CHARLES A. SHAW, District Judge.
This matter is before the Court on third-party defendant McAninch Corporation's ("McAninch") motion for summary judgment against defendants/third-party plaintiffs Lake Asphalt Paving & Construction, LLC; Gaines Construction, Inc.; Gaines Leasing & Investment, LLC; DGN, Inc.; William and Patricia Gaines; Keith and Jeannie Denney; Michaeland Sandra Rogers; and Harold E. Neumann ("defendants"). Defendants oppose the motion, and it is fully briefed. For the following reasons, the Court will grant McAninch's motion for summary judgment.
This action arises out of a highway construction project initiated by the Missouri Department of Transportation, known as the Route 54 project in Camden County, Missouri. Plaintiff Safeco Insurance Company of America ("Safeco") issued payment and performance bonds, as surety, to defendant Lake Asphalt Paving & Construction, LLC ("Lake Asphalt"), as principal, with respect to the construction project. In connection with the project, defendants entered into a General Agreement of Indemnity for Contractors ("Indemnity Agreement") with Safeco, under which defendants pledged to hold Safeco harmless from claims and other expenses incurred by Safeco in connection with the bonds.
In a letter dated March 4, 2010, the general contractor on the Route 54 project, McAninch, declared Lake Asphalt to be in default and called upon Safeco to honor the obligations of its performance bond. Lake Asphalt acknowledged to Safeco that it was unable to complete the performance of the work or comply with its contractual obligations to McAninch on the project and voluntarily abandoned that project. Pursuant to its performance bond obligations, Safeco contracted with other companies to complete the project.
Safeco sued defendants for indemnity, exoneration, quia timet, and specific performance. In response to this suit, defendants filed a third-party claim against the general contractor, McAninch, alleging breach of contract (Count I) and indemnification and contribution (Count III).
The standards applicable to summary judgment motions are well settled. Pursuant to Federal Rule of Civil Procedure 56(c), a court may grant a motion for summary judgment if all the information before the court shows "there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law."
The initial burden is placed on the moving party.
Once the burden shifts, the non-moving party may not rest on the allegations in its pleadings, but by affidavit and other evidence must set forth specific facts showing that a genuine issue of material fact exists. Fed. R. Civ. P. 56(e);
On March 6, 2006, plaintiff Safeco and defendants entered into the Indemnity Agreement. The Indemnity Agreement's purpose was to indemnify Safeco "from all loss and expense in connection with any Bonds" issued on behalf of Lake Asphalt.
The Indemnity Agreement provides Safeco with certain remedies in the event of a "default" by Lake Asphalt. It defines "default" to include any actual breach or abandonment of any contract guaranteed by a Safeco bond. The Indemnity Agreement also grants Safeco "the exclusive right" to determine whether any claims upon any of its bonds shall be "paid, compromised, defended or appealed."
Under the Indemnity Agreement, Lake Asphalt agreed to assign to Safeco "as of the date of execution of any Bond" all rights belonging to Lake Asphalt "in, or in any manner growing out of" any contract for which Safeco issued a bond. The Indemnity Agreement also provides for the concurrent assignment of "[a]ny actions, causes of action, claims or demands whatsoever which Contractor may have or acquire against any party to the Contract, or arising out of or in connection with any Contract."
Lake Asphalt and McAninch entered into a subcontract on March 25, 2008. Safeco issued a payment and performance bond in connection with Lake Asphalt's work for McAninch on the Route 54 project on June 30, 2008. Defendants have admitted that they executed the Indemnity Agreement and that Safeco issued a bond inconnectionwith Lake Asphalt's contract with McAninch.
On March 8, 2010, Lake Asphalt wrote to McAninch, admitting that it was in "default" of their subcontract for the Route 54 project and notifying McAninch of its intention to abandon the subcontract:
On April 19, 2010, Safeco and McAninch entered into a Takeover Agreement, wherein Safeco would "undertake to cause the performance of the Lake Asphalt Subcontract in accordance with the terms, covenants and conditions of the Lake Asphalt Subcontract." The Takeover Agreement acknowledged that Safeco, in executing this agreement, was "acting in its capacity as the surety for Lake Asphalt."
In Count I of their third-party complaint, Lake Asphalt sues general contractor McAninch for breach of Lake Asphalt's subcontract to install asphalt on the Route 54 project.
McAninch seeks summary judgment on this count, stating defendant Lake Asphalt is not the "real party in interest" under the subcontract and has no rights to assert breach of the subcontract against McAninch.
Here, under the unambiguous terms of the Indemnity Agreement, Lake Asphalt assigned any breach of contract claim against McAninch to Safeco at the time Safeco issued the bond.
In Count III, defendants assert a claim for "indemnification and contribution" against McAninch. Defendants state that because of McAninch's alleged delays in prep work, engineering, material handling, and design on the Route 54 project, Lake Asphalt was prohibited from performing under its subcontract with McAninch. Safeco made a claim against defendants in excess of $2,800,000 on the performance bond. Defendants claim they are entitled to recover this money from McAninch.
In its motion for summary judgment on Count III, McAninch argues defendants cannot use principles of tort law—contribution and indemnity—to hold McAninch liable under defendants' indemnity contract with Safeco. To state a claim for contribution, McAninch states defendants would have to allege a "common liability" to Safeco that exists among defendants and McAninch. Also, to state a claim for indemnity, defendants would have to show that they and McAninch shared an "identical duty" to Safeco.
Defendants do not dispute either legal argument asserted by McAninch. Instead, they state that "[w]hen right and justice demand it, the doctrine of unclean hands should be applied." (Defs. Resp. at 5). Because McAninch caused the delays that forced defendant Lake Asphalt to breach the subcontract, defendants want McAninch held liable for Safeco's indemnity claims against defendants. Defendants do not cite any case that would allow the Court to find the McAninch liable under the asserted theories of contribution or indemnity.
To the contrary, the Court finds that defendants cannot maintain their claim for contribution because they fail to allege any "common liability" to Safeco that defendants share with McAninch. Contribution seeks to distribute loss among joint tortfeasers by requiring each to pay its proportionate share.
Nor do defendants allege any "shared obligation" to Safeco between themselves and McAninch which would allow them to state a claim for indemnity.
The Court determines, based on uncontroverted facts, that third-party defendant McAninch Corporation is entitled to summary judgment on Counts I and III of defendants' third-party complaint. The Court will enter summary judgment in favor of McAninch Corporation on Counts I and III.
Accordingly,
An appropriate partial judgment will accompany this memorandum and order.