ROBERT HOLMES BELL, UNITED STATES DISTRICT JUDGE.
This is an action for declaratory and injunctive relief filed by Plaintiff Marquette County Road Commission ("MCRC") against the United States Environmental Protection Agency ("EPA"), Susan Hedman (in her capacity as Administrator of Region V of the EPA), and the United States Army Corps of Engineers ("Corps"), pursuant to the Clean Water Act (CWA), 33 U.S.C. §§ 1251 et seq., and the Administrative Procedure Act (APA), 5 U.S.C. §§ 551 et seq. Before the Court is Defendants' motion to dismiss (ECF No.13) and Plaintiff's motion for discovery (ECF No. 25). For the reasons stated herein, Defendants' motion to dismiss will be granted and Plaintiff's motion for discovery will be denied.
Plaintiff intends to fill 25 acres of wetlands in order to construct a road in Marquette County. To do so, it needs a permit under section 404 of the CWA. As the Sixth Circuit has explained:
Friends of Crystal River v. EPA, 35 F.3d 1073, 1074-75 (6th Cir.1994).
Plaintiff sought its permit from the Michigan Department of Environmental Quality ("MDEQ"), which is the state agency responsible for implementing Michigan's federally-approved CWA wetland permit program.
Friends of Crystal River, 35 F.3d at 1075 (footnotes omitted).
Plaintiff submitted its initial application to the MDEQ in October 2011, and a revised application on January 23, 2012. The MDEQ sent copies of the application to the EPA, the Corps, and the United States Fish and Wildlife Service ("FWS"). On April 23, 2012, after consulting with the Corps and the FWS, the EPA submitted comments on the application and objected to issuance of a permit, asserting that Plaintiff's proposal failed to comply with section 404 of the CWA, 33 U.S.C. § 1344, and the 404(b)(1) guidelines, 40 C.F.R. §§ 230.1 et seq., because, among other things, it did not demonstrate that the proposed road was the "least environmentally damaging practical alternative." (Ex. 19,
Friends of Crystal River, 35 F.3d at 1075 (footnote omitted).
Over the next several months, Plaintiff, the MDEQ, and the EPA discussed the application. Plaintiff submitted a second revised application on June 29, 2012, and a third revised application on July 24, 2012. At the MDEQ's request, the EPA held a public hearing on the third revised application on August 28, 2012. On September 17, the MDEQ notified the EPA that "it would soon be in a position to issue a permit under state authorities," and urged the EPA to withdraw its objections. (Compl. ¶ 262, ECF No. 1.) Plaintiff subsequently revised its wetland mitigation plan.
On December 4, 2012, the EPA notified the MDEQ that it was withdrawing some objections, but that it continued to object to the issuance of the permit because it did not believe that Plaintiff had provided "adequate plans to minimize impacts" or a "comprehensive mitigation plan that would sufficiently compensate for unavoidable impacts." (Id. ¶ 265.) The EPA informed the MDEQ that the state had 30 days to either issue a permit which satisfied the EPA's objections or to notify the EPA of its intention to deny the permit. See 40 C.F.R. § 233.50(h)(2). Between December 4 and December 27, 2012, Plaintiff "repeatedly" contacted the EPA to obtain more specific information about the objections and the conditions necessary to satisfy them. (Compl. ¶ 271.) It did not receive the information that it desired. Instead, the EPA told Plaintiff to work with the MDEQ. On December 27, 2012, Plaintiff sent the MDEQ a detailed letter responding to the EPA's concerns and asking the state to issue a permit. (Ex. 44, MCRC letter, ECF No. 8-12.)
On January 3, 2013, the MDEQ notified the EPA that, although it was working with Plaintiff to address the EPA's objections, it would not issue a permit because of "the short time frame allowed by statute and the complexity of the issues remaining." (Ex. 45, MDEQ letter, ECF No. 8-13.) The MDEQ acknowledged that, per section 404 of the CWA, "authority to process the permit application ... is now transferred to the [Corps]." (Id.)
Thereafter, the Corps told Plaintiff that it would not issue a permit based on the third revised application submitted to the MDEQ. (Compl. ¶ 299.) Rather, in order to proceed, Plaintiff would need to submit a new application to the Corps. (Id.) Plaintiff declined to do so. (Id. ¶ 301.)
