DAVID L. BUNNING, District Judge.
This matter is before the Court on Defendant Volatile Free, Inc.'s Motion for Summary Judgment. (Doc. # 20). Plaintiff Hall Waterproofing Technology having filed its Response (Doc. # 29), and Volatile Free having filed its Reply (Doc. # 30), this matter is ripe for review. Having reviewed the parties' briefing, and the Court being otherwise sufficiently advised, Volatile Free's Motion for Summary Judgment will be
This litigation arises from leaky roofs at the Kentucky Speedway in Sparta, Kentucky. On February 4, 2012, Hall Waterproofing Technology was retained by General Contractor Consulting Services to remove and install new recovery board under some roofs at the Kentucky Speedway. (Doc. # 1-1 at 9). In addition to installing recovery board, Hall was also to reseal the roofs. (Id.). Hall contacted Volatile Free to inquire about using their waterproofing product to reseal the Speedway's roofs. Volatile Free provides, among other things, polyurea roof-coating services. Polyurea roof coating is a type of liquid roofing, whereby a new or existing roof can be repaired at a fraction of the cost of roof replacement. After being sprayed on the roof, Volatile Free's polyurea roof coating dries in seconds and forms a waterproof barrier. Elastomeric roofing systems such as this not only provide waterproofing, but also help reduce heating and cooling costs and protect the underlying structure.
Hall consulted Volatile Free regarding which of their products would be best suited for the Speedway. Hall selected VFI-540R for the job on the advice of Mark Baum, a VFI representative. (Docs. # 29-4 & 29-10). Baum was provided with specifications for the job and ultimately approved both the type and amount of liquid roofing for Hall's project. (Doc. #29-4).
Before beginning work, Hall and VFI entered into a contract known as the "Authorized Roofing Applicator Agreement" ("ARAA"). (Doc. # 29-1). The ARAA governs the rights and obligations of Hall and Volatile to one another, both during and after completion of the project. Importantly, the ARAA requires Hall — the "Applicator" — to permit:
(Doc. # 29-1 at 2).
After substantial completion and approval of the work by Volatile Free, Hall remained liable for leaks at the structure for a two-year period. (Doc. # 29-1 at 2). After two years, however, the ARAA states that Hall:
(Doc. # 29-1 at 2).
Further, the ARAA lays out the contractual indemnity rights of Hall and Volatile Free:
(Doc. # 29-1 at 3).
Work began in March 2012. On the first day of work, Volatile Free representative Thomas Buckely was on the job site to demonstrate proper application of the VFI-540R coating. (Doc. # 29-2 at 1). Buckely sprayed a 4,000-5,000 square foot portion of the southwest corner of the south roof at the Speedway. (Id.). Hall applied the coating to the remaining 38,000 square feet of the roof.
Subsequent to the execution of the ARAA and commencement of work at the structure, Hall requested a fifteen-year "Material and Labor Warranty," but Volatile Free mistakenly sent him a fifteen-year "Material Only Warranty" instead. (Doc. # 29-10). The Material Only Warranty read:
(Doc. # 29-9). Hall noticed that the warranty did not require Volatile Free to cover the labor necessary to reapply the liquid roofing, which allegedly did not comport with the parties' agreement regarding the warranty. Hall requested, and was sent, the Material and Labor Warranty. (Doc. # 29-10).
The Material and Labor Warranty's first two sentences are identical to those in the Material Only Warranty. The latter half of the Labor and Material Warranty, however, purports to differ from the Material Only Warranty and reads:
(Doc. # 29-11). As is evident, the Material and Labor Warranty the parties signed required Hall, rather than Volatile Free, to provide the labor to install any new coating. The Material and Labor Warranty is substantively the same as the Material Only Warranty — Volatile Free provides the material and Hall supplies the labor under either. Despite this, the Material and Labor Warranty was forty-percent more expensive than the Material Only Warranty, and Hall paid for this upgrade. (Docs. # 29-7 & 29-8).
Work was completed in May 2012. Per their agreement, a Volatile Free representative came to the site to ensure that the work was completed to company specifications, and found that it was. (Doc. # 29-10). Certification that the work was properly completed allowed Hall to submit the paperwork indicating the same, and effectuated the fifteen-year Material and Labor Warranty. (Id.).
