JAMES F. HOLDERMAN, Chief Judge:
Plaintiff JPMorgan Chase Bank, N.A., successor in interest to the First National Bank of Chicago (collectively "JPMorgan"),
On October 14, 2009, 2009 WL 3367388, this court issued an order granting JPMorgan's Motion for Summary Judgment Against IK and TK in part, finding them liable for breach of contract. (Dkt. No. 258.) The court reserved the issue of damages. Now pending before the court is JPMorgan's "Motion and Memorandum of Law in Support of Summary Judgment Against Asia Pulp and Paper," (Dkt. No. 218 ("JPMorgan's Summary Judgment Motion")) as well as the issue of damages as to all three defendants: APP, IK, and TK. For the reasons set forth below, this court grants summary judgment in favor of JPMorgan.
When ruling on a motion for summary judgment, the court views the evidence in the light most favorable to the nonmoving party and draws all reasonable inferences in the nonmovant's favor. Omega Healthcare Investors, Inc. v. Res-Care, Inc., 475 F.3d 853, 857 (7th Cir.2007). In light of this principle, the following are the facts of this case, construed in the light most favorable to APP.
In 1996, APP and Beloit Corporation ("Beloit") entered into two contracts for
On September 24, 1998, IK and TK executed and delivered to Beloit new promissory notes which replaced and superseded the original notes in the principal amount of $26,701,678.00 ("IK Note") and $17,123,488.95 ("TK Note"). (JPMorgan's Summ. J. Mot., Exs. 12, 20.)
Also on September 24, 1998, APP executed guarantees on both the IK Note and the TK Note (respectively "IK Guarantee" and "TK Guarantee") and delivered them to Beloit, unconditionally guaranteeing payment of all obligations of IK and TK arising under either note.
On September 30, 1998, Beloit and JPMorgan amended the Note Purchase Agreement to reflect the increased balance of both the IK and TK promissory notes. That same day, September 30, 1998, Beloit executed and delivered to JPMorgan a new Form of Notice and Endorsement which assigned and transferred all of Beloit's rights, title and interest in the IK and TK Notes to JPMorgan.
On October 3, 2000, IK, TK, APP, Beloit, Beloit Asia Pacific (L), Inc. ("BAPL"), Beloit Asia Pacific PTE, Ltd. ("BAP"), and Harnischfeger Industries, Inc. ("Harnischfeger"), entered into a Deed of Settlement ("Settlement") in order to settle disputes, claims, controversies, and other matters in conflict involving certain "Disputed Contracts," including the PPM3 and MPM11 contracts. (JPMorgan's Summ. J. Mot. 8.) The Settlement specifically released Beloit, BAP, BAPL, and Harnischfeger and its successors from all claims relating to the sale, installation, or operation of the PPM3 and MPM11 machines. The Settlement also recognized that IK, TK, and APP were not released from their obligations to repay the IK and TK Notes.
IK and TK made or caused to be made payments of interest and principal to JPMorgan on their respective Notes in 1998, 1999, 2000. IK and TK have not made any further payments since October of 2000. APP has also failed to make payments on the IK and TK Notes.
On September 14, 2001, JPMorgan sent notice to APP informing it that, based on its failure to make a payment on the Notes, it was in default under the terms of the IK and TK Guarantees as of April 2, 2001. Pursuant to an acceleration clause in the IK and TK Notes, JPMorgan declared all unpaid principal and accrued
This court previously found IK and TK liable to JPMorgan for breach of contract in an order dated October 14, 2009. (Dkt. No. 258 at 23.) At that time, the court encouraged the parties to discuss settlement and reserved its ruling on JPMorgan's Motion for Summary Judgment Against APP and JPMorgan's damages. Defendants requested further briefing on the issue of damages, which the court allowed. Subsequently, Defendants filed their "Memorandum of Law in Response to Plaintiff's Motion for Summary Judgment on Damages" (Dkt. No. 261 ("Defendants' Damages Memorandum")),
Pursuant to Rule 56(c) of the Federal Rules of Civil Procedure, summary judgment is proper "if the pleadings, the discovery and disclosure materials on file, and any affidavits show that there is no genuine issue as to any material fact and that the movant is entitled to judgment as a matter of law." Fed.R.Civ.P. 56(c). When ruling on a motion for summary judgment, the court views the evidence in the light most favorable to the nonmoving party and draws all reasonable inferences in the nonmovants's favor. Omega Healthcare, 475 F.3d at 857. However, "[o]nce a party has made a properly-supported motion for summary judgment, the opposing party may not simply rest upon the pleadings but must instead submit evidentiary materials that `set forth specific facts showing that there is a genuine issue for trial.'" Harney v. Speedway SuperAmerica, L.L.C., 526 F.3d 1099, 1104 (7th Cir.2008) (quoting Fed.R.Civ.P. 56(e)).
