)
In September 2010, hydraulic modeling indicated that the LPP "would have more extensive downstream impacts than previously anticipated." (Id. at 17.) As a result, a supplemental DEIS ("SDEIS") was released in April 2011. (Id.) That SDEIS assessed and tentatively recommended several changes to the LPP, including reducing the capacity of the diversion channel, "raising upstream tie-back levee elevations, adding a 50,000 acre-foot storage area and a 150,000 acre-foot staging area, and compensating most affected landowners within the storage and staging areas." (Id.) These revisions reduced the downstream impacts of the diversion project, but increased the upstream impacts.
In July 2011, the Final Feasibility Report and EIS ("FEIS") was released, which considered comments received on the SDEIS and made several more revisions. (FEIS Executive Summary at 17.) In a December 19, 2011 report ("Chief's Report") to the Secretary of the Army, the then-Acting Chief of the Engineers of the Corps, Major General Merdith W. B. Temple, recommended the diversion project for authorization. (Second Decl. of Bruce Spiller ("Second Spiller Decl."), Ex. A ("Chief's Report") at 9, July 8, 2014, Docket No. 69.) The Office of Management and Budget ("OMB") then determined the project was consistent with Administration policy and the final Record of Decision was signed on April 3, 2012. (Snyder Decl. ¶ 24; see also Ex. D (Record of Decision ("ROD")), Feb. 12, 2015, Docket No. 162.)
Subsequent design and engineering studies led to additional proposed modifications. (Ex. H ("Supplemental EA") at 7, Feb. 12, 2015, Docket No. 162.) One of these modifications was the OHB ring levee, which would protect the OHB communities — all of which lie within the SDEIS's new flood-water staging area — from being flooded. (Id. at 7, 22-23.) In September 2013, the Corps released a supplemental environmental assessment ("EA") which evaluated various versions of this modification, along with a no-action alternative, and which ultimately proposed a full levee around the OHB communities. (Id. at 22-23, 55.) The EA also proposed in-town levees for Fargo, which would reduce the usage of the staging area to once every ten years. (Id. at 32, 36.)
Last year, Congress enacted the Water Resources Reform and Development Act of 2014 ("WRRDA 2014" or "WRRDA"). Pub. L. No. 113-121, 128 Stat. 1193 (2014). The President signed WRRDA into law on June 10, 2014. Id. In response to the Corps' recommendation that the diversion project be approved, WRRDA 2014 specifically authorized the project. Pub. L. No. 113-121, § 7002(2)(4). The law authorizes a total project cost of $1,924,300,000. Id. $846,700,000 of the project would be federally funded; $1,077,600,000 would be non-federally funded. Id. The law notes that that project should be "carried out by the Secretary substantially in accordance with the plan, and subject to the conditions, described in the respective reports designated in this section." Id. § 7002.
Although the project has been authorized, no federal construction funding has been earmarked for it yet, and construction funds were not included in the President's FY 2015 or FY 2016 budgets. (Decl. of Kent Lokkesmoe ¶ 17, July 22, 2014, Docket No. 80.) The project has received $40 million total in federal funds to date; it has received portions of that $40 million in each fiscal year since 2008. (Snyder Decl. ¶ 26.) Those funds have been used for the feasibility study and project design. (Id.)
The Authority began construction on the OHB levee in June 2014 and has completed portions of it along its southern and eastern borders. (Ex. A (Decl. of Brett R. Coleman ("Coleman Decl.")) at 6-7, Feb. 12, 2015, Docket No. 162.) The Corps is overseeing this work. (Id.) The Corps has determined that the OHB ring levee is integral to the diversion project and the Diversion Authority is thus receiving in-kind contribution credit for its work on the levee toward the required non-federal cost of the project pursuant to 42 U.S.C. § 1962d-5b(a)(4). (Second Spiller Decl., Ex. B ("Integral Determination Report").)
As the Court discussed in greater detail in its prior order, the State of Minnesota has expressed concerns about the diversion project and the scope of the Corps' environmental review on several occasions. See Richland/Wilkin, 38 F. Supp. 3d at 1046-48. As to the OHB ring levee in particular, the MDNR expressed the concern that beginning construction on the levee prior to the completion of the state's environmental review would violate Minnesota law, unless the levee was an independent project that would be constructed even if the full diversion project was not. Id. at 1048.
The MDNR determined that, because the project included a Class I high-hazard dam, it would require the MDNR — as the responsible governmental unit ("RGU") — to complete a full State EIS, in addition to the federal environmental review. (Decl. of Randall Doneen ("First Doneen Decl.") ¶ 12, July 22, 2014, Docket No. 81.); see also Minn. R. 4410.4400, subp. 18. Although the Corps did not address all of the Diversion Authority's comments on its DEIS and SDEIS, it recognized the state's need to complete its own review and agreed with the MDNR that the state process would begin when the Corps' FEIS was released. (Decl. of Michael R. Drysdale ("Drysdale Decl."), Ex. E ("FEIS App. U"), Feb. 12, 2015, Docket No. 152.)
Minnesota's environmental review of the entire diversion project is ongoing. (Second Decl. of Randall Doneen ("Second Doneen Decl.") ¶ 2, Mar. 12, 2015, Docket No. 180.) The MDNR expects to release its own State DEIS in August of 2015. (Id.) After a public comment period, the MDNR will complete a State FEIS and an adequacy determination. (Id.) It expects to complete this process by late fall of 2015 or early 2016. (Id. ¶ 3.) The state is considering several options, including a no-build alternative; the diversion project as proposed in the Corps' Final EIS; the diversion project as proposed, but moving the high-hazard dam one mile north; and the Distributed Storage Alternative ("DSA") favored by the JPA. (Decl. of Gerald Von Korff ("Third Von Korff Decl."), Ex. E (MDNR Final Scoping Decision) at 6-10, July 15, 2014, Docket No. 71.) The MDNR released a Final Scoping Decision Document for its DEIS in 2014. (First Doneen Decl. ¶ 40; Second Doneen Decl. ¶ 5.) Also in 2014, the MDNR completed a screening report on the DSA option favored by the JPA, which concluded that the DSA "does not meet the project purpose of flood protection from catastrophic flood events." (Second Doneen Decl. ¶ 6.) However, public comments could cause the MDNR to reconsider the DSA option and thus the MDNR has cautioned that "it is incorrect to say that the DSA has been dropped from consideration in the State environmental review." (Id. ¶ 7.)
