Robert J. Faris, United States Bankruptcy Judge.
This adversary proceeding arises out of a construction contract between Plaintiff
Defendant Canaan Construction has filed a counterclaim against Pearson and his wife, Julia Pearson. Counts 2 and 3 of the counterclaim seek recovery under equitable theories (quantum meruit/unjust enrichment and promissory estoppel/detrimental reliance). The Pearsons seeks a partial summary judgment determining that Canaan Construction has no equitable claims arising from work described in Change Order 9.
For the following reasons, I will grant (or recommend that the district court grant) the motion in part. This decision will be somewhat complex because some of my decisions are conditional upon subsequent resolution of factual issues.
Suiter is the president, sole officer, and principal responsible managing employee of Canaan Construction.
Pearson entered into a contract dated September 17, 2012, with Canaan Construction for the remodeling and reconstruction of a home.
I have previously ruled that Canaan Construction failed to give Pearson numerous written disclosures as required by Hawaii law.
Section 1.3 of the contract provides that it could only be modified by a change order or other writing.
The parties signed eight numbered change orders and one document called a proposal which was a change order in substance.
Disputes arose among the parties. Pearson disputed the payment applications presented by Canaan Construction and, around the end of 2013, Canaan Construction stopped work on the project. Later, Canaan Construction presented proposed Change Order 9 to Pearson for execution. Pearson never signed Change Order 9. Canaan Construction claims that Pearson's construction consultant later agreed to it in an email. The Pearsons argue that the consultant's email is an inadmissible settlement communication and deny that the consultant had authority to agree to Change Order 9.
The court has personal jurisdiction over the parties and jurisdiction of the subject
A party may move for summary judgment, identifying each claim or defense, or the part of each claim or defense, on which summary judgment is sought.
Hawaii law requires construction contractors to give specific disclosures in writing to homeowners.
The voidness of the contract does not deprive Canaan Construction of the right to recover from Pearson in quantum meruit.
This formula produces a sensible result: if a construction contract is void because the contractor did not comply with law, the construction contract can never recover more than the contractor could have recovered if the contract were valid. If this were not the rule, a construction contract could be better off if the contract is void than if it were not.
The Hiraga formula requires the court to calculate how much Canaan Construction could have recovered from Pearson if the contract were not valid. The Pearsons argue that Canaan Construction is not entitled to recover the charges set forth in
The Pearsons contend, and Canaan Construction does not deny, that Pearson never signed Change Order 9. Canaan Construction argues, however, that a construction consultant retained by Pearson sent an email to Suiter in which the consultant agreed to Change Order 9,
First, the Pearsons argue that the consultant's email is a settlement communication that is inadmissible under Fed. R. Evid. 408. I disagree. The rule does not preclude a party from attempting to prove that the parties actually agreed to settle some or all of the claims in the case.
Second, the Pearsons point out that, under the contract, Pearson was the "Designated Representative" of the owner, and the consultant never became a "Designated Representative." But the contract does not say that the Designated Representative is the only person with authority to bind the party. The Pearsons claim that the consultant sent the email in an effort to settle the dispute, that his statements about Change Order 9 would have been operative only if the parties reached an overall settlement (which they did not), and that, in any event, the consultant lacked authority to bind Pearson to an agreement.
Third, the Pearsons point out that, under Hawaii law, a construction contract must be in writing and signed by the owner. But the statute does not preclude the normal common law rules that a party may act through an agent.
All that having been said, there are genuine disputes of fact concerning whether the consultant had actual or apparent authority to bind Pearson to Change Order 9 and whether the consultant intended to bind Pearson to Change Order 9.
If the trier of fact finds that Pearson (through his consultant) agreed to Change Order 9, then Pearson's objections to the specific components of Change Order 9 would be irrelevant. Thus, the discussion contained in the following sections is applicable only if the trier of fact decides that Pearson did not agree to Change Order 9.
Because Canaan Construction does not deny that it failed to follow the contractual process for change orders and adjustments, Change Order 9 is not enforceable against Pearson, and the amounts claimed in Change Order 9 may not be added to Canaan Construction's maximum quantum meruit recovery.
Assuming that Canaan Construction is entitled to recover for any of the work covered by Change Order 9 despite its failure to comply with the applicable procedural requirements, there is a genuine dispute of material fact concerning the amount (if any) that Canaan Construction would be entitled to recover under the contract for the work that was incomplete but "in progress" at the date of termination. To the extent Canaan Construction is not entitled to recover for such work under the contract, its maximum quantum meruit recovery must also be reduced.
This statement completely ignores Suiter's repeated statements that Canaan Construction would provide the plumbing package for $25,000 plus the Change Order 1 amount, even though the actual cost was higher. Even if Change Order 9 is enforceable against Pearson, the Pearsons are entitled to summary judgment on this point.
Pursuant to a proposal dated November 18, 2012, and covered by Change Order 1, Canaan Construction installed micropiles to address possible movement of a retaining wall. Canaan Construction provided a "warranty [of] the structural integrity of the CMU repaired wall as long as the Pearsons, Tom, Julia, and Alicia own the home."
During October 2013, water began to leak through the retaining wall. Canaan Construction determined that "some of the waterproof barrier that was applied by Canaan Construction LTD on this Main Retaining Wall last year was delaminating.... [T]he waterproofing on the street side of the Main Retaining wall has failed since it was applied when the wall was built. The Hydrostatic pressure is too much for the inside membrane to hold."
There is a genuine dispute of material fact concerning the meaning of the term "structural integrity" in the warranty. One could read the term narrowly as a promise that the wall would not collapse; the record does not establish that the wall would have fallen down if the additional sealing were not done. One could also read the term more broadly and include watertightness as an aspect of "structural integrity;" this reading would be particularly plausible if it were shown that water leaks could have undermined the foundation of the wall. But I can not exclude either of these interpretations on this record.
If Change Order 9 is binding on Pearson, summary judgment on this point should be denied.
Pearson's motion should be granted to the extent set forth above.
SO ORDERED.