SUSIE MORGAN, District Judge.
This matter was tried before the Court, sitting without a jury, from March 25, 2013 to March 27, 2013.
1. Plaintiff Stewart Brothers Independent Contractors, L.L.C. ("SBIC") is a limited liability company organized under the laws of the State of Louisiana and having its principal place of business in the State of Louisiana.
2. Defendant Renata Lakes Apartments, L.P. ("RLA") is a limited partnership organized under the laws of the State of Delaware and having its principal place of business in the State of New York.
3. On February 10, 2010, an agreement captioned "Contract Between Owner and Contractor" (the "Contract") was executed by RLA and Stewart Brothers Construction, Inc.
4. The first page of Trial Exhibit 2, captioned "Exhibit A — Scope of Work," provides the following description of the project:
5. The third page of Trial Exhibit 2, captioned "Exhibit A. I. Bernard Construction: Scope of Work" describes on pages 3 and 4 the work to be done by Bernard Construction. The last paragraph of page 4 of Trial Exhibit 2 provides that "Except the jobs specifically designated above as the responsibility of Bernard Construction, the balance of the work is the responsibility of Stewart Brothers Construction. This is a turnkey project and all 83 units are to be delivered ready to rent, without defect, complete and the work shall include but not be limited to:". Even though this sentence ends with a colon, no description of work follows. No signatures appear on this portion of Exhibit A.
6. Pages 5-9 of Trial Exhibit 2, captioned "Exhibit A.II. Scope of Work — Stewart Brothers" describes the work to be done by SBIC. The description of the work is very general and no plans or specifications are provided.
7. Trial Exhibit 3, captioned "Exhibit B, General Specifications," describes the project as follows:
8. Article 2.2 of the Contract calls for the project to be completed within 220 calendar days of the project's "commencement date" of February 20, 2010, excluding delays caused by inclement weather and "reasons caused by the other contractor's delay."
9. Exhibit C to the contract, captioned "Payment Schedule," lists general tasks to be completed in each building or group of buildings.
10. Exhibit E of the contract, captioned "Materials Agreement," provides that RLA will provide all of the materials for the project, unless otherwise specified.
11. RLA agreed to pay SBIC $8,500 per apartment unit.
12. RLA paid a $3,000 mobilization fee to SBIC up front and later paid an additional $50,000 mobilization fee.
13. The Contract called for RLA to make progress payments "based upon Applications for Payment to the Owner by the Contractor and Certificates for Payment issued by the Owner as provided below and elsewhere in the Contract Documents."
14. The payment schedule defines the order in which SBIC was to perform the work and, as explained above, defines the specific tasks to be completed in each building or group of buildings.
15. According to the payment schedule, SBIC was to work on building L first, then buildings E and F, then buildings I and J, then building K, then building M, then building C, and then buildings A and B.
16. RLA and SBIC later agreed, however, that SBIC would work on all of the buildings at the same time to maximize efficiency of work to be done by subcontractors.
17. The payment schedule also further defines the progress payments called for in the contract.
18. The final payment of the Contract Sum was to be paid within 30 days after the Work had been completed.
19. Soon after the contract was signed, SBIC began work on the project.
20. The parties agree RLA paid $307,990.57 to SBIC for work performed on the project,
21. The evidence at trial demonstrated that SBIC performed the following tasks under the Contract for which RLA has not remitted payment:
22. In total, SBIC performed $37,900 worth of work under the Contract for which RLA has not remitted payment.
23. The evidence at trial demonstrated that SBIC performed the following taks that were not included in its scope of work under the Contract and for which RLA has not remitted payment:
24. SBIC also used $3,000 worth of generator gas on the project site.
25. Including generator gas costs, SBIC performed a total of $48,367.44 worth of off-contract work for which RLA has not remitted payment.
26. Including on- and off-contract work, SBIC performed a total of $86,267.44 worth of work at the Renata Lakes Apartment complex for which RLA has not remitted payment.
27. On August 3, 2010, 168 days after the Project's commencement date, RLA terminated the Contract and ordered SBIC off the Property.