Plaintiff subsequently brought this five-count declaratory judgment action. In Count I of the complaint, Plaintiff claims that the EPA's objections to its permit application were arbitrary and capricious. In Count II, Plaintiff claims that the EPA exceeded its delegated authority by issuing objections based on requirements that are not mandated by the CWA. In Count III, Plaintiff claims that the EPA's objections failed to list the conditions necessary for a permit to issue, as required by section 404(j) of the CWA. In Count IV, Plaintiff claims that the EPA did not follow the procedural requirements of section 404(j) of the CWA. In Count V, Plaintiff claims that the Corps improperly denied its permit application by failing to act on it.
Defendants assert that the complaint should be dismissed pursuant to Rules 12(b)(1) and 12(b)(6) of the Federal Rules of Civil Procedure, because the complaint fails to state a claim upon which relief can be granted and because the Court lacks subject matter jurisdiction to adjudicate the claims against the EPA.
Defendants contend that the Court lacks subject matter jurisdiction over the claims against the EPA. Their core objection to these claims is that the EPA's actions are not reviewable because they do not constitute a "final agency action" under the APA. See 5 U.S.C. § 704. As the Sixth Circuit has explained, however, "[t]he APA is not a jurisdiction-conferring statute; it does not directly grant subject matter jurisdiction to the federal courts." Jama v. Dep't of Homeland Sec., 760 F.3d 490, 494 (6th Cir.2014). Consequently, the "final agency action requirement" of the APA is not jurisdictional. Id. at 494 n. 4. Rather, the Court's jurisdiction stems from the federal question statute, 28 U.S.C. § 1331, which "`confer[s] jurisdiction on federal courts to review agency action, regardless of whether the APA of its own force may serve as a jurisdictional predicate.'" Id. at 494 (quoting Califano v. Sanders, 430 U.S. 99, 105, 97 S.Ct. 980, 51 L.Ed.2d 192 (1977)); see also Hill v. Norton, 275 F.3d 98, 103 (D.C.Cir.2001) (noting that "challenges brought under the APA fall within the reach of the general federal jurisdiction statute, 28 U.S.C. § 1331").
Plaintiff seeks review of agency action under the APA. The Court has subject matter jurisdiction to review Plaintiff's claims under 28 U.S.C. § 1331. Thus, the Court will not dismiss any claims for lack of subject matter jurisdiction, but will review them to determine whether they state a viable cause of action.
In reviewing a Rule 12(b)(6) motion to dismiss, the Court must "`construe the complaint in the light most favorable to the plaintiff, accept its allegations as true, and draw all reasonable inferences in favor of the plaintiff,'" but it "`need not accept as true legal conclusions or unwarranted factual inferences.'" Hunter v. Sec'y of U.S. Army, 565 F.3d 986, 992 (6th Cir.2009) (quoting Jones v. City of Cincinnati, 521 F.3d 555, 559 (6th Cir.2008)). A complaint must contain "a short and plain statement of the claim showing how the pleader is entitled to relief." Fed. R. Civ. P. 8(a)(2). The purpose of this statement is to "give the defendant fair notice of what the claim is and the grounds upon which it rests." Bell Atl. Corp. v. Twombly, 550 U.S. 544, 555, 127 S.Ct. 1955, 167 L.Ed.2d 929 (2007).
The complaint need not contain detailed factual allegations, but it must include more than labels, conclusions, and formulaic recitations of the elements of a cause of action. Id. "Threadbare recitals of the elements of a cause of action, supported by mere conclusory statements, do not suffice." Ashcroft v. Iqbal, 556 U.S. 662, 678, 129 S.Ct. 1937, 173 L.Ed.2d 868 (2009) (citing Twombly, 550 U.S. at 555, 127 S.Ct. 1955). To survive a motion to dismiss under Rule 12(b)(6), a complaint must allege facts that "state a claim to relief that is plausible on its face," and that, if accepted as true, are sufficient to "raise a right to relief above the speculative level." Twombly, 550 U.S. at 555, 570, 127 S.Ct. 1955.
