MARC E. JOHNSON, Judge.
Defendants/Appellants, Entergy Louisiana, LLC, Stewart Interior Contractors, LLC, and Carl E. Woodward, LLC all appeal dismissals of cross-claims resulting from the granting of motions for summary judgments from the 24th Judicial District Court, Parish of Jefferson. For the following reasons, we affirm the trial court's dismissals of the cross-claims filed by Entergy Louisiana, Inc., Carl E. Woodward and Stewart Interior Contractors, LLC, vacate the portion of the judgments dismissing the cross-claims with prejudice, and amend the judgments to dismiss the cross-claims without prejudice.
In the aftermath of Hurricane Katrina, Carl E. Woodward, LLC (hereinafter "Woodward"), general contractor, entered into a construction contract with Eagle
On January 5, 2006, while working at the Walgreens job site, Plaintiff, Daniel Moreno (hereinafter "Moreno"), was injured while atop a scaffolding that was too close to the power lines, which was located next to the facade of the Walgreens store. As Moreno was climbing the scaffolding to warn his co-workers that they were too close to the overhead power lines, one of his co-workers contacted the adjacent overhead power lines with a piece of metal that Moreno was removing from the scaffolding. That contact ultimately resulted in severe injuries to Moreno.
On January 4, 2007, Moreno filed suit on against Entergy Louisiana, LLC (hereinafter "Entergy"), Eagle Enterprises of Jefferson, Inc., Lafayette Insurance Company, Walgreens Louisiana Company, Inc., the Parish of Jefferson, Woodward, and Stewart.
Stewart filed an answer to Moreno's petition, a cross-claim against Landaverde, and a third-party demand against Landaverde's commercial liability insurer, Western World Insurance Company (hereinafter "Western World"). The third-party demand and cross-claim arouse out of a contractual indemnity clause found in the "Temporary Labor Contract" between Stewart and Landaverde.
Landaverde filed a motion for summary judgment seeking to dismiss Stewart's cross-claim. The trial court granted Landaverde's motion. Stewart filed a motion for new trial, and it too was denied by the trial court. Stewart is appealing the trial court's final judgment dismissing its cross-claim demand against Landaverde.
Western World filed a motion for summary judgment seeking to dismiss Stewart's third-party demand filed against it. The trial court granted the motion. Stewart is also appealing the trial court's final judgment dismissing its third-party demand against Western World.
Entergy answered Moreno's petitions and filed third-party demands against Stewart, Landaverde and Woodward. Entergy's third-party demand alleged that the third-party defendants were liable to Entergy for indemnity, pursuant to the Louisiana Overhead Power Line Safety Act ("OPLSA"). Entergy also filed a motion for summary judgment alleging that Stewart violated the OPLSA. The trial court denied Entergy's motion.
Landaverde filed separate a motion for summary judgment seeking to dismiss Entergy's cross-claim. At the July 8, 2009 hearing, the trial court granted Landaverde's motion for summary judgment and dismissed Entergy's cross-claim against Landaverde with prejudice. At the same hearing, Stewart and Woodward orally
At the July 8, 2009 hearing, the trial court continued Stewart's motion for summary judgment, alleging it was Moreno's statutory employer, against Moreno without date. Subsequently, Stewart re-filed its motion. The trial court granted Stewart's motion for summary judgment finding that Moreno was a statutory employee of Stewart.
We will now address each appeal separately.
On appeal, Entergy alleges that the trial court erred by granting the motions for summary judgment by disregarding the language of LSA-R.S. 45:144 of the OPLSA, which provides that the owner of a high voltage overhead power line is entitled to recover all damages from "persons responsible" who violate the Act, and holding that Entergy was precluded, as a matter of law, from being fully indemnified by the "persons responsible" for violating the Act.