28. Under the Contract, SBIC had 220 days from the commencement date to complete all work in the Contract. Accordingly, this work was done off the Contract. RLA does not dispute the $6,000 invoiced price, which the Court finds reasonable. phases of all buildings.
29. RLA listed a number of reasons why it believed it had sufficient cause to terminate the contract, including SBIC's failure to timely complete Phase One of the contract and deliver in "turnkey condition and ready to rent" sixteen town homes in Building L within 168 days (out of 220 total days to complete the project); SBIC's failure to complete work in the other buildings as called for in the other Phases of the contract within 168 days; SBIC's "failure to properly install air conditioners"; SBIC's "failure to remedy"; SBIC's "failure to adequately staff job"; and SBIC's "other unstated violations of the contract terms." The August 3, 2010 termination notice also included a narrative written by Mr. Becker detailing these alleged breaches.
30. SBIC admits the Project was not complete on the day the contract was terminated, but Kevin Stewart testified the Contract was terminated approximately sixty days early.
1. The Court has subject matter jurisdiction over this matter, pursuant to 28 U.S.C. § 1332. The parties are completely diverse and the amount in controversy, exclusive of interest and costs, exceeds $75,000.
2. Venue is proper in this district, pursuant to 28 U.S.C. § 1391(b), because a substantial part of the events or omissions giving rise to SBIC's claim occurred in the Eastern District of Louisiana and the property that is the subject of this action is situated in this district.
3. Because the Court is sitting in diversity, the Court applies the substantive law of Louisiana, the forum state. See, e.g., Holt v. State Farm Fire & Cas. Co., 627 F.3d 188, 191 (5th Cir. 2010) (citing Erie R. Co. v. Tompkins, 304 U.S. 64 (1938)). The Contract specifically provides that Louisiana law governs disputes arising thereunder.
4. Under Louisiana law, the elements of a valid contract are defined as follows:
La Bo J Partnership v. La. Lottery Corp., 08-1279 (La. App. 1 Cir. 1/30/09); 6 So.3d 191, 194, writ denied, 09-441 (La. 4/13/09); 5 So.3d 168; see also Granger v. Christus Health Cent. La., 12-1892 (La. 6/28/13); ___ So. 3d ___, 2013 WL 327128, at *17 (internal citations omitted) ("Under Louisiana law, the requirements for a valid contract are capacity, consent, a lawful cause, and a valid object.")
5. In this case, all four elements for a valid contract under Louisiana law are satisfied. First, both RLA and SBIC possessed capacity to contract. Second, both RLA and SBIC mutually and freely consented to the formation of the contract. Third and fourth, the object of the contract is determinable — the "gut rehabilitation" of units at the Renata Lakes Apartments complex. As a result, the Court finds that RLA and SBIC had a valid, enforceable contract under Louisiana law.
6. SBIC's obligations under the Contract were limited to the specific items listed in its scope of work and the attached payment schedule. Despite certain vague references in the Contract to the project being a "turnkey" project, there is no evidence that the parties ever reached an agreement that the project would, in fact, be a turnkey project in which SBIC was responsible for doing anything and everything necessary to complete the Project. Instead, both the Contract itself and the parties' conduct in carrying out the Contract — for example, RLA's divvying up work between SBIC and Bernard Construction and the Contract's confusing and contradictory explanations of the two contractors' scope of work — was such that there is no way SBIC could have ever understood the project to be its sole obligation to deliver "turnkey." Kevin Stewart's trial testimony confirms that SBIC understood the contract as specifically setting forth SBIC's scope of work and not requiring it to do anything and everything necessary to get all 83 units ready to rent, at least not independent of significant contributions from Bernard Construction, which also appears as a "Contractor" in the Contract. Accordingly, the Court finds SBIC was not obligated to deliver the project was not turnkey, and thus SBIC was obligated under the Contract only to do those things specifically listed in its scope of work and the payment schedule.