Based on the record before the Court, the next couple of years were uneventful. Then sometime in 2015, the roofs at the Speedway began to leak. Understandably, the Speedway wanted the leaky roofs repaired. (Doc. # 1-2 at 21). It is not clear from the record whether this has been done. What is known is that both Hall and Volatile Free believes they should not have to pay for the labor to reapply the liquid roofing. Hall filed suit in Gallatin County, Kentucky Circuit Court seeking a declaration of rights between it and Volatile Free. (Doc. # 1-1). Volatile Free removed the action to this Court, and has now filed a Motion for Summary Judgment. (Doc. # 20). Part of that Motion was previously denied as moot when the Court extended the deadline for expert disclosures. (See Doc. # 28). The remaining portions will be addressed, and denied, for the reasons stated below.
First, the Court must clarify the relief sought in this matter. The parties have not pled any contractual claims or alleged that any work has actually been done to correct the leaking roofs at the Speedway. Instead, the parties briefing implies that they are seeking a declaration of rights, and the Court construes this action as one brought pursuant to 28 U.S.C. § 2201. Accordingly, the rights to be determined are narrow — namely, which party is required to pay for the labor to reapply the liquid roofing.
Second, the Court needs to explain the limits of this Memorandum Opinion and Order. The Court acknowledges that the ARAA contains a contractual-indemnity clause. However, the parties do not allege that there has been a settlement or judgment against Hall. Therefore, based on the facts before the Court, that clause has not yet been triggered and indemnity is not an issue at this time. Thus, the Court makes no ruling as to that clause's effect. Instead, the parties' briefing reflects a disagreement regarding the scope of the Material and Labor Warranty. While the ARAA's provisions may ultimately affect the rights of the parties, the facts presented during this initial briefing do not allow the Court to delve deeply into that agreement. However, fact discovery has not yet closed, and should the Court need to make determinations regarding the ARAA, it will do so at that time.
Finally, the Court needs to address a potential choice-of-law issue. Parol evidence is a substantive rule of law, not a procedural one, Childers & Venters, Inc. v. Sowards, 460 S.W.2d 343, 345 (Ky. 1970); Town Bank v. City Real Estate Dev., LLC, 793 N.W.2d 476, 485 (Wis. 2010), so the Court must determine which states' law to apply by engaging in choice-of-law analysis. Kentucky choice-of-law rules apply in this case because a "federal court in a diversity case must apply the conflict of law rules of the state in which it sits." Banek Inc. v. Yogurt Ventures U.S.A., Inc., 6 F.3d 357, 361 (6th Cir. 1993) (citing Klaxon Co. v. Stentor Elec. Mfg. Co., 313 U.S. 487, 490 (1941)). At first blush, it might appear that Wisconsin law should apply because of the choice-of-law provision in the ARAA. (Doc. # 29-1 at 4). However, Kentucky is very egocentric, and despite Erie guesses by federal courts to the contrary, the Commonwealth does not consider a contract's choice-of-law provision determinative; instead, it is but one factor that a court must consider in its choice-of-law analysis.
However, courts "only need[ ] to go through the choice of law analysis when a conflict occurs between two states' laws." Asher v. Unarco Material Handling, Inc., 737 F.Supp.2d 662, 667 (E.D. Ky. 2010). After a review of Kentucky and Wisconsin law, the Court finds no conflict between the two that would necessitate choice-of-law analysis at this juncture. As will be seen below, adjudication of this motion turns on principles of parol evidence and agreement integration, and both Kentucky's and Wisconsin's laws track the Restatement (Second) of Contracts in those areas of contract law.
Summary judgment is appropriate if "the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law." Fed. R. Civ. P. 56(a). In deciding a motion for summary judgment, the Court must view the evidence and draw all reasonable inferences in favor of the non-moving party. Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587 (1986). The "moving party bears the burden of showing the absence of any genuine issues of material fact." Sigler v. Am. Honda Motor Co., 532 F.3d 469, 483 (6th Cir. 2008).
Once the movant has satisfied its burden, the non-moving party must "do more than simply show that there is some metaphysical doubt as to the material facts," Matsushita Elec. Indus. Co., 475 U.S. at 586; rather, it must produce specific facts showing that a genuine issue remains. Plant v. Morton Int'l, Inc., 212 F.3d 929, 934 (6th Cir. 2000). If, after reviewing the record in its entirety, a rational fact finder could not find for the nonmoving party, summary judgment should be granted. Ercegovich v. Goodyear Tire & Rubber Co., 154 F.3d 344, 349 (6th Cir. 1998).