In August 2014, Governor Dayton wrote the Assistant Secretary of the Army for Civil Works to express strong concern over the diversion project. (Decl. of Gerald Von Korff ("Fifth Von Korff Decl."), Ex. 1, Feb. 11, 2015, Docket No. 125.) The Governor noted that while Minnesota would only accrue some 10% of the benefits of the project, it would nevertheless bear much of the cost because the staging area would result in flooding of Minnesota farmland that generally does not flood. (Id. at 2.) Indeed, the Governor specifically stated that "a major feature of the Project's design appears to be the flooding of Minnesota (and North Dakota) farmland in order to assure North Dakota developers that their investments will be safeguarded." (Id.) The letter stated that "construction of the [OHB] Ring Levee, prior to completion of Minnesota's EIS, violates our state's law." (Id.) The Governor urged a halt to any construction on the project in general, and the OHB ring levee in particular. (Id. at 3.) The Governor also met directly with Diversion Authority officials regarding his concerns. (Decl. of Darrell Vanyo ("Third Vanyo Decl.") ¶ 2, Feb. 12, 2015, Docket No. 159.) The Diversion Authority responded in September 2014 with several concessions: (1) the OHB ring levee — which is being constructed entirely in North Dakota — would only be built to 100-year flood protection levels (i.e., a level that would be useful to the OHB cities whether the broader diversion project is completed or not); (2) no other construction on the diversion project's actual diversion channel would take place until the State EIS is complete (although the letter also encouraged the MDNR to complete its DEIS by July 1, 2015); and (3) the Diversion Authority would add representation from a broader geographic area, including upstream Minnesota interests. (Third Vanyo Decl., Ex. A.) More recently, the Governor has called for a complete freeze on all summer 2015 diversion project construction, pending Minnesota's environmental review.
The JPA filed its third amended complaint on November 4, 2014. (Third. Am. Compl., Nov. 4, 2014, Docket No. 112.) The JPA lists as defendants the Corps and the individual Corps officials, along with the Diversion Authority as defendant-intervenor. (Id.) The Corps alleges five counts. Counts I-II, under NEPA, are only against the federal defendants. (Id. at 1, ¶ 123.) Counts III-V, which assert state and local law claims, are against the federal defendants and the Diversion Authority. (Id. at 1, ¶ 123.)
Count I alleges that the federal defendants violated NEPA in the DEIS and FEIS by (1) failing to address appropriate alternatives to the LPP; (2) failing to address the claim that the LPP may violate Minnesota law; and (3) failing to address the argument that the project violates Executive Order 11988 and state and national flood plain management policy. (Id. ¶¶ 88-117.) Count II alleges that the federal defendants violated NEPA by filing only an EIS and Finding of No Significant Impact ("FONSI") as to the OHB ring levees. (Id. ¶¶ 118-22.)
Count III, against both the federal defendants and the Authority, is styled as a MERA claim, but it cites both the definition of pollution in MERA and
The JPA filed a motion for a preliminary injunction, seeking a temporary halt to any construction on the OHB ring levee. (Pl.'s Mot. for Prelim. Inj., Feb. 11, 2015, Docket No. 122.) The Corps filed a motion to dismiss the state and local law claims — Counts III-V. (Corps Partial Mot. to Dismiss Third Am. Compl., Feb. 11, 2015, Docket No. 141.) The Diversion Authority also filed a motion to dismiss Counts III-V. (Diversion Authority Mot. to Dismiss/Remit, Feb. 11, 2015, Docket No. 145.)
Finally, the State of Minnesota through the MDNR filed an amicus brief, arguing against dismissal of the state law claims against the Diversion Authority and supporting the injunction motion. (Amicus Br. of MDNR ("MDNR Br."), Mar. 12, 2015, Docket No. 179.) The State of North Dakota filed a motion to appear as amicus curiae and lodged a brief in support of the opposition to the preliminary injunction motion and in support of the Authority's dismissal motion. (State of North Dakota's Unopposed Mot. for Leave to Participate as Amicus Curiae, Mar. 25, 2015, Docket No. 185; Amicus Br. of State of North Dakota ("North Dakota Br."), Mar. 25, 2015, Docket No. 188.) The Court will grant North Dakota's unopposed motion to appear as amicus curiae.
A motion to dismiss pursuant to Federal Rule of Civil Procedure 12(b)(1) challenges the Court's subject matter jurisdiction and requires the Court to examine whether it has authority to decide the claims. Uland v. City of Winsted, 570 F.Supp.2d 1114, 1117 (D. Minn. 2008). Both the Corps' sovereign immunity argument for dismissal, and the Authority's standing argument, are analyzed under the Rule 12(b)(1) standard. See Brown v. Dosal, No. 10-4315, 2011 WL 1990445, at *2 (D. Minn. May 23, 2011). It is the plaintiff's burden to establish that jurisdiction exists. Osborn v. United States, 918 F.2d 724, 730 (8
A motion to dismiss for lack of subject matter jurisdiction pursuant to Rule 12(b)(1) may challenge the plaintiff's complaint either on its face or on the factual truthfulness of its averments. See Osborn, 918 F.2d at 729 n.6. A facial challenge, such as one based on the defendant's sovereign immunity, "does not call upon the Court to engage in a factual review by inquiring into and resolving factual disputes." Issaenko v. Univ. of Minn., No. 13-3605, 2014 WL 4954646, at *9 (D. Minn. Sept. 30, 2014) (internal quotation marks and alterations omitted). In a facial challenge to jurisdiction, the Court will decide "whether the asserted jurisdictional basis is patently meritless by looking to the face of the complaint, and drawing all reasonable inferences in favor of the plaintiff." Id. (internal quotation marks omitted). In a factual attack, the Court "considers matters outside the pleadings, and the non-moving party does not have the benefit of 12(b)(6) safeguards." Damon v. Groteboer, 937 F.Supp.2d 1048, 1063 (D. Minn. 2013) (quoting Osborn, 918 F.2d at 734 n.6).