Section 704 of the APA authorizes judicial review of "[a]gency action made reviewable by statute and final agency action for which there is no other adequate remedy in a court...." 5 U.S.C. § 704. Neither party contends that the EPA's actions have been made reviewable by statute. Defendants assert that Plaintiff does not state a viable claim against the EPA because the EPA's actions do not constitute a "final agency action." The Court agrees.
The Court must apply a "two-prong test" to determine whether agency action is "final":
Jama, 760 F.3d at 495-96 (quoting Bennett v. Spear, 520 U.S. 154, 177-78, 117 S.Ct. 1154, 137 L.Ed.2d 281 (1997) (internal citations omitted)); see also Franklin v. Massachusetts, 505 U.S. 788, 797, 112 S.Ct. 2767, 120 L.Ed.2d 636 (1992) ("The core question is whether the agency has completed its decisionmaking process, and whether the result of that process is one that will directly affect the parties."). "An agency action is not final if it `does not of itself adversely affect complainant but only affects his rights adversely on the contingency of future administrative action.'" Jama, 760 F.3d at 496 (quoting Rochester Tel. Corp. v. United States, 307 U.S. 125, 130, 59 S.Ct. 754, 83 L.Ed. 1147 (1939)).
At issue in this case is whether the EPA's issuance of objections to a section 404 permit to be issued by a state constitutes a final agency action. The Sixth Circuit touched on this question in Friends of Crystal River, noting cases which "stand for the broad proposition that an EPA decision to object does not constitute final agency action" and "may [not] be subjected to judicial review." 35 F.3d at 1079 (referring to American Paper Inst. v. EPA, 890 F.2d 869, 875 (7th Cir.1989) (finding that the EPA's decision to object to a section 402 permit was not reviewable because it was a discretionary act); and Champion Int'l Corp. v. EPA, 850 F.2d 182 (4th Cir.1988) (finding that the EPA's unsatisfied objections are not final agency actions, and thus are not reviewable)). In American Paper, the Seventh Circuit reasoned that the EPA's decision to object is not reviewable because it is discretionary, but the Sixth Circuit stated that a "more defensible basis for determining EPA objections to be non-reviewable lies in the fact that such decisions are non-final. For example, the EPA may, after issuing an objection, decide to (1) accept the modified state permit; (2) issue a permit on its own; or (3) deny the permit." Id. at 1079 n. 11.
The foregoing discussion in Friends of Crystal River is dictum, because the Sixth Circuit was not asked to review objections to a section 404 permit. In that case, as in this one, a party sought a section 404 permit from the State of Michigan and the EPA objected. Id. at 1076. Also, like this case, the EPA and the state could not resolve their objections within the applicable time frame, so permitting authority transferred to the Corps. Id. Unlike this case, however, the EPA subsequently withdrew its objections and attempted to have permitting authority transferred back to the state. Id. at 1077. The plaintiffs filed suit, challenging the EPA's attempt restore state control over the permitting process. They did not challenge the objections themselves. The court determined that review of the EPA's withdrawal of objections and purported transfer of permitting authority to the state was appropriate because it was a "final, non-discretionary act" that, "if unreviewed, will terminate the federal government's role in th[e] case." Id. at 1079.
Although it is not binding, the Court agrees with the discussion in Friends of Crystal River regarding the reviewability of EPA objections. As discussed in more detail below, under the first prong of the Bennett analysis, those objections do not mark the consummation of its decisionmaking process. After issuing objections, the EPA continues to work with the state to fashion an appropriate permit, and the EPA could decide to withdraw the objections or accept a modified permit. In addition, under the second prong of the Bennett
Under the first Bennett prong, the EPA's objections do not mark the "consummation" of its decisionmaking process. As it did in this case, the EPA continues to work with the state and the permit applicant after issuing objections. It has authority to modify or withdraw those objections in response to hearings or further information the state or the applicant. But for the lapse in the time provided by the statute and its implementing regulations,
In the parallel context of section 402 permits, several courts have indicated that EPA objections are not final. See American Paper Inst., 890 F.2d at 875; Champion Int'l Corp., 850 F.2d at 188 ("Since the EPA clearly intends to continue the administrative process and ultimately issue or deny a permit to Champion, its objection and assumption of issuing authority are not final actions subject to judicial review...."); see also City of Ames v. Reilly, 986 F.2d 253, 255-56 (8th Cir.1993) ("Various administrative opportunities still remain: the State could issue its own permit, the EPA could withdraw its objections, or the EPA could issue a final NPDES permit."); Westvaco Corp. v. EPA, 899 F.2d 1383, 1389 (4th Cir.1990) (noting that EPA objections to section 402 permits are not final).