Entergy avers that the purpose of the OPLSA is to make the persons responsible for the violation economically responsible if they fail to provide the required advance notification, thereby depriving Entergy of the opportunity to inspect the proposed work site and institute appropriate safety measures. Entergy further avers that, pursuant LSA-R.S. 45:144 of the OPLSA, it is entitled to indemnity from the persons responsible of violating the Act of all damages incurred from the violation. Entergy contends that the only way to force a company to comply with the Act is to ensure that it is responsible for "all damages," including the damages owed by the utility company, if the company fails to comply with the Act. As a result, Entergy alleges that the trial court erred in granting the motions for summary judgment and finding that Entergy was barred as a matter of law from seeking indemnity from Landaverde, Stewart and Woodward.
LSA-R.S. 45:144(A) of the OPLSA provides,
Entergy's cross-claims against Landaverde, Stewart and Woodward are based upon the indemnity provision of LSA-R.S. 45:144(A). The trial court granted the motions for summary judgment by Landaverde, Stewart and Woodward. The summary judgments dismissed Entergy's cross-claims against Landaverde, Stewart and Woodward with prejudice on the basis that Entergy did not have indemnity rights pursuant to the OPLSA.
We agree with the dismissal of Entergy's cross-claims against Landaverde, Stewart and Woodward; however, we agree for a reason other than the one provided by the trial court. We conclude that the cross-claims of Entergy and the motions for summary judgment by Landaverde,
In the interest of justice and judicial efficiency, we are upholding the dismissal of Entergy's cross-claims on account of our own motion of no cause of action on the basis of prematurity.
On appeal, Stewart alleges that the trial court erroneously granted the motion for summary judgment by Landaverde, which dismissed its cross-claim, because Stewart is entitled to seek indemnity from Landaverde pursuant to the "contract indemnity clause" in the Temporary Labor Contract because Landaverde's employees were negligent in causing the accident. Additionally, Stewart alleges that the trial court erroneously granted Western World's motion for summary judgment, which dismissed its third-party demand, because the Temporary Labor Contract between its insured, Landaverde, and Stewart is an "insured contract" under the terms of Western World's insurance policy.
As with Entergy's cross-claims, we also find that Stewart's cross-claims against Landaverde and Western World were properly dismissed because they were premature. Additionally, we find that the granting of the motions for summary judgment filed by Landaverde and Western World were also premature. No fault has been allocated to any party in the case, and no damages from Moreno's action have been assessed against Stewart. No cause of action for indemnity has been incurred by Stewart at this phase in the matter. See Toups v. Koch Gateway Pipeline, Inc. and Meloy v. Conoco, Inc., supra.
In the interest of justice and judicial efficiency, we are upholding the dismissal of Stewart's cross-claim against Landaverde and Western World on account of our own motion of no cause of action on the basis of prematurity.
Woodward argues that the trial court erroneously granted Landaverde's motion for summary judgment, which dismissed Woodward's cross-claim against Landaverde, because there are genuine issues of material fact remaining with respect to the question(s) pertaining to Landaverde's obligation to indemnify Woodward. In its cross-claim against Landaverde, Woodward is seeking indemnification from Landaverde, pursuant to the Temporary Labor Contract executed between Stewart and Landaverde. As a result of the contractual provision in the Temporary Labor Contract, Woodward maintains that Landaverde owes it indemnification for those damages "arising or out of act(s), action(s), behavior and/or negligence, either solely, in concert or in part of LCI
As with Entergy's cross-claims, we also find that Woodward's cross-claims against Landaverde and Western World were properly dismissed because they were premature. Additionally, we find that the granting of the motions for summary judgment filed by Landaverde and Western World were also premature. No fault has been allocated to any party in the case, and no damages from Moreno's action have been assessed against Woodward. No cause of action for indemnity has been incurred by Woodward at this phase in the matter. See Toups v. Koch Gateway Pipeline, Inc. and Meloy v. Conoco, Inc., supra.
In the interest of justice and judicial efficiency, we are upholding the dismissal of Woodward's cross-claim against Landaverde and Western World on account of our own motion of no cause of action on the basis of prematurity.
For the foregoing reasons, the trial court's dismissals of the cross-claims filed
GRAVOIS, J., concurs with reasons.
For the following reasons, I respectfully concur with the majority opinion herein.