In ruling on a motion for summary judgment, the court does not make credibility determinations or weigh conflicting evidence. Abdullahi v. City of Madison, 423 F.3d 763, 773 (7th Cir.2005). Instead, it only determines whether a genuine issue of material fact exists for trial, or in other words, whether "there is sufficient evidence favoring the nonmoving party for a jury to return a verdict for that party." Bombard v. Fort Wayne Newspapers, 92 F.3d 560, 562 (7th Cir.1996) (quoting Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986)). The evidence relied upon must be competent evidence of a type that is admissible at trial. Id.
APP, the guarantor of the IK and TK Notes, raised the same affirmative defenses to liability for breach of contract that were raised by IK and TK and rejected by this court in its previous order including breach of implied warranty of merchantability, breach of implied warranty of
In that order, this court also addressed an additional affirmative defense based on an alleged lack of consideration for the IK and TK Notes as that defense related to IK and TK. APP has raised the same lack of consideration affirmative defense, repeating verbatim the arguments made by IK and TK, which this court previously rejected. By merely reasserting IK and TK's arguments, APP has not distinguished its interests in the underlying transaction from those of IK and TK and, consequently, has failed to explain why the court's reasoning in its prior order does not apply to APP as well. Accordingly, APP's lack of consideration affirmative defense is also rejected for the same reasons explained in the court's October 14, 2009 order. (Dkt. No. 258.)
APP, therefore, has no viable affirmative defenses and is liable to JPMorgan for its breach of contract.
APP additionally has raised a counterclaim against JPMorgan, alleging that Beloit breached an implied warranty which entitles IK and TK to consequential damages pursuant to § 2-715 of the U.C.C. JPMorgan argues that this counterclaim is barred by the Settlement and that APP does not have standing to assert the claim.
APP, on the other hand, contends that the Settlement cannot bar its counterclaim because at the time the parties executed the settlement "none of the defendants were aware of Beloit's misrepresentations, thus, defendants could not have been aware of Beloit's breach of implied warranty, the subject of APP's counterclaim." (APP's Resp. Summ. J. 23.) APP goes on to state that Defendants were "unaware of Beloit's material misrepresentations regarding its skills and regarding the PPM3 and MPM11 negotiations and resulting contracts." (Id. at 24.) APP, however, does not identify any additional misrepresentations not previously identified in connection with APP's (and IK and TK's) affirmative defense for breach of implied warranty, which this court addressed above and discussed more thoroughly in its October 14, 2009 order and found insufficient to survive JPMorgan's motion for summary judgment for breach of contract. Merely recharacterizing an affirmative defense for breach of implied warranty as a counterclaim does not alter the court's analysis with respect to this evidence. Again, the court finds that APP's proffered evidence of Beloit's alleged misrepresentations does not create a genuine issue of material fact to defeat summary judgment.
Moreover, even assuming Beloit did make false representations to Defendants at the time of the negotiations for the purchase of the PPM3 and MPM11, APP has not demonstrated how these alleged misrepresentations prevented APP from discovering the breach of implied warranty before signing the Settlement. IK and TK received the machines and constructed them approximately three years after the alleged misrepresentations were made by Beloit (APP's Resp. Summ. J. 23, Ex. B ¶¶ 2-5) and approximately two years before the Settlement was signed on October 3, 2000 (APP's Resp. Summ. J., Ex. L at 5, Ex. M at 21). APP's own Statement of
Based on the court's determination that the Settlement bars APP's counterclaim, the court need not address JPMorgan's additional argument that APP lacks standing to assert this counterclaim. As a result, for the reasons set forth above and discussed more thoroughly in this court's previous October 14, 2009 order, APP's counterclaim is deficient as a matter of law.
This court will now consider the issue of damages with respect to all three defendants: APP, IK, and TK. JPMorgan contends that it is entitled to $30,552,692.49 in principal and interest due on the IK Note and Guarantee and $20,194,019.54 in principal and interest due on the TK Note and Guarantee (JPMorgan's Summ. J. Mot. 24), and further seeks $461,851.17 in attorneys' fees and collection costs, bringing JPMorgan's total damages request to $51,208,563.20 (id. at 25).