In reviewing a motion to dismiss brought under Rule 12(b)(6), the Court considers all facts alleged in the complaint as true to determine if the complaint states "`a claim to relief that is plausible on its face.'" See Magee v. Trs. of Hamline Univ., Minn., 747 F.3d 532, 535 (8
The JPA asserts its state and local law claims — found in Counts III, IV, and V — against both the Authority and the Corps. (Third Am. Compl. ¶ 123 ("The Federal Defendants are named as Defendants in Counts III-V because they may claim an interest relating to the subject of Counts III-V and may be so situated that disposing of the action in the person's absence may be regarded as impacting agency interests.").) As for the Corps' motion, it argues that the Court should dismiss Counts III-V against the federal defendants because those three counts assert state and local law claims. The Corps is a federal government entity and its officials — all sued only in their official capacity — are federal government officials. The federal government has not waived sovereign immunity as to Minnesota's environmental planning, protection, and permitting laws. Charter Int'l Oil Co. v. United States, 925 F.Supp. 104, 106 (D.R.I. 1996) ("The application of state law to federal government agencies requires an explicit waiver of sovereign immunity."); see also Block v. North Dakota ex rel. Bd. of Univ. & Sch. Lands, 461 U.S. 273, 280 (1983) ("The States of the Union, like all other entities, are barred by federal sovereign immunity from suing the United States in the absence of an express waiver of this immunity by Congress."). As a result, the Court lacks jurisdiction to hear state and local law claims against the Corps.
First, the Court notes that none of the jurisdictional statutes cited in the JPA's complaint provide a waiver of the federal government's sovereign immunity. (Third Am Compl. ¶¶ 29, 30.) For example, 28 U.S.C. § 1367, which the JPA cites to support this Court's supplemental jurisdiction over its state law claims, includes no waiver of the federal government's sovereign immunity. Dunn & Black, P.S. v. United States, 492 F.3d 1084, 1088 n.3 (9
The JPA also cites to the APA in its complaint as a basis for jurisdiction and seems to suggest that the APA might provide a waiver of immunity for the state and local law claims. (See, e.g., Third Am. Compl. ¶ 29.) The JPA is correct that Section 702 does provide a waiver of the federal government's sovereign immunity for persons who were harmed by a federal agency. 5 U.S.C. § 702. Moreover, as the JPA points out, that waiver is not strictly tied to the APA's cause of action, either. Trudeau v. Fed. Trade Comm'n, 456 F.3d 178, 187 (D.C. Cir. 2006) ("In sum, we hold that APA § 702's waiver of sovereign immunity permits not only [the plaintiff's] APA cause of action, but his nonstatutory and First Amendment actions as well."). But, as Trudeau demonstrates, in order to utilize the APA's immunity waiver against a federal agency without asserting an APA cause of action, a plaintiff needs a different, viable cause of action. See id. And the state environmental and permitting laws under which the JPA is suing in Counts III-V provide no viable cause of action against federal agencies. See, e.g., Minn. Stat. § 116D.04, subds. 1a, 10 (providing for judicial review under MEPA of action by a state or local governmental unit); NEPA Law & Litig. § 12:1 (2014) ("The state `little NEPAs'[, such as MEPA,] may apply only to state government agencies or may include local governments as well."); see also Minn. Stat. § 116B.03, subd. 1 (creating a civil action under MERA for any person, partnership, or corporation residing (or with shareholders, members, or partners residing) in Minnesota, the Attorney General of Minnesota, or any political subdivision of the state, against "
The JPA also responds to the Corps' sovereign immunity argument by contending that it simply made the Corps a party to its state and local law claims because of this Court's prior order in this case and to give the Corps a chance to be heard. (See Pl.'s Mem. of Law in Opp'n to Defs.' Mot. to Dismiss Third Am. Compl. on Immunity and Remittitur Grounds ("Pl.'s Opp'n to Corps Mot. to Dismiss") at 5, Feb. 13, 2015, Docket No. 163 ("The primary reason for naming the United States in the new count was to respond to the suggestion by Diversion Authority that the United States has an interest in the outcome of the claims. The Diversion Authority had stated that if we did not name them they would move to join them. By joining them, the United States is given a right to be heard, to the extent that it wishes.").) But this Court's prior order said nothing about subjecting the Corps to state or local law claims. And the JPA's desire to let the Corps be heard in general, does not allow it to attempt to hold the federal government liable under state and local law when the government has not waived its sovereign immunity. Consequently, the Court will grant the Corps' motion to dismiss Counts III-V against the federal defendants; those counts will be dismissed without prejudice.
The Authority first argues that, because the state and local law claims against the federal government must be dismissed due to the government's sovereign immunity, and because the JPA seeks broad relief under those claims in the hopes of halting construction on the entire diversion project,
Specifically, the Authority contends that because the Corps must be dismissed due to sovereign immunity, it is merely speculative whether any relief granted against the Authority under the state or local law claims would redress the JPA's alleged harms. The Corps could simply continue construction on its own, irrespective of an injunction against the Authority. See Nat'l Wrestling Coaches Ass'n v. Dep't of Educ., 366 F.3d 930, 938 (D.C. Cir. 2004) ("[T]he Supreme Court has made clear that a plaintiff's standing fails where it is purely speculative that [court action] will alter the behavior . . . of [] third parties that are the direct cause of the plaintiff's injuries."); see also Hollywood Mobile Estates Ltd. v. Seminole Tribe of Fla., 641 F.3d 1259, 1266 (11
However, the Authority's arguments ignore the practical realities of the project. As the MDNR points out, whether or not the Authority sees itself as simply carrying out the ultimate orders of the Corps in initiating action on the OHB ring levee, and attempting to acquire other property, (Diversion Authority Mem. in Supp. of Mot. to Dismiss/Remit Counts III-V ("Authority Mot. to Dismiss Mem.") at 6, Feb. 11, 2015, Docket No. 147 ("The Diversion Authority is doing nothing more than implementing its required portions of the congressionally authorized Diversion Project in order to receive credit for its cost sharing obligations.")), the Authority is still the only entity with funding that is actually taking any action on the project. It is unclear when Congress will actually
The cases the Authority cites do not require a contrary conclusion. Advantage Media, for example, is inapposite. In that case, the plaintiff was challenging local laws, and was only challenging some of the local laws that restricted its behavior. Advantage Media, 456 F.3d at 801-02. Here, the JPA makes broad claims under the relevant statutes, not leaving select statutes out. While it is true that the JPA cannot bring its state law claims against the Corps, that fact does not render its attempt at seeking redress as ineffectual as a case in which the plaintiff challenges only some of the laws that are causing it harm. The Authority and the Corps are intertwined and are both intimately involved in the planning and construction of the diversion project. Not asserting state law claims against the Corps, but asserting them against its state/local partner, offers a much better chance of gaining redress for injuries than the plaintiff's approach in Advantage Media. Similarly, the holding in National Wrestling Coaches is only somewhat relevant. That case states that it is difficult to demonstrate redressability when a plaintiff seeks agency action that might possibly impact or apply pressure to third-party behavior. 366 F.3d at 938. The Authority and the Corps — as partners on this project — are much more closely tied together than a regulator is to the third parties it regulates. (See, e.g., Authority Mot. to Dismiss Mem. at 6 ("The Diversion Authority is doing nothing more than implementing its required portions of the congressionally authorized Diversion Project in order to receive credit for its cost sharing obligations.").)