Before the FWPCA was amended in 1977, EPA objections to a state discharge permit under section 402 were found to be reviewable under 33 U.S.C. § 1369(b)(1)(F) (providing for review of EPA actions in "issuing or denying any permit") because, in effect, the objections functioned as a veto or denial of the permit. See Crown Simpson Pulp Co. v. Costle, 445 U.S. 193, 196, 100 S.Ct. 1093, 63 L.Ed.2d 312 (1980); Ford Motor Co. v. EPA, 567 F.2d 661, 668 (6th Cir.1977). Plaintiff cites case law relying on this authority. See Pa. Mun. Authorities Ass'n v. Horinko, 292 F.Supp.2d 95, 105 (D.D.C. 2003) ("In general, EPA objections or modifications to permits have been found to be final agency action.") (citing Crown Simpson). However, the 1977 amendments gave the EPA authority to issue the permit after its objections were not resolved
The permitting scheme for discharge permits under section 402 is similar to that for dredge-and-fill permits under section 404. As with permits under section 404, a state can obtain approval to issue permits under section 402. See 33 U.S.C. § 1342(b). In addition, the state's authority to issue the permit is subject to EPA oversight: the EPA receives notice of permit applications and can object to the issuance of a permit. Id. § 1342(d). After an objection is raised, the state has the opportunity to request a hearing; if the state does not submit a revised permit that satisfies the EPA's objections within 30 days after the hearing, or within 90 days after the objection (if no hearing is requested), then permitting authority passes from the state to the EPA. Id. § 1342(d)(4).
Plaintiff notes that there is a difference between the 402 process and the 404 process: the EPA assumes authority to issue a section 402 permit when the state cannot resolve the EPA's objections within the available time frame, whereas the Corps assumes authority to issue a section 404 permit when the state cannot resolve the EPA's objections within the available time frame.
Nevertheless, Plaintiff asserts that the EPA's unresolved objections to a section 404 permit are final with respect to the EPA because they are the EPA's final word on the matter. According to Plaintiff, after permitting authority transfers to the Corps, there is nothing left for the EPA to do. Plaintiff draws on language from Michigan Peat v. EPA, 175 F.3d 422 (6th Cir. 1999), in which the EPA initially objected to a state permit but then withdrew its objections and agreed to it. According to the court, "the logical conclusion is that the EPA's action was final. Statutorily, there was nothing left for the EPA to do...." Id. at 428.
Michigan Peat is distinguishable because Plaintiff's permit was not granted or denied. There is no question that the grant or denial of a permit is a final, reviewable decision. Moreover, it is not the case that there is nothing left for the EPA to do after it issues its objections. It can withdraw them or work with the state to resolve them. Even after permitting authority
Plaintiff also relies on Sackett v. EPA, ___ U.S. ___, 132 S.Ct. 1367, 182 L.Ed.2d 367 (2012), in which the EPA issued a compliance order asserting that the plaintiffs illegally filled wetlands in violation of the CWA. Id. at 1369. The order directed the plaintiffs to immediately undertake to restore the site in accordance with an EPA plan. Id. at 1371. The plaintiffs requested a hearing but the EPA denied their request. Id. The Court concluded that the compliance order was a final, reviewable action. Id. at 1374. As to the first prong of the Bennett analysis, the Court determined that the order marked the "consummation" of the agency's decisionmaking process because the findings and conclusions in the order were not subject to further agency review. Id. at 1372. Unlike Sackett, the EPA's determination in Plaintiff's case is subject to further agency review. The Corps is not bound by the EPA's objections; it can consider them and determine whether a permit is warranted and on what terms.
