DERRICK K. WATSON, District Judge.
This action arises out of an infrastructure construction project at Wheeler Army Airfield in Oahu, Hawaii. The prime contractor hired by the federal government, Defendant David Boland, Inc., retained Plaintiff Kingston Environmental Services, Inc., as a subcontractor to perform part of the work. By all accounts, there were numerous problems during the construction. Kingston brings this lawsuit under the Miller Act, 40 U.S.C. Sections 3131-34, and holds Boland responsible for the construction delays that occurred and the losses it allegedly suffered as a result.
In 2017, this Court granted in part Defendants' motion for summary judgment, stayed the case until Kingston had complied with the remedial administrative procedures in the subcontract, and reserved ruling on the issue of whether Kingston's claims were barred by the "no damages for delay" provision in the subcontract. Dkt. No. 145. Now that the stay has been lifted, this matter is before the Court on Defendants' renewed motion for summary judgment as to the enforceability of the "no damages for delay" provision. Dkt. No. 185. Because enforcement of the "no damages for delay" provision hinges on material facts disputed by the parties, Defendants' motion is DENIED.
On June 29, 2012, the United States Army Corps of Engineers (USACE or Government) entered into a contract with Defendant David Boland, Inc., (Boland), making Boland the primary contractor for a construction project known as the Combat Aviation Brigade Infrastructure, Phase I, Wheeler Army Airfield, Oahu, Hawaii (the Project).
Roughly a month after mobilizing, Kingston encountered obstacles. First, Kingston was unable to use its preferred labor force. Dkt. No. 116-4, ¶ 13. In particular, an internal email at Kingston states:
Id. Second, Kingston ended up procuring rental equipment and labor at much higher rates than it had accounted for.
By March 2014, Kingston had completed approximately 46% of the work it agreed to perform. Dkt. No. 134-2, ¶ 8. On March 6, 2014, Boland and Kingston revised the Subcontract by executing Change Order No. 10, under which, inter alia: (a) the scope of the work Kingston was to perform was reduced by over $8.4 million; and (b) Boland and Kingston "waiv[ed] and release[ed]" any claims they had against each other "resulting directly from delays in performance . . . and the schedule impacts of such delays caused [at] any time prior to the date" of Change Order No. 10.
Boland and Kingston later revised the Subcontract on at least three separate occasions by executing three additional Change Orders—Change Order Nos. 12, 13, and 14—which were respectively executed on June 20, 2014, September 5, 2014, and September 22, 2015.
Kingston filed this action on April 29, 2016, seeking payment from Western Surety under its Miller Act bonds (Count I) and alleging that Boland breached the Subcontract (Count II). Dkt. No. 1, ¶¶ 38-50. Boland and Western Surety moved for partial summary judgment, arguing that: (1) Kingston failed to comply with the administrative remedial procedure mandated in Paragraph 13A of the Subcontract; and (2) Kingston's delay claims are barred by the "no damage for delay" clause in Paragraph 12.B of the Subcontract.
Once the stay was lifted on June 28, 2019 (Dkt. No. 178), Defendants renewed their motion for partial summary judgment on the issue of the enforceability of the "no damages for delay" provision in the Subcontract, and incorporated the briefing and argument submitted as part of their initial motion for partial summary judgment. Dkt. No. 185 at 5. Plaintiffs agreed that the matter was "procedurally ripe" and should be decided on the briefing and oral argument previously submitted. Dkt. No. 188. As a result, the Court took the matter under submission without any further briefing or argument. Dkt. No. 189.
Summary judgment under Rule 56 is appropriate only when the Court, viewing the record as a whole and in the light most favorable to the nonmoving party, determines that there exists no genuine issue of material fact and that the moving party is entitled to judgment as a matter of law. See Fed.R.Civ.P. 56(a); Celotex Corp. v. Catrett, 477 U.S. 317, 322-24 (1986); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248-50 (1986). A genuine issue of material fact exists when, "there is sufficient evidence favoring the nonmoving party for a jury to return a verdict for that party." Anderson, 477 U.S. at 249; see Scott v. Harris, 550 U.S. 372, 380 (2007). "[A] complete failure of proof concerning an essential element" of a claim "necessarily renders all other facts immaterial." Celotex, 477 U.S. at 323.
"A moving party without the ultimate burden of persuasion at trial"—such as Boland in this case—"has both the initial burden of production and the ultimate burden of persuasion on a motion for summary judgment." Nissan Fire & Marine Ins. Co. v. Fritz Cos., 210 F.3d 1099, 1102 (9th Cir. 2000). To meet its initial burden, the moving party must either: (1) "submit affirmative evidence that negates an essential element of the nonmoving party's claim"; or (2) "demonstrate to the court that the nonmoving party's evidence is insufficient to establish an essential element" of its claim at trial. Celotex, 477 U.S. at 331; Jones v. Williams, 791 F.3d 1023, 1030-31 (9th Cir. 2015); cf. Fed.R.Civ.P. 56(c).
Once the movant has done so, the opposing party cannot rely on the mere hope that the trier of fact will disbelieve the movant's evidence, but instead "must present affirmative evidence" in order to avoid summary judgment. See, e.g., Anderson, 477 U.S. at 256-57; Teamsters Local Union No. 117 v. Wash. Dep't of Corr., 789 F.3d 979, 994 (9th Cir. 2015); Fed.R.Civ.P. 56(c)(1). This requires "more than simply show[ing] that there is some metaphysical doubt as to the material facts." Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 586 (1986). By the same token, "evidence [that] is merely colorable, or is not significantly probative" is not enough, Anderson, 477 U.S. at 249-50, and "a scintilla of evidence in support of the plaintiff's position will be insufficient." Id. at 252. To the extent probative, supporting evidence does exist, it must be "set forth in the opposing papers with adequate references so that it could conveniently be found." Carmen v. S.F. Unified Sch. Dist., 237 F.3d 1026, 1031 (9th Cir. 2001); S. Cal. Gas Co. v. City of Santa Ana, 336 F.3d 885, 889 (9th Cir. 2003) ("General references without page or line numbers are not sufficiently specific.").