7. RLA terminated the Contract on the 168th day after the project's commencement date. Under the Contract, SBIC had 220 days from the commencement date to complete all phases of all buildings. Article 15.2 of the Contract states that payments may be withheld on account of a number of issues, including "reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Sum" and "reasonable evidence that the Work will not be completed within the Contract Time and that the unpaid balance would not be adequate to cover actual or liquidated damages for the anticipated delay." Article 20.2 provides that "if the Contractor defaults or persistently fails or neglects to carry out the work in accordance" with the Contract, RLA was entitled, upon providing SBIC seven days written notice, to either remedy the issue and deduct a proportional amount from the amount due to SBIC or, upon certification by the Owner or the Architect that sufficient cause exists to justify such action, to terminate the contract, take possession of SBIC's tools, and "finish the Work by whatever method the Owner may deem expedient." RLA's termination notice cited Article 20.2 as a basis for its early termination of the contract and RLA listed SBIC's failure to have more of the project completed by the 168th day as sufficient cause for invoking Article 20.2. However, the Court finds that sufficient cause did not exist for RLA's exercise of its option to terminate the contract under Article 20.2. The fact that SBIC had not completed certain Phases of the project on the 168th day of a 220-day project, without more, is not sufficient cause to terminate the Contract. Kevin Stewart testified at trial that even though only a few Phases of the project had been certified complete by this date, most of the difficult work had been performed, and that SBIC was still on schedule to complete all phases in a timely manner. In addition, while the termination notice stated that Building L was "uninhabitable," the evidence at trial demonstrated that SBIC obtained a certificate of occupancy for that building prior to RLA's termination of the contract.
8. RLA's unjustified early termination of the contract constitutes a breach of the Contract.
9. Under Louisiana law, the measure of damages as result of a defendant's breach of contract is the amount that will place the plaintiff in the same position it would have been in had the contract not been breached. See, e.g., Ducote v. City of Alexandria, 97-947 (La. App. 3 Cir. 2/4/98); 706 So.2d 673, 675 (quoting Meltzer v. Roof Coatings, Inc., 536 F.2d 663 (5th Cir. 1976) and citing Dixie Roofing Co. of Pineville, Inc. v. Allen Parish School Bd., 95-1526, 95-1527 (La. App. 3 Cir. 5/8/96); 690 So.2d 49, 56)). While the measure of damages in a breach of contract case is ordinarily governed by the four corners of the contract itself, Quality Flooring v. B.F. Const. Co., Inc., 09-1471 (La. App. 4 Cir. 1/5/11); 56 So.3d 395, 401, "when there is a legal right to recovery and there is no set way under the contract to determine the exact amount due, the trial court awards damages based upon all facts and circumstances of the case, and such award is within the trial court's discretion." Ducote v. City of Alexandria, 97-947 (La. App. 3 Cir. 3/6/96); 670 So.2d 1378, 1386 (citations omitted). The burden of proving entitlement to damages due to a breach of contract is on the party claiming rights under the contract. Quality Flooring, 56 So.3d at 401.
10. Because RLA breached the contract, SBIC has a legal right to recover damages from RLA. The Court, in its discretion and based on the facts and circumstances of the case, determines the appropriate amount of damages to be the value of the work actually performed by SBIC, either under or off the Contract, for which RLA has not remitted payment. In its post-trial memorandum, SBIC demands the remainder of the total contract price,$705,000,
11. As set forth above, SBIC performed work at the Renata Lakes Apartments complex, under and off the Contract and for which RLA has not remitted payment, in the reasonably invoiced amount of $86,267.44. RLA owes this amount to SBIC in damages.
12. In addition to the specific amounts listed on Invoice 31 for specific tasks, SBIC seeks $70,550 in "Contractors Profit."
13. RLA's counterclaim is based on the argument that the $307,990.39 RLA has already paid to SBIC is more than the amount it actually owed to SBIC. The Court has found that RLA owes additional sums to SBIC for work performed by SBIC under and off the Contract.
14. To date, RLA has not permitted SBIC to recover its tools from the Renata Lakes Apartments complex project site.
The Court will enter judgment accordingly.