When determining whether the EPA's action was one "for which there is no other adequate remedy in a court," 5 U.S.C. § 704, the Court in Sackett rejected the government's argument that an adequate remedy for the plaintiffs would have been to seek a permit from the Corps and then seek judicial review of that decision if the Corps denied the permit. Sackett, 132 S.Ct. at 1372. According to the Court, "[t]he remedy for denial of action that might be sought from one agency does not ordinarily provide an `adequate remedy' for action already taken by another agency." Id. Plaintiff uses the foregoing statement to support its argument that the EPA's objections are final. According to Plaintiff, the availability of a permit from another agency (the Corps) is not an adequate remedy and does not render the EPA's actions non-final. This argument takes the Supreme Court's statement out of context. The Court was discussing the adequacy of available remedies, not the finality of the EPA's compliance order. It had already determined that the order was a final action. Thus, Plaintiff's reliance on the Sackett decision is misplaced.
EPA objections also fail under the second prong of the Bennett analysis, because they do not conclusively determine Plaintiff's rights or obligations, and their issuance is not an action from which legal consequences will flow. Unlike the plaintiffs in Sackett, Plaintiff is not subject to immediate consequences from the EPA's objections. The compliance order in that case required the plaintiffs to promptly restore the property according to an EPA plan and to give the EPA access to site records and documentation. Sackett, 131 S.Ct. at 1371-72. If they failed to do so, they could be subject to double penalties in a future enforcement proceeding. Id. at 1372. In contrast, the EPA's objections did not require Plaintiff to do anything that it was not already required to do. The objections appear to have prolonged the administrative process that Plaintiff started, but should Plaintiff decide to continue that process, it can do so by seeking a permit from the Corps.
Plaintiff relies on Alaska Dep't of Environmental Conservation v. EPA, 540 U.S. 461, 124 S.Ct. 983, 157 L.Ed.2d 967 (2004), in which the EPA issued three compliance orders after a state agency issued a permit under the Clean Air Act. Id. at 480-81, 124 S.Ct. 983. The compliance orders prohibited the state agency from issuing the permit unless certain conditions were met, and prohibited the applicant from beginning construction. Id. The Supreme Court noted the EPA's concession that these orders met the finality requirement, because the EPA had asserted its "final position" on the state permit, and because the compliance orders "imposed new legal obligations on" the party subject to them. Id. at 481, 124 S.Ct. 983 n. 10. Among other things, the applicant would not be able to escape the "lost costs and vulnerability to penalties ... of any [state]-permitted construction" that it endeavored. Id. at 483, 124 S.Ct. 983. In contrast, the EPA's objections to Plaintiff's permit application did not impose new legal obligations on Plaintiff.
Plaintiff argues that this transfer of authority has "fundamentally alter[ed] the substantive legal regime to which [it] is now subject." (Pl.'s Resp. in Opp'n to Mot. to Dismiss 19, ECF No. 23.) Plaintiff notes that Michigan's section 404 permit program expressly incorporates Michigan statutes and regulations, see 40 C.F.R. § 233.70 (listing the statutes and regulations incorporated by reference into Michigan's section 404 permit program), whereas a permit application submitted to the Corps is processed pursuant to the Corps' "vaguely worded" regulations. (Pl.'s Resp. 19.) Plaintiff also notes that the Corps' regulations are substantively different from the requirements of Michigan's section 404 permit program. For instance, the two programs define the term "wetland" differently. Compare Mich. Comp. Laws § 324.30301(m) with 33 C.F.R. § 328.3(c)(4). They also set forth different "public interest" factors. Compare Mich. Comp. Laws § 324.30311 with 33 C.F.R. § 320.4.
The substantive differences identified by Plaintiff are attributable to the fact that the federal government and the State of Michigan each have their own, separate and independent clean water regulations. See United States v. Rapanos, 376 F.3d 629, 646 (6th Cir.2004) (discussing the differing definitions of wetlands under Michigan and federal law), overruled on other grounds in Rapanos v. United States, 547 U.S. 715, 126 S.Ct. 2208, 165 L.Ed.2d 159 (2006). But Plaintiff is always required to comply with both sets of regulations. Even when Michigan has authority to grant a federal permit, the requirements of state law do not supplant those in the CWA. Id. at 647. CWA regulations expressly state that "[a]ny approved State Program shall, at all times, be conducted in accordance with the requirements of the Act and of this part. While States may impose more stringent requirements, they may not impose any less stringent requirements for any purpose." 40 C.F.R. § 233.1(d). Thus, regardless of whether the state or the Corps issues the CWA permit, Plaintiff is subject to the same legal obligations. In both scenarios, it must comply with both state and federal requirements.
