JANE TRICHE MILAZZO, District Judge.
Before the Court is Defendants' Motion for Summary Judgment (Doc. 185). For the following reasons, the Motion is GRANTED.
This is a civil action for declaratory and injunctive relief. The plaintiffs are White Oak Realty, LLC and Citrus Realty, LLC. The defendants are the United States Corps of Engineers (the "Corps") and various Corps employees. The dispute involves mitigation requirements imposed by the Corps on a tract of land in Southeast Louisiana ("Idlewood Stage 2"), jointly owned by Plaintiffs.
In response to the devastation caused by Hurricanes Katrina and Rita, Congress authorized the Corps to undertake a series of projects collectively known as the Hurricane and Storm Damage Risk Reduction System ("HSDRRS"). One of these projects involves the use of soil and clay ("borrow material") to reinforce levees and floodwalls in the Gulf South. In order to respond to the unprecedented amount of borrow material needed for this project, the Corps instituted the contractor-furnished borrow program. The contractor-furnished borrow program allows landowners to have their land pre-qualified as a suitable source for borrow material based on certain requirements.
At some point in 2010, Plaintiffs discovered the presence of borrow material on their property. They subsequently filed a "suitability determination" with the Corps to confirm the borrow material could be used in HSDRRS projects. Some of the property (Idlewild Stage 1) was quickly qualified and clay mining began. On other portions (Idlewild Stages 2 and 3), the Corps approved the land's use for borrow material but found that the excavation of borrow material would cause "unavoidable impacts" to the bottomland hardwood ("BLH") forests on the property, and therefore mitigation would be required. In addition, the portions of the land that were wetlands were excluded from excavation. Plaintiffs, therefore, sought to mine clay only from the uplands portions of Idlewild Stage 2 and that area was later cleared of the BLH forest.
In a letter dated November 4, 2010, the Corps notified Plaintiffs that Idlewood Stage 2 "appears to be acceptable for use as a source" of borrow material. The letter confirmed the preliminary report's determination that excavation would harm the environment. The letter required "proof of mitigation to the Corps[] . . . prior to excavation." The Corps issued a similar letter on April 14, 2011, reaffirming the requirement that the impacts to the BLH forests on the land be mitigated. The letter informed Plaintiffs that their "compensatory mitigation requirements may be met" by obtaining credits from select mitigation banks.
Plaintiffs subsequently hired Mitigation Strategies, LLC ("Mitigation Strategies") hoping to convince the Corps of the "legal and factual errors underlying [its] mitigation requirements." Mitigation Strategies argued to the Corps on numerous occasions that mitigation was neither necessary nor appropriate under the law. In the alternative, if mitigation was required, Mitigation Strategies argued the law required in-kind mitigation, rather than the purchase of credits from mitigation banks.
The Corps disagreed. A February 20, 2013 letter from the District Commander reiterated the Corps's position that if borrow material from Idlewood Stage 2 is used in connection with the HSDRRS project, the impacts to the BLH forests on that land must be mitigated (the "Mitigation Requirement"). It further confirmed the Corps's position that such mitigation must occur through the purchase of mitigation bank credits (the "Purchase Requirement").
As a result of the Corps's position, Plaintiffs filed this suit, arguing that the Water Resource Development Act of 2007 ("WRDA"), 33 U.S.C. § 2201 et seq., does not require mitigation for Idlewood Stage 2 or alternatively, that the WRDA does not authorize the Corps to mandate the purchase of mitigation credits as the sole form of compensatory mitigation. This Court has previously dismissed all of Plaintiff's claims on summary judgment, save a regulatory takings claim. Defendant has filed the instant Motion for Summary Judgment seeking dismissal of that remaining claim.
Summary judgment is appropriate "if the pleadings, depositions, answers to interrogatories, and admissions on file, together with affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law."
In determining whether the movant is entitled to summary judgment, the Court views facts in the light most favorable to the non-movant and draws all reasonable inferences in his favor.
As a threshold matter, Plaintiffs dispute the appropriateness of considering Defendants' second motion for summary judgment. They argue that Defendants' motion is improper under the scheduling order and should be considered under the standard of a motion for reconsideration.
This case has followed an unusual procedure. Initially, the Court set a scheduling order establishing a trial date, as well as a deadline for nonevidentiary pre-trial motions. After the parties filed a motion for judgment on the pleadings and cross-motions for summary judgment, however, the Court vacated the scheduling order pending resolution thereof.
"Courts have found that a subsequent summary judgment motion based on an expanded record is permissible."
The Fifth Amendment of the Constitution prohibits the government from taking private property without just compensation. "A `taking"` may occur either by physical invasion or by regulation."
At the outset, Defendants reassert many of the arguments previously made in their Motion for Judgment on the Pleadings alleging that this Court lacks jurisdiction to hear Plaintiffs' takings claim. Defendants argue that Congress has not withdrawn Tucker Act jurisdiction over Plaintiffs' claims, and thus Plaintiffs' claims should be brought in the United States Court of Federal Claims. This Court has already addressed these arguments, and Defendants' renewed objection to jurisdiction does not dissuade this Court from its prior holding. Accordingly, this Court again holds that it has jurisdiction to hear Plaintiffs' takings claims for the reasons stated in Record Document 142.
Next, Defendants argue that Plaintiffs lack a compensable property interest in the property that they allege was taken. At the outset, the parties dispute the nature of Plaintiffs' takings claim. Defendants characterize Plaintiffs' claim as alleging a taking of the clay itself as well as the business opportunity to sell the clay as part of the HSDRRS project. They argue that Plaintiffs' ownership of Idlewild Stage 2 does not give them a right to insist that their clay be purchased by the Corps, to demand they be exempt from the Purchase Requirement, or to dictate the terms of the Corps's contracts.
Plaintiffs, on the other hand, characterize their claim as one for a loss of rights in an existing asset. They argue that their right to mine the borrow material from Idlewild Stage 2 is inherent in their interest in the property and that the Purchase Requirement destroyed the right to realize profits from that material. Plaintiffs argue that ownership "means that a landowner has the right to exercise those property rights that are inherent in ownership, such as mining and realizing the value of sub-surface minerals, and it is that interest that Defendants have destroyed in this case."
"Property interests . . . are not created by the Constitution. Rather, they are created and their dimensions are defined by existing rules or understandings that stem from an independent source such as state law."
Under Louisiana law, the borrow material on Idlewild Stage 2 is a "product." Products are things the production of which result in the diminution of the property.
In Hearts Bluff Game Ranch v. U.S., the plaintiff alleged a taking when the Corps denied it a permit to create a mitigation bank on its property.
In Schooner Harbor Ventures, Inc. v. U.S., the plaintiff alleged a takings claim when it was required to give seventy-seven acres of property to the Fish and Wildlife Service ("FWS") to be used as a wildlife refuge in order to sell another parcel of land to the U.S. Navy.
As in these cases, here, the only limitation on Plaintiffs' right to sell the borrow material on its property is the condition that it is required to purchase mitigation credits if the borrow will be used in the HSDRRS project. The imposition of this condition is in the Corps's sole discretion, and it does not destroy any of the "bundle of rights" that Plaintiffs have in owning the land. Plaintiffs are still entitled to mine and sell the borrow material on their property. Accordingly, Plaintiffs do not have a compensable property interest in selling their borrow material for use in the HSDRRS without satisfying the Purchase Requirement.
For the foregoing reasons, Defendants' Motion for Summary Judgment is GRANTED, and Plaintiffs' claims are DISMISSED WITH PREJUDICE.