Defendants jointly raise three arguments against a judgment of $51,208,563.20 in favor of JPMorgan: (1) the increased interest rate applied after Defendants defaulted constitutes an unenforceable penalty clause, (2) the amount of damages should be mitigated by Beloit's alleged fraud, and (3) the request for attorneys' fees and collection costs should be denied because the contract between the parties did not expressly provide for such damages. (Defs.' Damages Mem. 2.) The court finds Defendants' arguments lack merit for the reasons expressed below.
Defendants' first argument relates to the increased interest rate that went into effect upon default of payment. The Credit Agreements for the IK and TK Notes each contain a provision indicating that the interest rate on the notes would increase by slightly less than one percent in the event of default. (Dkt. No. 220 ("JPMorgan's Summ. J. Mot. Against IK/ TK") at Exs. 13, 23.) Defendants contend that this provision constitutes an unenforceable penalty clause because its purpose is to secure performance of the contract. (Defs.' Damages Mem. 5.) To the contrary, in Illinois, contractual provisions mandating an increased interest rate upon default are considered enforceable liquidated damages provisions, not unenforceable penalties. Baker v. Loves Park Savings & Loan Assoc., 61 Ill.2d 119, 333 N.E.2d 1, 5-6 (1975). The court, therefore,
Defendants also argue that damages must be mitigated due to Beloit's alleged misrepresentations and fraud. Notably, Defendants have not cited any authority supporting the proposition that evidence of fraud may mitigate damages after a finding of liability, and this court is aware of none. Having previously considered and rejected Defendants' evidence of Beloit's purported fraud in determining that Defendants are liable for breach of contract, the court declines to revisit the issue.
Consequently, the court finds that APP is liable to JPMorgan for the $30,522,692.49 in principal and interest due on the IK Note and Guarantee and $20,194,019.54 in principal and interest due on the TK Note and Guarantee.
Defendants further argue that under Illinois common law, attorneys' fees are not a recoverable element of damages for breach of contract in the absence of an express contractual provision to the contrary. They point to an Illinois appellate court case, Qazi v. Ismail, 50 Ill.App.3d 271, 7 Ill.Dec. 434, 364 N.E.2d 595 (Ill.App. Ct.1977), which held that damages for attorneys' fees are not recoverable without a statutory or contractual provision using "specific language such as listing `attorney's fees.'" Id. at 597, 364 N.E.2d 595. According to Defendants, the contracts at issue do not expressly provide for recovery of attorneys' fees. The court disagrees. Section 8.1 of the Credit Agreements unambiguously states:
(JPMorgan's Damages Mem. 3-4; Defs.' Damages Mem. 4 (emphasis added).) While Defendants quote this provision in their brief, they fail to explain how the phrase "fees and disbursements of counsel to the Lender" does not equate to an authorization of damages for attorneys' fees. The agreement may not use the exact words "attorneys' fees," but section 8.1 does provide specific language indicating that attorneys' fees are recoverable, which is all that Qazi requires. Therefore, based on the express terms of the Credit Agreements, JPMorgan is entitled to recover its attorneys' fees from Defendants.
Pursuant to section 8.1 of the Credit Agreements, attorneys' fees and costs are recoverable as long as (1) they "aris[e] in connection with the . . . enforcement of this Agreement, the Note(s) and any documents or transactions contemplated hereby;" and (2) they are "reasonable." Although Defendants have not disputed that JPMorgan's claimed attorneys' fees arose in connection with the enforcement of the Agreement or Notes, they have requested that this court reopen discovery to determine the reasonableness of JPMorgan's attorneys' fees and costs. As discussed below, the court finds that additional discovery is not necessary.
The requirements of proof of reasonableness of attorneys' fees are procedural matters governed by federal law. Taco Bell Corp. v. Cont'l Casualty Co., 388 F.3d 1069, 1076 (7th Cir.2004). The Seventh Circuit has held that attorneys' fees awarded pursuant to a contract are reasonable
Specifically, the court needs documentation regarding the amount actually paid by JPMorgan, in U.S. Dollars, to the law firm Chadbourne & Parke. The majority of bills JPMorgan has provided from this law firm are in Pounds Sterling. (See JPMorgan's Summ. J. Mot., Ex. 28). Based on the Affidavit of John H.P. Barlow, an attorney from Chadbourne & Parke, JPMorgan appears to have calculated its requested attorneys' fees using the U.S. Dollar to Pounds Silver conversion rate effective on the date the Affidavit was written. (See id. at 3). However, the relevant conversion rate(s) would be the rate on the date(s) JPMorgan paid Chadbourne & Parke's bills. This court, therefore, requests documentation of the U.S. Dollar amount JPMorgan actually paid on each bill provided in JPMorgan's Summary Judgment Motion Exhibit 28.