Plaintiff also notes that there are procedural differences when obtaining a permit from the Corps rather than the state. Michigan regulations provide for shorter response times when a permit application is under state review compared to what is set forth in the Corps' regulations. In addition, when the Corps is responsible for issuing a permit, its decision is subject to the lengthy and costly review process laid out by the National Environmental Policy Act (NEPA), 42 U.S.C. § 4321 et seq. These distinctions are not sufficient in themselves to render an agency action final, however. The cost of administrative proceedings is not viewed as a legal consequence sufficient to satisfy the second prong of the Bennett analysis. See Home Builders Ass'n of Greater Chicago v. U.S. Army Corps of Eng'rs, 335 F.3d 607, 616 (7th Cir.2003) ("[T]he mere presence of increased administrative costs is insufficient to establish the finality required for nonstatutory review under the APA."); see also FTC v. Standard Oil Co. of Cal., 449 U.S. 232, 242, 101 S.Ct. 488, 66 L.Ed.2d 416 (1980) (noting that complying with administrative
In summary, Plaintiff argues that the EPA's objections have left it with essentially two choices: (1) construct the road and risk enforcement action or (2) go through the "costly, time-consuming, and futile exercise of submitting an entirely new application to the Corps." (Pl.'s Resp. 11.) But Plaintiff was subject to the first consequence even before the EPA issued its objections. There is no question that Plaintiff must obtain a permit in order to complete its construction project; the EPA's objections have not altered that fact. The second consequence is merely a byproduct of the scheme created by Congress to resolve the state's failure to address concerns raised by the EPA in a timely manner. The cost of complying with this scheme is not sufficient to render the EPA's objections to its permit application final and reviewable. Finally, Plaintiff's assertion that an application to the Corps would be "futile" is unsupported, as discussed in Section VI below. Because the EPA's actions do not satisfy either prong of the Bennett analysis, they are not reviewable under the APA.
In Count II of the complaint, Plaintiff contends that the EPA engaged in ultra vires action outside of its delegated authority. Plaintiff asserts that the EPA did not comply with section 404(j), which permits the EPA to raise objections to a state permit that falls "outside the requirements" of section 404 and the 404(b)(1) guidelines. 33 U.S.C. § 1344(j). Plaintiff contends that the EPA raised issues that are matters of discretion for the MDEQ and, thus, are not "requirements" of section 404 or the 404(b) guidelines. In addition, Plaintiff asserts that the EPA failed to list the conditions necessary for issuance of a permit, as required by 33 U.S.C. § 1344(j). Thus, Plaintiff contends that, even if the EPA's actions are not final and reviewable under 5 U.S.C. § 704, Plaintiff is entitled to review under the exception in Leedom v. Kyne, 358 U.S. 184, 79 S.Ct. 180, 3 L.Ed.2d 210 (1958).
In Leedom, the Supreme Court determined that a statutory bar to judicial review would not apply where an agency acted "in excess of its delegated powers and contrary to a specific prohibition" in a statute. Id. at 188, 79 S.Ct. 180. The Sixth
Plaintiff's assertion that the EPA failed to list the conditions necessary for a permit to issue ignores the December 4, 2012, letter from the EPA, which provided a detailed list of such conditions. (See Ex. 39, 12/4/2012 EPA letter, ECF No. 8-7, PageID.1042-44.) For example, with regard to mitigation of direct impacts, the letter specified, in part:
(Id. at PageID.1042 (footnotes omitted).) Thus, Plaintiff's assertion is not supported by the record.
