DAVID SAM, Senior District Judge.
This case involves an action for construction lien foreclosure filed by Garlett Construction, Inc. ("GCI") relating to the construction of a residence in Moab, Utah for Defendants Curtis and Genevieve Leonard (the "Leonards").
Under Federal Rule of Civil Procedure 12(b)(6) the Leonards move to dismiss the Complaint contending that GCI cannot state a claim under Utah's foreclosure statues because (1) "GCI is an unlicensed contractor who lacks standing under Utah Code Ann. § 58-55-604 to bring a collection action"; (2) "GCI's preliminary notice of construction lien... is defective, and ... cannot be foreclosed upon by the Court"; and (3) GCI "executed lien waivers precluding any claim to foreclose a construction lien at the Leonard Residence". Mot. at 2.
Because matters outside the pleadings have been presented by the parties which will not be excluded by the Court, the Motion must be treated as one for summary judgment under Rule 56. Fed. R. Civ. P. 12(d).
Under Federal Rule of Civil Procedure 56, summary judgment is proper only when the pleadings, affidavits, depositions or admissions establish there is no genuine issue regarding any material fact and the moving party is entitled to judgment as a matter of law. The burden of establishing the nonexistence of a genuine issue of material fact is on the moving party.
The central inquiry is "whether the evidence presents a sufficient disagreement to require submission to a jury or whether it is so one-sided that one party must prevail as a matter of law." Id. If the nonmoving party cannot muster sufficient evidence to make out a triable issue of fact on his claim, a trial would be useless and the moving party is entitled to summary judgment as a matter of law. Celotex, 477 U.S. 242.
The Leonards first assert that because GCI is not a licensed contractor in the State of Utah it lacks standing to bring a claim for construction services which requires a valid contractor's license.
"In Utah a contractor that is a business entity can only be licensed through a natural person know as a `qualifier' — which individual must pass the required examination and which individual must exercise `material authority' in the conduct of the business entity's contracting business. Utah Code Ann. § 58-55-304." Mem. Opp'n at 4. GCI has provided documentation that the d/b/a "Chuck Garlett Construction" is a licensed contractor and that Chuck Garlett is the qualifier for Chuck Garlett Construction. See Mem. Opp'n, Ex. A
As GCI urges, simply because the d/b/a Chuck Garlett Construction, and not GCI, is the entity listed by the state as the licensee, is not a reason to grant the relief requested by the Leonards. See Fillmore Products, Inc., v. Western States Paving, Inc., 561 P.2d 687, 689, 690 (Utah 1977)(quotation marks and citation omitted) (Utah "has not applied the general rule of denying relief to unlicensed persons ... inflexibly or too broadly" and the general rule should not "become an unwarranted shield for avoidance of a just obligation"). See also A.K. & R. Whipple Plumbing and Heating v. Aspen Construction, 977 F.2d 518, 523 (Utah App.), cert denied, 997 P.2d 518 (1999) ("an unlicensed contractor may recover if the work it performed was supervised by a licensed contractor" or "if the reason a contractor fails to obtain a proper license is minor and does not undermine its ability to perform work, the unlicensed contractor may recover"). The Court agrees with GCI that this is not a case involving a claim by an unlicensed contractor. By their allegations, the Leonards have acknowledged that GCI "is a Utah corporation ... owned and/or operated by ... Chuck Garlett." Am. Compl. at ¶ 6. It is undisputed that GCI ia a family business and the Chuck Garlett is its president and sole shareholder. It is also undisputed that the work performed was supervised and performed by a licensed contractor. In any event, the Court also agrees with Plaintiff that "the reason GCI is arguably unlicensed is certainly minor, i.e., application for the license by the qualifier Chuck Garlett in the name of a d/b/a — `Chuck Garlett Construction' — as opposed to "Garlett Construction, Inc.'" Mem. Opp'n at 5. The Leonards' position on this issue, therefore, is rejected.
Next, the Leonards contend that GCI's preliminary notice of construction lien is defective because GCI failed to plead that it entered into a written contract and provided notice to the Leonards as homeowners regarding "what actions are necessary for the owner to be protected ... from the maintaining of a mechanic's lien" as required by Utah Code Ann. § 38-11-108.
Utah's Residence Lien Restriction and Lien Recovery Fund Act, Utah Code Ann. §§ 38-11-101 38-11-302 ("URLRLRA") requires that an "original contractor" or "real estate developer" state in a written contract with the owner what actions are necessary for the owner to be protected under the URLRLRA. It is undisputed that GCI was not the original contractor or real estate developer. Utah Code Ann § 38-11-108(1), therefore, has no application to GCI, and the Leonards' position on this issue is rejected.
The Leonards' further assert, as an alternative position, that GCI's preliminary notice is defective under Utah Code Ann. § 38-1a-501(h)(ii), because it states that GCI was employed by the Leonards, rather than the General Contractor White Horse.
A construction lien claimant must file a preliminary notice with the Utah State Construction Registry in order to claim a construction lien. Utah Code Ann. § 38-1a-501. GCI has documented that it "did file a preliminary notice with the SCR [Utah State Construction Registry]." Mem. Opp'n at 7. See Mem. Opp'n, Ex. B. On its face Exhibit B reflects that the Leonards are the owner of the project for which GCI worked as a contractor. There is no specific representation that GCI was employed by or directly contracted with the Leonards as they allege. In short, the Court is not persuaded that the Leonards have carried their burden of proof on this issue as GCI suggests.
Mem. Opp'n at 7 n. 9. Based on the present record, the Court concludes that the Leonards have not met their burden of proof and their position on this issue is rejected.
Finally, the Leonards urge that because Chuck Garlett Construction executed unconditional lien waivers it waived its right to foreclose via lien waivers. At a minimum, the Leonards contend that the lien waivers for construction work performed in April, June and July of 2015, preclude recovery of a portion of the amount claimed since GCI claims entitlement to a lien of $61,094 for the period of January 5, 2015 to August 10, 2015.
The Court agrees with GCI that the Leonards "Unconditional Lien Waivers" are unenforceable. "[T]he sole criteria for the execution of an effective lien waiver are ... the execution of a `waiver and release signed by the lien claimant or the lien claimant's authorized agent,' and the receipt of `payment of the amount identified in the waiver and release.' Lane Myers Construction, LLC v. National City Bank, 342 P.3d 749, 753 (Utah 2014). The Leonards' Unconditional Lien Waivers" do not identify any amount for which those waivers purportedly apply, nor is there any evidence of record that GCI was paid any amounts in connection with those waivers.
For the reasons stated, the Leonards' Motion to Dismiss (Doc. #38) which the Court, after notice, converted to one for Summary Judgment, is denied.
IT IS SO ORDERED.