The Sierra Club v. Clinton, 689 F.Supp.2d 1147 (D. Minn. 2010), case is relevant here. In that case, the plaintiff challenged the State Department's FEIS and issuance of a pipeline permit under NEPA. Id. at 1155. The State Department argued the claim was not redressable, because even if the court found that the department had violated NEPA and invalidated the permit, the President could still choose to grant the permit pursuant to his inherent authority. Id. The court rejected that argument, noting that the "President's future actions or inactions are too speculative to preclude standing in this case." Id. While the Corps' eventual actions vis-à-vis the project are less speculative — given the congressional authorization of the diversion project in WRRDA — the principles of the Sierra Club case still apply. The Diversion Authority is the one moving forward on the project and it is responsible, under WRRDA, for more than half the project's funding. (Chief's Report at 9-13.) The Authority and the Corps seem to argue that the state and local law claims against the Authority are not redressable because the Corps might step in and move forward, irrespective of what the Court decides in this case. (See, e.g., Second Spiller Decl. ¶¶ 6-7) Given that no federal construction money has yet been earmarked, and the significant percentage of the project that is to be funded through non-federal means, such an argument is far too speculative.
Additionally, while the Corps states that it is the only entity that can change the diversion project and that it will not make significant changes from what was authorized in the 2014 WRRDA, (Snyder Decl. ¶ 44), that does not change the fact that successful state or local law claims against the Authority might be able to limit or restrain critical non-federal funding for the project, or show a violation of state or local law that would bar state approval of aspects of the project (including the high-hazard dam). Those possibilities would provide some redress to the JPA on its state and local law claims, if successful on the merits. In sum, the Court concludes that the JPA's alleged state and local law injuries are redressable.
The Authority contends that the JPA's MEPA and MERA claims, and state and local law permitting claims, violate the Constitution's so-called dormant Commerce Clause. Specifically, by seeking to enjoin construction on the entire diversion project, the JPA is attempting to stop construction of portions of the project that are being or will be constructed entirely in North Dakota, like the OHB ring levee. (See Third Am. Compl. at 47-48.) By doing so, the Authority argues that the JPA is impermissibly attempting to apply the laws of one state to conduct occurring wholly within another state.
The Constitution's Commerce Clause "grants Congress the authority to regulate interstate commerce." S.D. Farm Bureau, Inc. v. Hazeltine, 340 F.3d 583, 592 (8
There are multiple stages to the dormant Commerce Clause analysis. First, a state statute or regulation "is per se invalid when it has an `extraterritorial reach,' that is, when the statute has the practical effect of controlling conduct beyond the boundaries of the state." Cotto Waxo Co. v. Williams (Cotto Waxo), 46 F.3d 790, 793 (8
If a state statute or regulation is not per se invalid, the next question is what level of scrutiny applies. "If the challenged statute discriminates against interstate transactions either on its face or in practical effect, it burdens interstate commerce directly and is subject to strict scrutiny." Id. (internal quotation marks omitted). Similarly, if a state statute was enacted "for a discriminatory purpose," it is also subject to strict scrutiny. Id. This strict scrutiny standard invalidates the statute "unless the state can show that the statute serves a legitimate local purpose unrelated to economic protectionism and that the purpose could not be served as well by nondiscriminatory means." Id.
On the other hand, if the statute does not discriminate and was not enacted for a discriminatory purpose, but instead "regulates evenhandedly, then it burdens interstate commerce indirectly and is subject to a balancing test." Id. (citing Pike v. Bruce Church, Inc., 397 U.S. 137, 142 (1970)). The Pike balancing test asks whether a statute's burdens on interstate commerce are "clearly excessive in relation to the putative local benefits." Pike, 397 U.S. at 142.
Both the Authority and the State of North Dakota in its amicus brief, contend that if Minnesota's environmental laws — namely MEPA and MERA — are used as a basis to obtain the relief sought in the JPA's third amended complaint — a halt on all diversion project construction — or simply to obtain the relief sought in the injunction, it would amount to an extraterritorial application of those statutes to conduct occurring wholly outside the state. They contend that such an application would be per se invalid. Cotto Waxo, 46 F.3d at 793. They argue that the first step of the analysis, however, is to assess the scope of the relevant statutes. North Dakota v. Heydinger, 15 F.Supp.3d 891, 908-09 (D. Minn. 2014) (considering a dormant Commerce Clause challenge to a Minnesota statute that regulated the importation of power from facilities outside the state "that would contribute to statewide power sector carbon dioxide emissions," and rejecting the Minnesota commissioner defendant's attempt to construct the statute narrowly as only applying within the state to Minnesota power producers). Regardless of the scope of MERA — which they acknowledge is designed to have a broad reach beyond the state itself — they claim that since MEPA is clearly not meant to apply outside of the state, it cannot be used to achieve the relief sought in the complaint and therefore the MEPA claim must be dismissed before even reaching the dormant Commerce Clause analysis.
As to the scope of MEPA and MERA, the Court notes first that this case is distinct from Heydinger. There, the Court interpreted the scope of the statutes because the defendant state argued the statutes only applied narrowly to wholly in-state conduct. Id. at 908. Here, the MDNR takes the opposite position, contending that MEPA and MERA both apply to out-of-state conduct, at least when that conduct is committed by Minnesota government entities. (Amicus Br. at 9-14.) Nevertheless, to the extent the Court still must construe the scope of the statutes, this Court agrees with the MDNR's interpretation.