Regarding the EPA objections that were allegedly based on factors within the discretion of the state rather than requirements of section 404(b)(1), Plaintiff fails to satisfy the narrow exception provided by Leedom. There is no dispute that the EPA has statutory authority to issue objections to a state permit. Nevertheless, Plaintiff contends that the following statements by
Contrary to Plaintiff's assertion, neither the CWA nor the regulations give exclusive authority or discretion to the state to determine whether any aspect of the CWA or its guidelines have been satisfied. See 40 C.F.R. § 233.50(e) (permitting EPA objections based on "the Regional Administrator's determination that the proposed permit is ... outside [the] requirements of the Act, these regulations, or the 404(b)(1) Guidelines.") (emphasis added). Moreover, the guidelines themselves do not distinguish between "requirements" and other factors. Indeed, many of the guidelines are inherently qualitative and/or quantitative. See, e.g., 40 C.F.R. § 230.1 (noting the fundamental precept of the guidelines that the discharge of dredge and fill material not have an "unacceptable" adverse impact); id. § 230.5(c), (j) (requiring assessment of "practicable" alternatives and plans to "minimize" the impacts of the discharge); id. § 230.10(a), (c)-(d) (prohibiting discharge if there is a "practicable" alternative with a less adverse impact, if the discharge will cause "significant" degradation of the waters of the United States, or if steps have not been taken to "minimize" potential adverse impacts); id. § 230.94 (requiring preparation of a mitigation plan "commensurate" with the scale and scope of the impacts). But it does not necessarily follow that they are "discretionary," or that the state has sole authority to determine whether they have been satisfied.
Plaintiff's narrow view of the EPA's authority is not supported by the statute as a whole or its legislative history. Section 402 of the CWA uses similar language, stating that the EPA can object to a state permit if it is "outside the guidelines and requirements of this chapter." 33 U.S.C. § 1342(d)(2). But no court has held that this language limits the scope of EPA objections to "qualitative" or "quantitative" factors. Indeed, the Senate Report to the 1977 amendments makes clear that Congress wanted "strong EPA oversight" of state programs, and that "the authority of the [EPA] to assure compliance with guidelines in the issuance and enforcement of permits ... is in no way diminished" by the establishment of a state permit program. S. Rep. No. 95-370, at 73, 78 (1977) (emphasis added), as reprinted in 1977 U.S.C.C.A.N. 4326, 4398, 4403. Similarly, the Sixth Circuit has observed:
Friends of Crystal River, 35 F.3d at 1078 (emphasis added). In short, because the EPA was authorized to object to the proposed permit, and because its objections were based on the guidelines, they were by no means a "patent violation" of the EPA's delegated authority or a "manifest infringement" of Plaintiff's rights. Greater Detroit Res. Recovery Auth., 916 F.2d at 323. Consequently, Leedom does not apply.
In Count V of the complaint, Plaintiff alleges that the Corps failed to take any action on the permit application that it filed with the MDEQ, which constituted a "constructive denial" of that application. (Compl. ¶ 391.) The Corps "took the position that Plaintiff would need to file an entirely new permit application with the Corps," but Plaintiff declined to file a new application. (Id. at ¶¶ 14, 299, 301.) As relief, Plaintiff seeks an order setting aside the "constructive denial" of its application and requiring the Corps to approve the permit. (Id. ¶ 398.) Defendants assert that these allegations do not state a viable claim.
Norton v. S. Utah Wilderness Alliance, 542 U.S. 55, 63-64, 124 S.Ct. 2373, 159 L.Ed.2d 137 (2004) (footnote omitted).
Section 404 of the CWA provides that, when the state does not submit a revised permit to satisfy the EPA's objections within the requisite time period, "the Secretary may issue the permit pursuant to subsection (a) or (e) of this section...." 33 U.S.C. § 1344(j) (emphasis added). This provision indicates the Corps assumes authority to issue the permit; it does not require the Corps to act. Moreover, it refers to subsection (a), which states that the Corps "may issue permits, after notice and opportunity for public hearings," and that the Corps must publish notice within 15 days after the applicant "submits all the information required to complete an application for a permit under this subsection[.]" 33 U.S.C. § 1344(a). Thus, before the Corps is required to act on an application, the applicant must provide the Corps with all the information required to complete one. Id. Notably, subsection (a) applies to all applications for a section 404 permit from the Corps, including those in states where there is no federally-approved state permitting program. Consequently, when read in conjunction with subsection (a), subsection (j) cannot be interpreted as requiring the Corps to act on a permit application submitted to the state.
