YOUNG, D.J.
This action involves the alleged breach of a commercial lease agreement (the "Lease"). The plaintiff and building owner Bridge Over Troubled Water, Inc. ("Bridge") entered into the Lease with the defendant Argo Tea, Inc. ("Argo"), pursuant to which Argo would rent a portion of Bridge's premises to operate a tea shop.
Bridge sued claiming that Argo failed to perform its obligations under the Lease and that Argo engaged in unfair and deceptive practices in violation of Massachusetts General Laws, chapter 93A, and seeking to recover rent under the Lease's liquidated damages clause (an "accelerated rent" provision). Argo filed an answer in which it argued, as an affirmative defense, that Bridge failed to mitigate its damages. It also brought counterclaims seeking declaratory relief that the Lease's rent acceleration clause is unenforceable, claiming that Bridge itself violated chapter 93A, and asking the Court to impose a constructive trust for Argo's benefit upon any net revenue received by Bridge as a result of releasing the premises in order to prevent Bridge from "double-dipping."
Bridge now moves for summary judgment on both its counts for breach of contract and for violations of chapter 93A as well as on Argo's counterclaim for violations of chapter 93A. Argo, in turn, moves for summary judgment as to both of Bridge's counts for breach of contract and for violations of chapter 93A.
Bridge initiated this action for breach of contract and for violations of Massachusetts General Laws, chapter 93A ("chapter 93A") on October 21, 2015. Compl., ECF No. 1. Argo timely filed an answer which contained fifteen affirmative defenses and counterclaims for declaratory relief regarding the enforceability of the acceleration clause, violations of chapter 93A, and
On December 10, 2015, Bridge moved to dismiss each of Argo's three counterclaims and to strike its tenth affirmative defense (failure to mitigate). Pl.'s Mot. Dismiss Def.'s Countercls. and Strike Affirmative Defense, ECF No. 13; Mem. Supp. Pl.'s Mot. Dismiss Def.'s Countercls. and Strike Affirmative Defense, ECF No. 14. Argo opposed Bridge's motion to dismiss. Argo Tea's Opp. Mot. Dismiss Countercls. and Strike Affirmative Defense, ECF No. 21. After a hearing on January 20, 2016, this Court denied Bridge's motion to dismiss. Elec. Clerk's Notes, ECF No. 26.
On October 7, 2016, Bridge filed a motion for partial summary judgment, Pl.'s Mot. Partial Summ. J., ECF No. 38, on both its counts for breach of contract and for violations of chapter 93A, as well as on Argo's second counterclaim for violations of chapter 93A, along with a supporting memorandum, Pl.'s Mem. Supp. Mot. Partial Summ. J. ("Pl.'s Mem."), ECF No. 39, and statement of facts. Statement of Undisputed Facts Supp. Bridge's Mot. Partial Summ. J. ("Pl.'s Statement Facts"), ECF No. 40.
That same day, Argo filed a motion for summary judgment on both Bridge's counts for breach of contract and for violations of chapter 93A, Def.'s Mot. Summ. J., ECF No. 41, along with a supporting memorandum, Argo Tea's Mem. Supp. Mot. Summ. J., ("Def.'s Mem."), ECF No. 42, and statement of facts, Argo's Statement of Undisputed Facts ("Def.'s Statement Facts"), ECF No. 43.
On October 28, 2016, Argo and Bridge each filed a memorandum in opposition to the other's motion for summary judgment, Pl.'s Opp. Def.'s Mot. Summ. J. ("Pl.'s Opp. Mem."), ECF No. 59; Argo's Mem. Opp. Pl.'s Mot. Summ. J. ("Def.'s Opp. Mem."), ECF No. 55, along with supporting counterstatements of facts. Pl.'s Resp. Def.'s Statement Undisputed Material Facts ("Pl.'s Counterstatement Facts"), ECF No. 60; Argo Tea's Resp. Bridge's Statement Facts Supp. Mot. Partial Summ. J. ("Def.'s Counterstatement Facts"), ECF No. 56. On November 7, 2016, Argo filed a reply to Pl.'s Opp. Mem. Argo's Reply Supp. Mot. Summ. J. ("Def.'s Reply"), ECF No. 64.
Bridge is a nonprofit corporation headquartered in Massachusetts. Pl.'s Statement Facts ¶ 1; Def.'s Counterstatement Facts ¶ 1. Defendant Argo is a Delaware corporation headquartered in Illinois. Compl. ¶ 2, Answer ¶ 2; Pl.'s Statement Facts ¶ 2; Def.'s Counterstatement Facts ¶ 3. Bridge owns a building at 47 West Street in Boston. Pl.'s Statement Facts ¶ 4; Def.'s Counterstatement Facts ¶ 4. Bridge leases out part of the ground floor of that building ("the premises") to commercial tenants to help fund its nonprofit activities. Pl.'s Statement Facts ¶ 7; Def.'s Counterstatement Facts ¶ 7.
On January 8, 2015, Bridge and Argo entered into a lease agreement, according to which Argo was to operate a retail tea shop on the premises. Pl.'s Statement Facts ¶ 8; Def.'s Counterstatement Facts ¶ 8. The parties dispute much of what happened next.