MEPA has the broad overarching purpose of ensuring that "governmental agencies contemplating taking action . . . on a proposed project must first consider the project's environmental consequences." Citizens Advocating Responsible Dev. v. Kandiyohi Cnty. Bd. of Comm'rs, 713 N.W.2d 817, 823 (Minn. 2006). The statute and its regulations codify this requirement to conduct environmental analysis before taking action. Minn. Stat. § 116D.04, subd. 2b(3) (stating that a "project may not be started and a final governmental decision may not be made to grant a permit, approve a project, or begin a project, until . . . the [EIS] has been determined adequate"); Minn. R. 4410.3100, subp. 2 (stating that prior to the completion of environmental review, "the governmental unit shall not take any action with respect to the project"). Indeed, the Authority which is undertaking the project is partially run by a Minnesota city and county (i.e., governmental units under MEPA), Minn. R. 4410.0200, subp. 33-34, and will indisputably be constructed and have effects, in part, in Minnesota. It is therefore the type of governmental action envisioned by and subject to MEPA. Id.
These mandates on Minnesota governmental units do not evaporate when those units take action on portions of cross-border project built outside of Minnesota. Holding as much would allow Minnesota cities or counties favoring a cross-border project but apprehensive about Minnesota environmental review to cross the border, start construction, and build momentum that prejudices and eviscerates the power of MEPA. Moreover, MEPA's requirements are not avoided simply because the actual memorandum of understanding for the construction of the OHB ring levee specifically was signed only by North Dakota political subdivisions. (North Dakota Br. at 6-7.) The motion to dismiss is not focused solely on the OHB ring levee's construction, but more broadly on the connection between the JPA's state law claims and the relief it seeks. More importantly, while Moorhead and Clay County may not have signed the MOU, they are equal members of the Diversion Authority with their counterpart North Dakota political subdivisions and responsible for the JPA's actions. They cannot evade MEPA's requirements by simply letting North Dakota's Authority members sign off on portions of a cross-border project that may violate MEPA, or eviscerate its review.
MERA even more obviously applies outside the state. The statute allows any person with ties to Minnesota to sue "any person" to protect the state's resources from destruction, pollution, and impairment. Minn. Stat. § 116B.03, subd. 1. A "person" is not just a Minnesota person, but is "any natural person, any state, municipality or other governmental or political subdivision . . . ." Minn. Stat. § 116B.02, subd. 2. Indeed, MERA has a long-arm provision that specifically reaches "any foreign corporation or any nonresident individual." Minn. Stat. § 116B.11, subd. 1. In sum, both MEPA and MERA are sufficiently broad in scope to achieve the relief the JPA seeks.
The Authority's dormant Commerce Clause argument centers not on a contention that MEPA or MERA are discriminatory in effect or purpose, or that they impose a "clearly excessive" burden on interstate commerce, but instead that their application here is per se invalid because they have an improper "extraterritorial reach."
The Court concludes that the application of MEPA and MERA in this case does not violate the dormant Commerce Clause. The Authority's arguments overstate the reach of the dormant Commerce Clause, and ignore critical distinctions between this case and Heydinger. First, the dormant Commerce Clause "precludes application of a state statute to commerce that takes place
The Authority's arguments to the contrary — that the OHB ring levee is of independent value, for example — ignores the project's practical reality. The Fargo-Moorhead metropolitan region is facing significant flood risks. (FEIS Executive Summary at 14.) Mitigating those risks, for the significant numbers of people living in those two communities, is a top priority of the two communities, their states, and the Corps. The OHB communities, on the other hand, have certainly experienced flooding, but do not appear to face the same risk or present the same sense of urgency, unless the diversion project is constructed. (Miller, Berg, Hovland Decl., Ex. A at 1.) In other words, the OHB ring levee is being built now not because its independent value is so great that North Dakota has prioritized the OHB communities over the Fargo-Moorhead region, but because it is an integral part of the overall diversion project. Moreover, it is a part of the diversion project that the Authority — as opposed to the Corps, which lacks earmarked federal construction funding — can easily fund and construct. The Court rejects the Authority's "independent value" argument. Enjoining construction on part of a two-state project — which is conducted by an Authority made up of Minnesota and North Dakota political subdivisions and commenced prior to the completion of Minnesota environmental review (and therefore in violation of Minnesota law) — irrespective of which side of the border that construction is located, does not contravene the bar on the extraterritorial application of state law.
To the extent the Authority contends that such a holding allows Minnesota environmental law to run amok in a different state, it ignores that the holding it seeks would have effectively the same result, just in reverse: in the unique context of a crossborder, two-state project, if political subdivisions seek to evade the environmental review of one state, they can begin construction in the other, generating momentum that neuters the first state's review. Cf. Sierra Club v. U.S. Army Corps of Eng'rs, 645 F.3d 978, 995 (8
Indeed, Heydinger demonstrates the difficulty of squarely applying the dormant Commerce Clause's extraterritoriality doctrine in this context. Colon Health Ctrs. of Am., LLC v. Hazel, 733 F.3d 535, 547 (4
Moreover, this case is also different than Heydinger in part because MEPA and MERA would be regulating Minnesota actors, in part, in this case.
Although no case deals with precisely the issue presented here, several cases do support the Court's conclusion. The Third Circuit has noted, for example, that "it is inevitable that a state's law, whether statutory or common law, will have extraterritorial effects. The Supreme Court has never suggested that the dormant Commerce Clause requires Balkanization, with each state's law stopping at the border." Instructional Sys., Inc. v. Computer Curriculum Corp., 35 F.3d 813, 825 (3d Cir. 1994). Here, laws governing a project that crosses the border between two states are bound to have some extraterritorial effect. Both the Third and Seventh Circuits have gone further, as well, acknowledging that states have an interest in these effects when a transaction involves cross-border activity. Dean Foods Co. v. Brancel, 187 F.3d 609, 619-20 (7
The Authority also argues that, even if the Court allows the JPA's MEPA and MERA claims to proceed, it must remit them under MERA's remittitur provision. Minnesota Statute § 116B.08, subd. 1, states:
The remittitur provision, however, falls under MERA. The statute's language makes plain that remittitur is appropriate, and required, when administrative proceedings, like the environmental and permitting review happening now, are required to determine whether a defendant's actions are legal. Id. But while the ongoing review may determine the project's compliance with MERA, the JPA's claims under MEPA do not require an administrative determination first. The Court concludes that the statute does not mandate remittitur where, as here, the ongoing administrative process would not determine the legality of the entirety of the Authority's conduct. Id. As a result, the Court declines to remit these proceedings.
