ANDREWS, Presiding Judge.
R.G. Williams Construction, Inc. (Williams), the general contractor on a construction project, hired Atlanta Flooring Design Centers, Inc. (AFDC) as the flooring subcontractor for the project. Williams and AFDC entered into a written contract governing the work on the project which included a provision requiring that disputes under the contract be resolved by arbitration, and further stating that:
After a dispute was submitted to arbitration, and the arbitrator rendered an award, AFDC filed a motion pursuant to OCGA § 9-9-13(a) of the Georgia Arbitration Code (GAC) seeking a court order vacating the award on the basis that its rights were prejudiced in the arbitration proceedings on the statutory grounds set forth in OCGA § 9-9-13(b). Williams responded and moved to dismiss AFDC's motion on the basis that the parties' contractual agreement "not to challenge the validity of the arbitration or the award" precluded AFDC from seeking to vacate the award under the GAC. The reviewing court ruled that the contract language unambiguously precluded any challenge to the arbitration or the award pursuant to OCGA § 9-9-13; found that the agreement not to challenge the arbitration award was not unconscionable; and granted the motion to dismiss AFDC's motion to vacate the award. AFDC appeals from the dismissal order. For the following reason, we find the reviewing court erred and reverse.
"The [GAC] requires a trial court to confirm an award upon the timely application of a party to the award, unless one of the statutory grounds for vacating or modifying the award is established." Greene v. Hundley, 266 Ga. 592, 595, 468 S.E.2d 350 (1996); OCGA §§ 9-9-12; 9-9-13; 9-9-14. As quoted above, the contractual language at issue retains a party's right to have the arbitration award confirmed and made a judgment of the court pursuant to the GAC, while waiving any right for a party to challenge the arbitration process or the award by seeking judicial review pursuant to the GAC to vacate or modify the award. In Brookfield Country Club, Inc. v. St. James-Brookfield, LLC, 287 Ga. 408, 413, 696 S.E.2d 663 (2010), the Supreme Court considered the validity of contractual language which altered the statutory scheme of the GAC by expanding the scope of judicial review of an arbitration award. The Court
Id. (citation and punctuation omitted). Similarly, we conclude that the GAC does not permit contracting parties who provide for arbitration of disputes to contractually waive or eliminate a party's right to apply to a court to vacate or modify an award on the statutory grounds set forth in OCGA §§ 9-9-13 and 9-9-14.
"Because [the GAC] closely tracks federal arbitration law, we look to federal cases for guidance in construing our own statutes." Brookfield Country Club, 287 Ga. at 412, 696 S.E.2d 663 (citation and punctuation omitted). In In re Wal-Mart Wage & Hour Emp't Practices Litig., 737 F.3d 1262, 1267 (9th Cir.2013), the Court considered whether the statutory grounds for vacating an arbitration award under 9 USC § 10(a) of the Federal Arbitration Act (FAA) (which sets forth grounds similar to those in OCGA § 9-9-13(b) of the GAC) may be waived or eliminated by contract. The Court found that the text of the FAA compels the conclusion that the statutory grounds for vacatur under
Accordingly, we find that the contract provision stating that the parties "expressly agree not to challenge the validity of the arbitration or the award" conflicts with and frustrates Georgia public policy as expressed in the GAC, and is void and unenforceable, to the extent it prevents AFDC from challenging the validity of the arbitration or the award by filing a motion under OCGA § 9-9-13 for the court to vacate the award. See Brookfield Country Club, 287 Ga. at 413, 696 S.E.2d 663; Emory Univ. v. Porubiansky, 248 Ga. 391, 393-394, 282 S.E.2d 903 (1981) (contractual provision eliminating statutory duty of care void as against public policy). The reviewing court erred by dismissing AFDC's motion to vacate.
Judgment reversed.
MILLER, J., concurs.
BRANCH, J., concurs specially and in the judgment.
BRANCH, Judge, concurring specially.
