Rulings by summary order do not have precedential effect. Citation to a summary order filed on or after January 1, 2007, is permitted and is governed by Federal Rule of Appellate Procedure 32.1 and this Court's Local Rule 32.1.1. When citing a summary order in a document filed with this Court, a party must cite either the Federal Appendix or an electronic database (with the notation "summary order"). A party citing a summary order must serve a copy of it on any party not represented by counsel.
Plaintiff-appellant Triodetic Inc. appeals from the District Court's November 7, 2013 entry of summary judgment in favor of defendants on plaintiff's claims for a maritime lien, unjust enrichment, and conversion. We assume the parties' familiarity with the underlying facts, the procedural history of the case, and the issues on appeal.
We review a grant of summary judgment de novo, viewing the facts "in the light most favorable to the non-moving party and draw[ing] all reasonable inferences in that party's favor." Cox v. Warwick Valley Cent. Sch. Dist., 654 F.3d 267, 271 (2d Cir. 2011). Summary judgment is appropriate where "there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law." Fed. R. Civ. P. 56(a). "Where the record taken as a whole could not lead a rational trier of fact to find for the non-moving party, there is no `genuine issue for trial.'" Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587 (1986).
Upon de novo review of the record and relevant law, we conclude that the District Court properly granted summary judgment in favor of defendants on plaintiff's claim for a maritime lien. Plaintiff expressly agreed that no maritime lien could be deployed with respect to its purchase order with contractor Derecktor Shipyard Conn. LLC ("Derecktor"). The purchase order expressly provides that:
The phrase "Vessel for which the items are being utilized" plainly refers to the vessel M/V Hornblower Hybrid, for which plaintiff was subcontracted to construct and install an atrium.
The District Court also properly granted summary judgment in favor of defendants on plaintiff's unjust enrichment claim. There is no evidence in the record that defendants expressly consented to undertake Derecktor's payment obligations to plaintiff after it became apparent that Derecktor would be unable to pay, nor do the circumstances surrounding the parties' dealings give rise to an obligation to pay. See Perma Pave Contracting Corp. v. Paerdegat Boat & Racquet Club, Inc., 549 N.Y.S.2d 57, 59 (2d Dep't 1989) ("[I]t is a firmly established principle that a property owner who contracts with a general contractor does not become liable to a subcontractor on a quasi-contract theory unless it expressly consents to pay for the subcontractor's performance.") (rejecting plaintiff's unjust enrichment claim); U.S. E. Telecommunications, Inc. v. US W. Commc'ns Servs., Inc., 38 F.3d 1289, 1298 (2d Cir. 1994) ("[U]nder New York law, a subcontractor may recover from a landowner (and a sub-subcontractor from a general contractor), even when a separate contract exists between the subcontractor and general contractor, if the owner has agreed to pay the general contractor's debt or if the circumstances surrounding the parties' dealings can be found to have given rise to an obligation to pay.").
Finally, the District Court properly granted summary judgment in favor of defendants on plaintiff's conversion claim. Although the District Court did not address whether the bills of lading were non-negotiable, and apparently overlooked the fact that some of the bills of lading did not list Derecktor as consignee, plaintiff never raised these arguments in its opposition to defendants' motion for summary judgment. Accordingly, these arguments were waived. See Palmieri v. Lynch, 392 F.3d 73, 87 (2d Cir. 2004).
We have considered all of the arguments raised by plaintiff on appeal and find them to be without merit. For the reasons stated above, we