In its motion for a preliminary injunction, the JPA asks the Court to enjoin "the defendants and those acting in concert with them [to] cease and desist work on the [OHB] Ring Dike and other work connected that would reconfigure Oxbow to make it ready for the staging and storage component of the diversion project." (Pl.'s Mot. for Prelim. Inj. at 2.) The JPA seeks to enjoin construction both because it contends that the Corps' environmental review has already violated NEPA and, therefore, construction of an illegal project should not be allowed, and, most importantly, because construction of the OHB ring levee would "compromis[e] the State of Minnesota['s] environmental review." (Id.)
While the injunction motion is directed at both defendants, it only asks the Court to enjoin the construction of the OHB ring levee, which the Authority alone is carrying out. (See Second Spiller Decl., Ex. B at 15, 26-28 (noting that the OHB ring levee work is integral to the overall project, and that the Authority would complete the ring levee and receive in-kind contribution credit for the levee's design and completion costs toward the non-federal portion of the project cost).) Indeed, the Corps conceded at argument that while the Corps had approved the levee, the authority was constructing it with its own funds. Although it is true that the Corps could decide to complete the levee in the Authority's absence, (see id. ¶ 7 ("[T]he Corps is capable of undertaking design and construction of any Project elements the non-Federal sponsors are unable to perform or prevented from performing.")), that possibility is unlikely to occur, both because no federal dollars have yet been earmarked for the project and because the parties acknowledge that the underlying issues in this case are largely ready for speedy review by the Court, save for the State of Minnesota's environmental review. As a result, the Court will consider only the JPA's arguments in support of the injunction against the Authority.
"A preliminary injunction is an extraordinary remedy never awarded as of right." Winter v. Natural Res. Def. Council, Inc., 555 U.S. 7, 24 (2008). The Court considers four factors (sometimes referred to as the Dataphase factors) in determining whether to grant preliminary injunctive relief: (1) the probability that the moving party will succeed on the merits; (2) the threat of irreparable harm to the moving party; (3) the balance of harms as between the parties; and (4) the public interest. S.J.W. ex rel. Wilson v. Lee's Summit R-7 Sch. Dist., 696 F.3d 771, 776 (8
While no single Dataphase factor is determinative, the likelihood of success on the merits is predominant in the preliminary injunction analysis. Janel Russell Designs, Inc. v. Mendelson & Assoc., Inc., 114 F.Supp.2d 856, 863 (D. Minn. 2000). The general standard is that the movant must show that it has a "fair chance of prevailing" on its claims. Planned Parenthood Minn., N.D., S.D. v. Rounds (Rounds), 530 F.3d 724, 732 (
The Corps and the Diversion Authority argue that a more stringent test should apply under this factor. In Barrett v. Claycomb, the Eighth Circuit noted that courts should analyze this first Dataphase factor under a stricter "likely to prevail" standard, versus the more lenient "fair chance of prevailing" standard, when seeking to enjoin a statute or regulation. 705 F.3d 315, 321 n.4 (8
The Court will apply the "fair chance of prevailing" standard. It is true that this project was brought about through a robust environmental planning process that involved significant public input. But the Eighth Circuit in Rounds applied the more stringent "likely to prevail" test more narrowly — not just to governmental decisions that involved public input, but to government statutes and regulations that involved debate and deliberation by an elected legislative body. See id. at 732-33 ("Only in a case such as this one, where a preliminary injunction is sought to enjoin the implementation of a duly enacted state statute, must district courts make a threshold finding that a party is likely to prevail on the merits.").
At argument, the Authority correctly noted that the project was also authorized in WRRDA, which Congress enacted. Pub. L. No. 113-121, § 7002(2)(4). But that fact highlights another distinction between this case and the Eighth Circuit's "likely to prevail" cases. First, those cases involve a straightforward attempt to enjoin the enforcement of the statute or regulation that was the product of a deliberation by an elected legislative body. See, e.g., Rounds, 530 F.3d at 726. Here, the JPA is not trying to enjoin the enforcement of WRRDA — a statute that does not appropriate funds for the diversion project — but is instead simply trying to delay the local partner's construction of part of the project pending Minnesota environmental review. Moreover, even if the JPA were trying to enjoin WRRDA's authorization of the project more broadly, that project was adopted along with other projects pursuant to the Army Corps' Chief's Report. (Chief's Report.) Congress's authorization of a project pursuant to expert agency recommendation is far different than adopting a complex statute through fulsome debate that a plaintiff seeks to permanently bar from being enforced. In sum, the Court concludes that the less stringent "fair chance of prevailing" standard should be applied in this case.
Counts III and IV of the third amended complaint allege violations of MEPA and MERA, claiming that the project will damage the environment more than necessary since feasible and prudent alternatives exist, (Third Am. Compl. ¶¶ 123-30), and that the OHB ring levee should not be constructed before the MDNR's environmental review has been completed, (id. ¶¶ 131-33). MEPA "requires that governmental agencies contemplating taking action . . . on a proposed project must first consider the project's environmental consequences." Citizens Advocating Responsible Dev., 713 N.W.2d at 823. MEPA requires the preparation of an environmental impact statement for major governmental actions that carry a "potential for significant environmental effects," and a final decision as to the adequacy of that environmental impact statement. Minn. Stat. § 116D.04, subds. 2a, 3a. The MDNR is completing an EIS for the diversion project in this case. (Second Doneen Decl. ¶ 2.)