The majority opinion herein upholds the dismissal of Entergy's claims against Landaverde, Stewart, and Woodward "on account of our own motion of no cause of action on the basis of prematurity", then vacates the portion of the trial court's ruling dismissing Entergy's claims with prejudice, and amends the dismissal of Entergy's claims to be without prejudice, in order to allow an indemnity claim to be raised by Entergy in the event it is allocated fault.
The motions and cross-motions for summary judgment were in the nature of declaratory actions, i.e., they sought to define the parties' rights and obligations under the OPLSA in the event Entergy is cast in liability to Moreno, which has yet to be determined. See Faucheaux v. Prytania Medical Complex Owners Ass'n, 93-2042 (La.App. 4 Cir. 8/17/94), 642 So.2d 242, 245, where that court vacated portions of two summary judgments granted in favor of a third-party plaintiff on its indemnification claim against a third-party defendant, finding that decision on the issue was premature. As in Faucheaux, no fault determination has been made herein, nor have any damages been awarded relative to any party at this point in the case. Entergy's liability to Moreno is a contingency that has not yet arisen and may not arise.
After thoroughly considering the procedural posture of this case, rather than dismissing Entergy's claims without prejudice, I would simply vacate the trial court's rulings on Entergy's motions for summary judgment as premature and remand for further proceedings, allowing Entergy to re-urge its motions at such time as the matters asserted therein are ripe for determination.
The next judgment on appeal is the granting of motions for summary judgment filed by and in favor of Landaverde and its liability insurer Western World, dismissing the cross-claim and third party demand filed by Stewart against Landaverde and Western World, respectively. The majority opinion herein upholds the dismissal of Stewart's claims against Landaverde and Western World "on account of our own motion of no cause of action on the basis of prematurity", then vacates the portion of the trial court's ruling dismissing Stewart's claims with prejudice, and amends the dismissal of Stewart's claims to be without prejudice, in order to allow an indemnity claim to be raised by Stewart against Landaverde and/or Western World in the event it is allocated fault.
In its brief, Stewart frames the issues as follows:
Accordingly, Stewart is appealing in an abundance of caution should this court find that it owes Entergy indemnity under the OPLSA. Because the other judgments regarding the application of the OPLSA in this case have been found to be premature, I agree with the majority opinion herein that this judgment in favor of Landaverde and Western World against Stewart, too, is premature. Rather than dismissing Stewart's claims without prejudice, however, I would simply vacate the ruling on Landaverde's and Western World's motions for summary judgment and remand for further proceedings, allowing the parties to re-urge their motions at such time as the matters asserted therein are ripe for determination.
The majority opinion herein similarly dismisses Woodward's claims against Landaverde and Western World as premature and amends that dismissal to be without prejudice.
Woodward's cross-claim against Landaverde seeks indemnification from Landaverde, pursuant to the indemnification clause of the Temporary Labor Contract between Stewart and Landaverde, in the event Woodward is found liable to Entergy under the OPLSA. Because Woodward's contingent liability to Entergy has yet to be determined, I agree with the majority opinion herein that the trial court's ruling on Landaverde's motion for summary judgment against Woodward is premature. Rather than dismissing the motion without prejudice, however, I would simply vacate the ruling on Landaverde's motion for summary judgment against Woodward and remand for further proceedings, allowing the parties to re-urge their motions at such time as the matters asserted therein are ripe for determination.
Western World argues on appeal that the basis for its motion for summary judgment against Woodward was the "employer's liability" exclusion contained in the commercial general liability ("CGL") policy issued to Landaverde, which precluded coverage for bodily injury to an employee of the insured.
Because Western World's liability to Woodward has yet to be determined, I agree with the majority opinion herein that the trial court's ruling on Western World's motion for summary judgment against Woodward is also premature. Rather than dismissing Woodward's claims against Western World without prejudice, however, I would simply vacate the ruling on Western World's motion for summary judgment against Woodward and remand for further proceedings, allowing Western World to re-urge its motion at such time as the matters asserted therein are ripe for determination.