Under the terms of the Lease, Argo had to make "reasonable efforts" to obtain all required governmental permits to build and operate the shop within 120 days from the signing of the Lease (
After many rounds of revision, Argo submitted revised plans to Bridge on April 20, 2015. Pl.'s Statement Facts ¶ 25; Def.'s Counterstatement Facts ¶ 25. The parties further dispute whether Bridge gave written approval of the plans on May 7, or whether, having failed to give written approval, they were deemed tacitly to have approved only on May 18, 2015 (after Argo's deadline to obtain all necessary permits). Pl.'s Statement Facts ¶¶ 31, 42; Def.'s Counterstatement Facts ¶¶ 31, 42.
On June 10, 2015, Argo wrote Bridge expressing its intent to terminate the Lease and seeking the return of its security deposit. Pl.'s Statement Facts ¶ 45; Def.'s Counterstatement Facts ¶ 45; Decl. Kyle Dorso Supp. Pl.'s Mot. Partial Summ. J. ("Dorso Decl."), Ex. 24, ECF No. 50-24. In that letter, Argo maintained that it was exercising its right to terminate the Lease pursuant to Lease Section 4.5(c) which provides in relevant part that:
Lease 12.
Bridge responded on June 16, 2015 by sending a letter to Argo rejecting its purported termination and stating that Argo was in breach of its obligations under Section 4.5(c) of the Lease. Pl.'s Statement Facts ¶ 4 6; Def.'s Counterstatement Facts ¶ 46; Dorso Decl., Ex. 25, ECF No. 50-25. Bridge further informed Argo that under the terms of the Lease, Argo had 30 days to cure the breach.
Under Federal Rule of Civil Procedure 56(c), summary judgment is appropriate when the moving party demonstrates that there exists no genuine issue of material fact and that it is entitled to judgment as matter of law.
Under Massachusetts law, whether a material breach of contract has occurred is matter of fact.
Here, the parties dispute whether Argo made "reasonable efforts" to obtain all required governmental permits to build and operate the shop within 120 days from the signing of the Lease, Pl.'s Mem. 2-5; Def.'s Mem. 4-5, including timely submitting complete renovation plans for Bridge's approval. Pl.'s Mem. 3, 10; Def.'s Mem. 4. To support its claim. Bridge points to email exchanges between Argo's employees and Argo's architects suggesting that Argo delayed putting together the plans required to obtain the permits until only a few days before the deadline for Bridge's approval. Pl.'s Mem. 5. Bridge also claims that Argo knowingly submitted an incomplete first set of plans to Bridge while stating that they were complete, or almost so.
Argo, in turn, argues that it diligently prepared the plans and timely submitted them to Bridge. Def.'s Mem. 4; Def.'s Statement Facts ¶ 10. Argo also contends that it did not breach the Lease because its failure to apply for permits was due to Bridge's failure to give timely written approval to Argo's plans, as required under
Bridge, in response, argues that Argo failed timely to submit its initial plans to Bridge and, had Argo done so, it would likely have had enough time to apply for permits even on a tight schedule. Pl.'s Opp. Mem. 5. Moreover, as Bridge points out, the Lease allowed for Argo to request a one-time 30-day extension of the deadline to obtain the permits.
From the record before this Court, there are genuine issues of material fact in dispute regarding Argo's alleged breach of contract. This is an issue properly reserved to the factfinder. Accordingly, summary judgment is denied as to the breach of contract claim.
The parties also dispute whether the Lease's accelerated rent provision is enforceable under Massachusetts law.
Whether a provision in an agreement is an enforceable liquidation of damages or an unenforceable penalty is matter of law.
Argo, however, offers only conclusory statements and no actual evidence, that at the time it negotiated the Lease with Bridge, the actual damages were not difficult to ascertain. Def.'s Mem. 8-9; Def.'s Statement Facts ¶ 17. Bridge, in turn, denies
Argo's argument that the accelerated rent provision does not represent a reasonable forecast of damages because it would allow Bridge to "double dip" by recovering rent from Argo while simultaneously collecting rent from a replacement tenant, Def.'s Mem. 9-11, finds no support in binding precedent. Nor does Argo provide at any point an estimate as to what reasonable damages would be in this case. The First Circuit has held that such failure is sufficient to defeat a claim that a liquidated damages contract provision represents an unreasonable forecast of damages and is grossly disproportionate to the expected damages.
Accordingly, this Court holds that the accelerated rent provision in the Lease is enforceable under Massachusetts law. The exact amount of damages to be awarded if Bridge prevails in its breach of contract claim, however, is properly reserved to the factfinder.
Chapter 93A prohibits "unfair methods of competition and unfair or deceptive acts or practices in the conduct of any trade or commerce,"
Whether a party's conduct amounts to an unfair or deceptive act or practice is matter of fact.
Even were this Court to conclude that the counts for violations of chapter 93A did not arise out of the breach of contract count, it would still reject both chapter 93A counts on the ground that any "`unfair practice[ ]' `must attain a level of rascality that would raise an eyebrow of someone inured to the rough and tumble world of commerce.'"
Accordingly, summary judgment as to this count is proper.
For the foregoing reasons, this Court GRANTS IN PART and DENIES IN PART Bridge's motion for partial summary judgment, ECF No. 38, and GRANTS IN PART and DENIES IN PART Argo's motion for summary judgment, ECF No. 41. Summary judgment is DENIED as to the claim and counterclaim for breach of contract; it is GRANTED as to the claim and counterclaim for alleged violations of chapter 93A, extinguishing those claims in this action.
Compl., Ex. 1 ("Lease") 12, ECF 1-1 (emphasis added).