COHEN, J.
Royal Palms Senior Apartments Limited Partnership ("Royal Palms") appeals the nonfinal order entered in favor of Construction Enterprises Inc. of Tennessee d/b/a Construction Enterprises, Inc. ("CEI") staying Royal Palms' lawsuit pending mediation and arbitration. Royal Palms argues that the trial court erred in finding that a valid arbitration agreement existed and that its claim was subject to arbitration.
In December 2006, the parties entered into a contract for CEI to construct the Royal Palms Senior Apartments. The agreement was comprised of the "AIA Document A201-1997 General Conditions of the Contract for Construction" ("General Conditions") and a supplementary document ("Supplementary Conditions"), which modified and deleted portions of the General Conditions and controlled if the two documents conflicted.
In October 2017, Royal Palms filed a complaint against CEI alleging negligence, vicarious liability, breach of contract, and breach of applicable building codes. CEI moved to dismiss or alternatively, to compel mandatory and exclusive dispute resolution procedures, including mediation and arbitration. After a hearing on CEI's motion, the trial court determined that the mediation and arbitration provisions of the General Conditions were binding and enforceable. It stayed the case and ordered mediation followed by arbitration if mediation was unsuccessful. This appeal followed.
"Under both federal statutory provisions and Florida's arbitration code, there are three elements for courts to consider in ruling on a motion to compel arbitration of a given dispute: (1) whether a valid written agreement to arbitrate exists; (2) whether an arbitrable issue exists; and (3) whether the right to arbitration was waived."
Although courts generally favor arbitration, "no party may be forced to submit a dispute to arbitration that the party did not intend and agree to arbitrate."
While the Supplemental Conditions eliminated some of the General Conditions related to arbitration, multiple provisions contemplating arbitration remained. "An interpretation of a contract which gives a reasonable, lawful and effective meaning to all of the terms is preferred to an interpretation which leaves a part unreasonable, unlawful or of no effect."
Pursuant to the General Conditions as modified by the Supplementary Conditions, the "exclusive procedure[]" for resolving claims arising before final payment is due is to submit such claims to the Architect for a final, binding decision. If the parties are not satisfied with the Architect's decision, they may mediate the claim. If mediation is unsuccessful, the only remaining option is to arbitrate the claim. Thus, because the General Conditions as modified by the Supplementary Conditions require arbitration of claims arising before final payment is due if the parties are unsatisfied with the Architect's decision and mediation is unsuccessful, we find that the trial court did not err in determining that the parties had a valid agreement to arbitrate.
However, the contract is silent regarding the procedure for resolving claims that arise after final payment is due. The provisions comprising the "exclusive procedures" for resolving such claims reference litigation, mediation, and arbitration. Because those claims are not required to be submitted to the Architect, they are not subject to arbitration if mediation is unsuccessful. A party cannot be forced to arbitrate a claim it did not agree to arbitrate.
The record is less clear regarding the second prong of the
AFFIRMED, in part, REVERSED, in part; and REMANDED.
BERGER and EDWARDS, JJ., concur.
NOT FINAL UNTIL TIME EXPIRES TO FILE MOTION FOR REHEARING AND DISPOSITION THEREOF IF FILED