Although a court may consider evidence in the record not cited by the parties, Fed.R.Civ.P. 56(c)(3), "it is not [the court's] task . . . to scour the record in search of a genuine issue of triable fact." Californians for Renewable Energy v. Cal. PUC, 922 F.3d 929, 936 (9th Cir. 2019) (citations and internal quotation marks omitted); Fed.R.Civ.P. 56(c)(1)(a) (providing that a party "must support [its] assertion[s] by citing to particular parts of materials in the record, including depositions"); Fed.R.Civ.P. 56(c)(3) (a "court need consider only the cited materials").
The only issue before the Court is whether Kingston's delay claims are barred by the "no damages for delay" provision in Paragraph 12.B of the Subcontract. That provision states:
Dkt. No. 116-2 at 6-7 (emphasis added). The parties agree that the issue is governed by Florida law,
Kingston maintains that this case falls within the exception to the rule that delay clauses are enforced. Dkt. No. 133 at 15-16, 27.
At the outset, it bears emphasis that "whether a party has actively interfered with another party's contractual obligation is a question usually inappropriate for resolution at the summary judgment stage" because the issue is "highly case-specific and fact intensive." United States ex rel. Dura-Stress, Inc. v. David Boland, Inc., No. 6:05-cv-549-Orl-19JGG, 2006 WL 2683304, at *4 (M.D. Fla. Sept. 18, 2006) (collecting cases). Although not binding, Dura-Stress involved facts similar to this case and the reasoning in Dura-Stress is persuasive. There, the government described Boland as having a "cavalier attitude" and that Boland had exhibited performance that was "substandard." Id. at *5. Further, the parties disputed whether Boland failed to "timely and adequately respond" to the subcontractor's requests for information and whether Boland "knowingly contribut[ed] to a lengthy delay in the installation of the pilings" by failing to have the site ready for the subcontractor. Id. at *4-5. As a result, the court ultimately concluded that summary judgment was inappropriate because the parties disputed several facts pertaining to whether Boland engaged in active interference with the subcontractor's performance. Id. at *4, *6.
The situation and result here are no different than in Dura-Stress. The parties dispute facts that are relevant to the enforceability of the "no damages for delay" provision, and viewing the evidence in the light most favorable to Kingston, a jury could conclude that Boland knowingly delayed, or actively interfered with, Kingston's performance.
First, there is evidence in the correspondence between USACE and Boland to overcome the "no damages for delay" clause. Just as the government described Boland as having a "cavalier attitude" in Dura-Stress, here the USACE stated that Boland had an "unresponsive attitude." Dkt. No. 134-10 at 2. The USACE also noted that (1) Boland's "project schedules are fatally flawed" because they contain "erroneous logic ties, inaccurate scope of work, and unrealistic activity durations," and therefore "cannot be utilized as an accurate and reliable tool"; and (2) "[Boland]'s poor schedule management has been and continues to be a major detriment to the project." Dkt. No. 134-7 at 1-2. USACE later scorned Boland for continuing "to manipulate the schedule logic and durations to minimize and eliminate
Second, Bob Wysocki, the General Manager for Kingston, testified that Boland "knowingly and willfully" prevented Kingston from performing its contractual obligations. See supra note 5; Dkt. No. 134-2 at ¶¶ 4-7. For instance, Wysocki testified that Boland, "prevent[ed] Kingston from accessing construction areas as planned"; "fail[ed] to timely or diligently address and resolve issues to allow Kingston's work to proceed"; "fail[ed] to complete other activities on site that disrupted and negatively impacted Kingston in the performance of its work"; "chang[ed] site access points due to incomplete Boland work"; and, as in Dura-Stress, "fail[ed] to have areas ready for Kingston to perform its work." Id. at ¶ 4; Dura-Stress, 2006 WL 2683304, at *5.
These facts support the inference that Boland's conduct was more than "mere lethargy or bureaucratic bungling." Southern Gulf, 238 So. 2d at 459; McIntire, 318 So. 2d at 199-200. As such, the evidence is enough for a jury to find that Boland "willfully and knowingly delayed" Kingston's ability to perform under the contract. See Newberry Square Dev. Corp. v. Southern Landmark, Inc., 578 So.2d 750, 752 (Fla. 1st Dist.Ct.App.1991) (concluding "no damage for delay" clause did not preclude plaintiff's recovery because the evidence that defendant "delayed in executing change orders and required that construction not proceed without such orders [and] . . . repeatedly failed to make timely payments required by the contract" was "adequate evidence to present a jury question as to whether [defendant] actively impeded, or willfully and knowingly delayed, [plaintiff]'s ability to timely perform under the contract"). Of course, Boland disputes the veracity of the charges that it engaged in such conduct. Dkt. No. 115-1 at 16.
Having carefully reviewed the record in the light most favorable to Kingston, the Court is convinced that a jury trial is warranted. Material questions of fact exist as to whether Boland "knowingly delayed," or "actively interfered" with, Kingston's performance under the Subcontract so as to overcome the "no damages for delay" provision in the Subcontract. Boland's motion is therefore DENIED.
For the reasons set forth herein, Defendants' Renewed Motion for Partial Summary Judgment (Dkt. No. 185) is DENIED.
IT IS SO ORDERED.