Although I agree with the result reached in this appeal, I write separately to emphasize both the way this court views arbitration agreements generally and the uniqueness of the question presented in this case-that is, whether two commercial parties may agree to waive the right to contest an arbitration award on the limited grounds listed in Section 9-9-13(b) of the Georgia Arbitration Code (GAC).
In this case, claimant Atlanta Flooring and Design Centers, Inc. ("AFDC") filed an arbitration petition against R.G. Williams Construction, Inc. ("Williams"), a general contractor which had refused to pay AFDC the flooring subcontractor on the ground that AFDC had delayed completion of its subcontract. AFDC filed a motion to vacate on the grounds that the arbitrator had overstepped his authority and manifestly disregarded the law when he awarded Williams liquidated damages. Williams moved to dismiss AFDC's motion to vacate on the ground that in their agreement to arbitrate, the parties had "expressly agree[d] not to challenge the validity of the arbitration of [any] award" made. AFDC appeals from the trial court's grant of Williams's motion to dismiss AFDC's motion to vacate the award.
As a preliminary matter, it bears repeating that "[i]n enacting the GAC, the General Assembly established a clear public policy in favor of arbitration." Order Homes, LLC v. Iverson, 300 Ga.App. 332, 334-335, 685 S.E.2d 304 (2009). As a result, "Georgia courts are required to uphold valid arbitration provisions in contracts." Saturna v. Bickley Const. Co., 252 Ga.App. 140, 555 S.E.2d 825 (2001) (affirming arbitration provision in contract between homeowners and contractor). This is especially true of arbitration provisions agreed upon by two commercial parties such as those before us in this case. See Bishop Contracting Co. v. Center Bros. Inc., 213 Ga.App. 804, 805(1), 445 S.E.2d 780 (1994) (upholding arbitration provision in contract between contractor and subcontractor). But this case also presents us with what I, like AFDC, believe to be a question of first impression: that is, whether two contracting parties may agree to waive their respective rights to seek vacatur of an arbitration award on the specific and limited grounds listed in OCGA § 9-9-13(b).
In Brookfield Country Club, Inc. v. St. James-Brookfield, LLC, 287 Ga. 408, 696 S.E.2d 663 (2010), the Supreme Court of Georgia held that the GAC "does not permit contracting parties who provide for arbitration of disputes to contractually expand the scope of judicial review that is authorized by statute." Id. at 413, 696 S.E.2d 663 (emphasis
First, the Second Circuit's decision in Hoeft v. MVL Group, Inc., 343 F.3d 57 (2d Cir.2003), disapproved on other grounds, Hall Street Associates, LLC v. Mattel, Inc., 552 U.S. 576, 585, 128 S.Ct. 1396, 170 L.Ed.2d 254 (2008), provides a convincing rationale for the result reached by us in this case.
Id. at 64-65. Similarly, I believe that the parties to this arbitration agreement, who must turn to a Georgia court in order to confirm an arbitration award, were not empowered to relieve the Georgia courts of their obligation to review the same kind of award for the fundamental flaws identified in OCGA § 9-9-13(b).
Second, I wish to emphasize, as the Georgia Supreme Court has repeatedly done, that the grounds for vacatur set out in OCGA § 9-9-13(b) are strictly limited,
Third, our result merely reverses the trial court's grant of Williams's motion to dismiss AFDC's motion to vacate the arbitration award, such that AFDC's motion to vacate remains pending below. It would be a misreading of our result, moreover, to infer any conclusion from it as to the merits of that pending motion. See, e.g., Berger v. Welsh, 326 Ga.App. 290, 297(3), 756 S.E.2d 545 (2014) (reversing superior court's vacatur of an arbitrator's award when that award had stated no legal or factual rationale for the award such that the party moving to vacate had failed to make the "extremely difficult" showing of manifest disregard of the law).
Because I believe these matters require further explanation and require a slightly different analysis, I concur in the judgment only.