MEPA bars a project from being "started" and a final governmental decision from being rendered until "the environmental impact statement has been determined adequate." Minn. Stat. § 116D.04, subd. 2b(3); see also Minn. R. 4410.3100, subp. 1. MEPA's implementing regulations specify that the governmental unit responsible for carrying out a project "shall not take any action with respect to the project, including the acquisition of property, if the action will prejudice the ultimate decision on the project, . . . until the final EIS has been determined adequate by the [responsible governmental unit] or [Environmental Quality Board]." Minn. R. 4410.3100, subp. 2. The regulations define a governmental unit as "any state agency and any general or specific purpose unit of government in the state, including . . . counties, towns, cities, port authorities, housing authorities, and the Metropolitan Council, but not including courts, school districts, the Iron Range Resources and Rehabilitation Board, and regional development commissions." Minn. R. 4410.0200, subp. 34. The responsible governmental unit, or RGU, is "the governmental unit that is responsible for preparation and review of environmental documents." Id., subp. 75. The RGU in this case is the MDNR. (See Second Doneen Decl. ¶ 2; First Doneen Decl., Ex. 1 at 2); see also Minn. R. 4410.4400, subp. 18.
MEPA explicitly provides a cause of action. Minn. Stat. § 116D.04, subd. 10; see also Lakes & Parks Alliance of Minneapolis v. Fed. Transit Admin., ___ F. Supp. 3d ___, No. 14-3391, 2015 WL 999945, at *14 (D. Minn. Mar. 6, 2015) (quoting Nat'l Audubon Soc'y v. Minn. Pollution Control Agency, 569 N.W.2d 211, 218 (Minn. Ct. App. 1997)). A MEPA plaintiff "aggrieved by a final decision on . . . the adequacy of an environmental impact statement is entitled to judicial review of the decision" under the standards enunciated in the Minnesota Administrative Procedure Act ("MAPA"). Minn. Stat. § 116D.04, subd. 10; see also In re Declaring a Negative Need for an Envtl. Impact Statement for the Proposed Living Word Bible Camp Project, Nos. A13-1153, A13-1157, 2014 WL 3557954, at *5 (Minn. Ct. App. July 21, 2014).
MERA "permits any person to maintain a civil action for declaratory or equitable relief against another person `for the protection of the air, water, land, or other natural resources located within the state, whether publicly or privately owned, from pollution, impairment, or destruction.'" White v. Minn. Dep't of Natural Res., 567 N.W.2d 724, 737 (Minn. Ct. App. 1997) (quoting Minn. Stat. § 116B.03, subd. 1). "Person" is defined as "any natural person, any state, municipality or other governmental or political subdivision or other public agency or instrumentality, [or] any public or private corporation. . . ." Minn. Stat. § 116B.02, subd. 2. To demonstrate a prima facie case under MERA, "a plaintiff must show (1) the existence of a protectable natural resource; and (2) that defendant's conduct will or is likely to cause pollution, impairment or destruction of that resource." White, 567 N.W.2d at 737. "Pollution, impairment or destruction" is defined as
Minn. Stat. § 116B.02, subd. 5.
The Minnesota Supreme Court has identified the following factors for determining whether conduct "materially adversely affects or is likely to materially adversely affect the environment":
State by Schaller v. Cnty. of Blue Earth, 563 N.W.2d 260, 267 (Minn. 1997).
The Court concludes that the JPA has a fair chance of prevailing on at least one of its MEPA and MERA claims. First, under MEPA, the JPA presents a strong case that action on the ring levee, which is an integral part of the overall project, (Integral Determination Report; Supplemental EA at 7), amounts to a violation of MEPA's prohibition of starting a project prior to an EIS being determined adequate. Minn. Stat. § 116D.04, subd. 2b. Indeed, since "project" is defined under MEPA as "governmental action, the results of which would cause physical manipulation of the environment, directly or indirectly," Minn. R. 4410.0200, subd. 65, and construction is defined as "any activity that directly alters the environment," Minn. R. 4410.0200, subp. 10, there is little dispute that beginning construction on a project — even if just one portion of it — constitutes the sort of initiation of action that Section 116D.04, subd. 2b proscribes at this point. Indeed, since the OHB ring levee is intended to mitigate the effects of a specific version of the diversion project, (Coleman Decl. ¶ 6), the JPA also presents a strong case that construction on the OHB ring levee "will prejudice the ultimate decision on the project" by the MDNR. Minn. R. 4410.3100, subp. 2.
Ultimately, the facts and law are straightforward. Construction is underway on a project clearly subject to the State of Minnesota's environmental review, (Ex. C, Decl. of Craig O. Evans ("Evans Decl.") ¶ 5, 10, Feb. 12, 2015, Docket No. 162), and Minnesota law bars such action until environmental review is complete, Minn. Stat. § 116D.04, subd. 2b; Minn. R. 4410.3100, subp. 2. This showing is sufficient to demonstrate a fair chance of prevailing on the merits. Of course, the JPA's MEPA claims are written more broadly, and target the entirety of the diversion project, (Third Am. Compl. ¶¶ 123-33), but in that broad scope they clearly encompass the argument that action on the OHB ring levee now, prior to the completion of state environmental review, violates MEPA and its regulations, (see id. ¶ 132). Because the Court concludes that the JPA has a fair chance of prevailing on its MEPA claim, the Court need not consider whether the JPA has a fair chance of prevailing on its MERA claim. Am. Rivers, 271 F. Supp. 2d at 250.
The Authority argues that the JPA has no fair chance of prevailing on the merits of its state law claims because the MDNR's review has effectively ejected DSA from consideration and, as a result, "all likely outcomes of MDNR review involve some variant of the current plan of the F-M Project, including the OHB Ring Levee." (Authority's Resp. to Pl.'s Mot. for Prelim. Inj. ("Authority's Prelim. Inj. Opp'n") at 27, Feb. 12, 2015, Docket No. 151 (emphasis omitted).) While this argument — which assumes that the state's decision has effectively already been made — might counter a MEPA claim under Minnesota Rule 4410.3100, subp. 2, which only bars action that "prejudice[s] the ultimate decision on the project," it ignores the broader requirements of Minnesota Statute § 116D.04, subd. 2b, which bars a project from being started until the state EIS has been determined adequate. Even if the MDNR had effectively ruled out all alternatives that would not require construction of the OHB ring levee, beginning construction prior to the completion of the state EIS could still lead to a violation of MEPA. Moreover, the MDNR itself, which is conducting the state EIS, disputes the assertion that it has definitively ruled out DSA as a flood mitigation option. (Second Doneen Decl. ¶¶ 5-7 ("Although the DSA is not being fully evaluated as part of the Draft EIS, it is incorrect to say that the DSA has been dropped from consideration in the State environmental review process at this time because the process has not been completed").) As a result, construction on the OHB ring levee, which is tied to the overall project choice of a diversion channel and high-hazard dam, could plausibly prejudice the eventual outcome of the environmental review. Minn. R. 4410.3100, subp. 2.