Volatile Free claims that the Material and Labor Warranty is unambiguous and requires it to provide materials, while Hall covers labor and any other expenses incurred in repairing leaks at the Speedway. Hall counters that it was told during prior negotiations that the Material and Labor Warranty required Volatile Free to cover materials and labor. (Doc. # 29-10). Adjudication of this argument requires the Court to determine whether Hall's evidence of prior negotiations is barred by the parol-evidence rule.
The parol-evidence rule is designed to "preserve the integrity and reliability of written contracts, to reduce the opportunity for perjury and to prevent unsophisticated jurors from being misled by false or conflicting testimony." FDIC v. First Mortg. Investors, 250 N.W.2d 362, 365 (Wis. 1977). Thus, where an agreement was been reduced to a writing, it is presumed that the writing supercedes prior negotiations and oral agreements. Id. But the rule is also "a maze of conflicting tests, subrules and exceptions." Id.
The first step in parol-evidence analysis is to determine if the agreement is integrated, and if so, whether it is completely or partially integrated. Id. at 366. When parties reduce their agreement to a writing, there is a presumption that the writing represents the entire, final agreement, into which all prior negotiations and preliminary agreements are merged. Russell v. Halteman's Adm'x, 153 S.W.2d 899, 904 (Ky. 1941). This presumption is rebuttable, Restatement (Second) of Contracts §§ 209-210 & 214, but if the Court finds that the document is integrated, parol evidence of prior and contemporaneous oral agreements is not admissible to vary the terms of the writing. Sowards, 460 S.W.2d at 345; Town Bank, 793 N.W.2d at 485; Restatement (Second) of Contracts §§ 213 & 216. If a writing is completely integrated, even consistent additional terms are barred by the parol evidence rule. Town Bank, 793 N.W.2d at 484-86, In contrast, where the agreement is only partially integrated, parol evidence of consistent terms may be presented. Id. at n. 3; Restatement (Second) of Contracts § 213. However, both completely and partially integrated agreements forbid the introduction of inconsistent terms. Bullock v. Young, 67 S.W.2d 941, 946 (Ky. 1933); Town Bank, 793 N.W.2d at 485; Restatement (Second) of Contracts § 215. Thus, Hall's parol evidence of prior negotiations should be barred, regardless of the Material and Labor Warranty's level of integration, because his assertion that Volatile Free agreed to cover materials and labor is in direct conflict with that agreement's plain language.
Yet, there are exceptions to the seemingly ironclad parol-evidence rule. Restatement (Second) of Contracts § 214 provides:
In this case, the Court finds that Hall's evidence of prior negotiations, during which it claims Volatile Free promised that the Material and Labor Warranty required Volatile Free's cover materials and labor, is not barred by the parol-evidence rule because it is evidence of a potential fraud or mutual mistake of fact. The affidavit of Richard Hall claims that he was initially sent a Material Only Warranty. He contacted Volatile Free because he claims this was not the warranty the parties had negotiated. Instead, he says that they had agreed to the Material and Labor Warranty that put the cost of both on Volatile Free. Hall claims that Volatile Free acknowledged the error and promptly sent him a new Material and Labor Warranty. Additionally, Hall paid a premium for this "upgraded" warranty; the Material and Labor Warranty cost forty-percent more than the Material Only Warranty. Since the plain language of both Warranties indicates that Volatile Free will pay for only materials and that Hall will be responsible for labor, it is hard to figure why Hall would pay a premium to Volatile Free for a promise that it could have made for free to the Speedway. Furthermore, Hall claims that warranties in which the manufacturer pays for both materials and labor are common in the industry. Accordingly, Hall's evidence is not barred by the parol-evidence rule because it relates to a possible fraud or mutual mistake of fact.
These facts — Hall's affidavit regarding the warranty negotiations, the premium paid for the warranty upgrade, and the evidence of practice in the trade, working in unison and construed in favor of the non-movant — suggest that Volatile Free could have misled Hall or that the parties may made a mistake when they signed the Material and Labor Warranty. This genuine dispute of material fact requires that the Court deny Volatile Free's Motion for Summary Judgment.