Additionally, the court's calculations of the total sum paid to the Rock Fusco and Crowley & Lamb law firms, based on the amounts listed in the Affidavit of James M. Crowley, are $3,000 less than the total sum provided in the Affidavit. The court requests further clarification from JPMorgan on how the sum of $385,606.02, identified in the Affidavit of James M. Crowley, was reached. (See JPMorgan's Summ. J. Mot., Ex. 27 at 5.)
The court finds that the further documentation requested above will aid the court in determining the reasonableness of JPMorgan's claimed attorneys' fees, but the court does not believe that additional discovery is necessary on this matter. Although the Defendants have had access to the affidavits and invoices of JPMorgan's attorneys for over one year, they have not explained why JPMorgan's claimed fees are potentially unreasonable. Furthermore, Defendants have not identified what additional discovery they would seek. Defendants' request that discovery be reopened to determine the reasonableness of JPMorgan's requested attorneys' fees is therefore denied.
For the reasons set forth above, this court grants summary judgment in favor of the plaintiff, JPMorgan, and awards damages in the amount of $50,746,712.03. The court reserves judgment on the remaining requested $461,851.17 for attorneys' fees and collection costs pending the submission of the further documentation requested in this opinion by May 5, 2010.
Plaintiff JPMorgan Chase Bank, N.A.'s ("JPMorgan") First Amended Complaint alleges that defendants Asia Pulp and Paper Company, Ltd. ("APP"), PT Indah Kiat Pulp and Paper Corporation, Tbk ("IK") and PT Pabrick Kertas Tjiwi Kimia, Tbk ("TK") (collectively "Defendants") are liable to JPMorgan for breaching the terms and conditions of certain promissory notes and guarantees. On December 12, 2008, JPMorgan filed motions for summary
Now before the court is JPMorgan's "Motion Pursuant to Rule 60(b) to Modify the Judgment Entered April 21, 2010 and Supplemental Motion for Attorney's Fees and Costs" (Dkt. No. 293) ("Motion"), through which JPMorgan has supplied the additional documentation necessary to support JPMorgan's requested attorneys' fees. Defendants have not responded to JPMorgan's Motion or otherwise disputed the accuracy of JPMorgan's documentation or calculations. The court finds that the numerous invoices and billing summaries submitted by JPMorgan reflect the amount of attorneys' fees actually paid by JPMorgan in litigating this matter and substantially support its request for attorneys' fees and costs in the amount of $503,641.26. As previously noted by this curt in its April 21, 2010 Memorandum Opinion and Order, the best evidence that legal fees and costs are reasonable is the value placed on these legal services by actual paying clients. (Dkt. No. 266 at 12.) Moreover, although an outstanding balance of $16,117.60 remains unpaid by JPMorgan to the law firm of Crowley & Lamb, P.C., the court finds that the rates and hours charged in connection with these fees, as set forth in the Second Supplemental Affidavit of Attorney James M. Crowley (Dkt. No. 293, Ex. F (attachments)), are reasonable. Accordingly, the court awards JPMorgan attorneys' fees and costs in the requested amount of $503,641.26, covering "all attorney's fees and costs incurred in connection with this litigation . . . as of July 31, 2010." (Mot. ¶ 22.)
JPMorgan also seeks modification of this court's April 21, 2010 order awarding JPMorgan damages, because that damages award was based on out affidavits. JPMorgan is correct that the court erroneously based its damages calculations in the order on outdated affidavits. Relying on the most current affidavits, that damages award is hereby amended to award JPMorgan $52,992,696.51 for the amounts due on the IK and TK Notes, including prejudgment interest through April 21, 2010, as requested by JPMorgan. (Mot. ¶ 17.)
The total amount awarded to JPMorgan is thus $53,496,337.77. The specific amount for which each of the defendants is liable is explained below.
Defendant IK is liable to JPMorgan for $31,904,510.92, for the principal and prejudgment interest due on the IK Note, plus $251,820.63 in attorneys' fees and costs, for a total amount of $32,156,331.55. (See Mot. 8.)
Defendant TK is liable to JPMorgan for $21,088,185.59, for the principal and prejudgment interest due on the TK Note, plus $251,820.63 in attorneys' fees and costs, for a total amount of $21,340,006.22. (Id.)
Defendant APP, as the guarantor, is liable to JPMorgan for $52,992,696.51, for the principal and prejudgment interest due on both the IK and TK Notes, plus the full amount of JPMorgan's attorneys' fees and