Corps regulations provide specific requirements for a permit application, including the specific form that must be used in the application, the contents of the application, and the applicable fees. 33
Plaintiff relies on an EPA regulation which states that, when the EPA's objections are not resolved by the state, "the [Corps] shall process the permit application." 40 C.F.R. § 233.50(j). However, this regulation does not specify or mandate any procedure that the Corps must follow when processing permit applications, let alone require that the Corps consider the application submitted to the state. Moreover, the Corps is responsible for adopting its own procedures for processing permit applications; it is not required to follow regulations developed by the EPA. Cf. Coeur Alaska, Inc. v. Se. Alaska Conservation Council, 557 U.S. 261, 273-74, 129 S.Ct. 2458, 174 L.Ed.2d 193 (2009) (delineating EPA and Corps responsibilities for section 404 permits). The Corps has not adopted specific procedures for processing permit applications when authority to issue a section 404 permit transfers from the state to the Corps. Instead, it has decided to follow the same procedures for all such permit applications. See 33 C.F.R. § 325.1 (noting that "[t]he processing procedures of this part apply to any Department of the Army (DA) permit"); see also 33 C.F.R. § 325.2 (setting forth procedures for processing permit applications).
Practical considerations support the Corps' approach. Although Plaintiff would require the Corps to act as soon as it assumes authority to issue the permit, it cannot do so without knowing which materials are relevant and whether it has received all the necessary information. Even the most recent version of an application submitted to the state may not be relevant. After the EPA issues its objections, the applicant has an opportunity to continue working with the state to resolve them. Substantial changes could be made to the applicant's proposal during that time, and an applicant could decide to submit an application to the Corps that contains these additional revisions. In addition, after permitting authority transfers to the Corps, the applicant could decide to delay its application and make further revisions before seeking a permit from the Corps. If the applicant believes that the EPA's objections are invalid, it could ignore those objections and modify its application accordingly. In Plaintiff's case, it revised its application several times following the EPA's comments and objections. Even after the EPA objected to Plaintiff's third revised application in December 2012, Plaintiff continued in its attempts to satisfy those objections. The Corps should not be expected to assume that the most recent version of the application that Plaintiff submitted to the state is the relevant application for review, or that the Corps possesses all the relevant information needed to evaluate it.
Plaintiff contends that it should not be required to file an application with the Corps because such an application would be futile. Plaintiff relies on comments that the Corps made to Plaintiff's first revised application in March 2012, in which the Corps questioned the stated purpose of the project and identified other deficiencies. (Compl. ¶¶ 209-11.) Plaintiff asserts that there "is no reason to think the Corps would now reverse course." (Pl.'s Resp. 33.) But Plaintiff revised its application several times after the Corps made comments. There is no reason to think that the same issues would arise for a different application. In any event, Plaintiff's belief that an application would be futile does not excuse it from filing one before seeking judicial review.
In short, Plaintiff does not state a claim based on the Corps' failure to act. The Corps was not legally required to act on the application that Plaintiff filed with the state. The Corps did not deny its application, because Plaintiff declined to file one in accordance with the Corps' procedures. If Plaintiff wanted the Corps to make a determination on its request for a permit, it could have filed a proper application.
Moreover, even if Plaintiff stated a valid claim against the Corps, the relief that it requests is not available. Plaintiff asks the Court to have the Corps issue the permit, but the Court does not have authority to do so. The APA "empowers a court only to compel an agency `to perform a ministerial or non-discretionary act,' or `to take action upon a matter, without directing how it shall act.'" Norton, 542 U.S. at 64, 124 S.Ct. 2373 (quoting Attorney General's Manual on the Administrative Procedure Act 108 (1947)). Because Plaintiff claims that the Corps failed to act on its application, the Court can direct the Corps to consider that application; it cannot require the Corps to issue the permit.
In summary, Defendants' motion to dismiss will be granted. Plaintiff fails to state a claim against the EPA (and the EPA administrator) because the EPA's actions are not reviewable under the APA. Plaintiff fails to state a claim against the Corps because the Corps was not required to act until Plaintiff filed a proper application with the Corps. Finally, because the complaint is subject to dismissal for failure to state a claim, Plaintiff's motion for discovery will be denied as moot.
An order and judgment will be entered consistent with this Opinion.