In addition, the Authority contends that, even if the MDNR changed course and issued an EIS that disagreed with the current plan for the diversion project, the JPA is unlikely to succeed against the OHB ring levee specifically, and an injunction is therefore not justified. Since the OHB ring levee has independent utility if constructed to levels that would prevent flooding in the OHB communities if the diversion project was never completed, and since the Authority has voluntarily agreed to limit construction of the OHB levee in 2015 to those levels, the levee is "justified by itself" such that it stands apart from the overall project, irrespective of whether the JPA can successfully assert a MEPA or MERA claim against the rest of the project. See 40 C.F.R. 1506.1(c) ("While work on a required program [EIS] is in progress . . . . agencies shall not undertake in the interim any major Federal action covered by the program which may significantly affect the quality of the human environment unless such action: (1) is justified independently of the program. . . ."); Minn. R. 4410.0200, subp. 9c ("Two projects are `connected actions' if a responsible government unit determines they are related in any of the following ways:. . . C. neither project is justified by itself.").
First, the claim that the OHB ring levee is an independent project that would have been constructed in any event is belied by the Corps' supplemental environmental assessment that labels the OHB levee as a component of the overall diversion project that serves the purpose of mitigating the effects of the to-be-constructed high-hazard dam. (Supplemental EA at 7; Coleman Decl. ¶ 6.) It may be, as several Oxbow residents — including Oxbow's mayor — state, that the ring levee will provide critical flood protection to the OHB communities. (See, e.g., Decl. of Jim Nyhof ("Nyhof Decl.") ¶¶ 8-9, Feb. 12, 2015, Docket No. 156.) But the Authority has not shown that the project stands apart, such that the North Dakota legislature would have funded it at this time irrespective of its ties to the overall diversion project. More importantly, as the MDNR points out, the Authority does not identify any provision under
To succeed in demonstrating a threat of irreparable harm, "a party must show that the harm is certain and great and of such imminence that there is a clear and present need for equitable relief." Roudachevski v. All-Am. Care Ctrs., Inc., 648 F.3d 701, 706 (8
Here, the JPA has sufficiently demonstrated a procedural harm under MEPA, by showing that the Authority is moving forward with an integral part of the diversion project prior to the completion of the MDNR's environmental review, in violation of Minnesota Statute § 116D.04, subd. 2b and Minnesota Rule 4410.3100, subp. 2. Id. The more important question is whether the JPA has shown sufficient allegations of harm to its "specific environmental interests." Id.
The Authority claims the JPA has failed to show irreparable harm, arguing that none of the declarations provided by the JPA are from officials or residents of Richland and Wilkin Counties, and therefore that they do not allege any irreparable harm to the JPA itself. Moreover, the Authority contends that the JPA's declarations allege vague and non-specific harms that are not imminent, James River Flood Control Ass'n v. Watt, 680 F.2d 543, 544-45 (8
The Court concludes that the JPA has sufficiently demonstrated irreparable harm. First, although some of the JPA's declarations are somewhat vague and not sufficiently connected to the JPA, the Authority dispenses with all of the declarations too quickly. For example, one declaration is from Pleasant Township. The chair and former chair of the JPA have submitted a declaration that clarifies that Pleasant Township, although not within Richland or Wilkin Counties, is a member of the JPA. (Miller, Berg, Hovland Decl. ¶ 3.) The Authority cites no precedent — including Minnesota's joint powers law, Minnesota Statute § 471.59 — that states that a township from one county cannot be a member of a joint powers authority that is tied to two other counties.
Finally, as to the balance of harms, the Court acknowledges that delay may result in higher construction costs, continued risk of flooding for the OHB communities, and uncertainty for homeowners within the ring levee that are attempting to sell their homes. (See, e.g., Decl. of John Rustvang ("Rustvang Decl."), Feb. 12, 2015, Docket No. 157.) But, as noted above, those arguments are belied by two points. First, Minnesota's environmental review should be completed soon and the injunction need not be a lengthy one. Second, prior to the agreement to build the ring levee, OHB-community residents noted that they themselves had created significant flood protection and that the completed diversion project was what posed the greatest risk to them. (See, e.g., Miller, Berg, Hovland Decl. Ex. A at 1.) While they do face a risk, that risk is less the motivation for the OHB ring levee than the need to pave the way for the diversion project. In sum, the JPA has shown sufficient risk of irreparable harm and the balance of harms weighs in the JPA's favor.
Finally, before granting a preliminary injunction, the Court must also consider the public interest. Gen. Motors Corp., 563 F.3d at 316. The Court finds that the public interest clearly aligns with the JPA. The costs of delaying construction, with respect to the longer-term public interest in constructing the diversion project and mitigating floods in Fargo-Moorhead, are relatively minor. But the public's interest in enforcing a state's environmental laws, and, in particular, ensuring that every major environmental action is subjected to robust review and compliant with all of the relevant federal, state, and local requirements, is significant. As a result, the Court concludes that the public interest favors granting the JPA's request for a preliminary injunction. And, since the Court finds in the JPA's favor on all four factors,
The Court emphasizes that the scope of this injunction is narrow — it applies only to construction of the OHB ring levee — and the length of the injunction may be short — it applies only until the State of Minnesota has completed its environmental review of the diversion project and the Court has had the opportunity to review the legal landscape at that time. The law simply requires that all federal and state environmental review be completed before construction begins. Construction of the OHB ring levee violates this principle and creates the real risk of a "steam roller" effect. When considering a project of this size, scope, and potential environmental impact, the review process must be completed first. When Minnesota has completed a State FEIS and an adequacy determination, the Court will further consider this case.
Based on the foregoing, and all the files, records, and proceedings herein,
1. The State of North Dakota's unopposed motion for leave to participate as amicus curiae [Docket No. 185] is
2. The federal defendants' partial motion to dismiss [Docket No. 141] the third amended complaint, Counts III, IV, and V, is
3. The Authority's motion to dismiss [Docket No. 145] the third amended complaint, Counts III, IV, and V, is
4. The JPA's motion for a preliminary injunction [Docket No. 122] is