FRANCIS M. ALLEGRA, Judge.
On September 21, 2011, plaintiff filed a complaint in this case. That complaint asserts the same claim as a complaint that was dismissed by this court for lack of jurisdiction on June 23, 2011. See Northrop Grumman Computing Sys., Inc. v. United States, 2011 WL 2508241 (Fed. Cl. June 23, 2011). That dismissal occurred because plaintiff failed to file a proper claim with the contracting officer, as is required, as a precondition to filing suit in this court under the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 601, et seq. On July 20, 2011, plaintiff submitted a new CDA claim to the contracting officer. On August 23, 2011, plaintiff appealed this court's dismissal order. On September 16, 2011, the contracting officer purported to deny plaintiff's claim. Five days later, plaintiff filed the instant suit.
On September 22, 2011, this court issued an order to show cause why this case should not be dismissed for lack of jurisdiction. That order explained —
On October 17, 2011, plaintiff filed its response to the show cause order, asserting that Sharman is inapposite here. As will be seen, however, plaintiff is wrong — and decidedly so.
This court has "jurisdiction to render judgment upon any claim by or against, or dispute with, a contractor arising under . . . [the Contract Disputes Act of 1978 (CDA)] . . . on which a decision of the contracting officer has been issued under . . . that Act." 28 U.S.C. § 1491(a)(2); see also Applied Cos. v. United States, 144 F.3d 1470, 1477 (Fed. Cir. 1998); North Star Alaska Housing Corp. v. United States, 76 Fed. Cl. 158, 183 (2007). In this framework, the "strict limits" of the CDA constitute "jurisdictional prerequisites to any appeal." England v. The Swanson Group, Inc., 353 F.3d 1375, 1379 (Fed. Cir. 2004) (citing Sharman Co., 2 F.3d at 1569 n. 6). Hence, jurisdiction is lacking "unless the contractor's claim is first presented to the contracting officer and that officer renders [or is deemed to render] a final decision on the claim." England, 353 F.3d at 1379; see also D.L. Braughler Co., Inc. v. West, 127 F.3d 1476, 1480 (Fed. Cir. 1997); James M. Ellett Constr. Co. v. United States, 93 F.3d 1537, 1541-42 (Fed. Cir. 1996); Bath Iron Works Corp. v. United States, 20 F.3d 1567, 1578-79 (Fed. Cir. 1994).
Jurisdiction is assessed based on the circumstances existing at the time the complaint was filed. Sharman, 2 F.3d at 1569; see also Mullan v. Torrance, 22 U.S. 537, 539 (1824) ("[T]he jurisdiction of the Court depends upon the state of things at the time of the action brought[.]"). Here, plaintiff did not have a valid final decision on its second claim at the time that it filed its second lawsuit.
This conclusion is dictated by Sharman. There, the Federal Circuit held that a "final decision" regarding progress payments issued by a contracting officer after a complaint presenting that claim had been filed in this court was a nullity and could not supply the court with jurisdiction under the CDA to consider a government counterclaim. 2 F.3d at 1567-68. The Federal Circuit's analysis started from the premise that "[o]nce a claim is in litigation, the Department of Justice gains exclusive authority to act in the pending litigation[,] . . . [a]nd that exclusive authority divests the contracting officer of his authority to issue a final decision on the claim." Id. at 1571. The Sharman court based this rule on its reading of 28 U.S. C. §§ 516 and 519, noting that under the former provision the Justice Department controls "the conduct of litigation in which the United States is a party," while under the latter provision, the Attorney General supervises all such litigation. 2 F.3d at 1571; see also Case, Inc., 88 F.3d at 1009.
Plaintiff asserts that Sharman is distinguishable, claiming that the contracting officer here was revested with the authority to decide its claim upon this court's dismissal of its first lawsuit. But, there is little doubt that, at the time the contracting officer rendered his purported decision on the second claim, the first claim was still in "litigation" within the meaning of 28 U.S.C. § 516. To be sure, in Hughes Aircraft Co. v. United States, 534 F.2d 889, 901 (Ct. Cl. 1976), this court's predecessor stated that because section 516 was "so broadly inclusive," it "must be narrowly construed." See also Fed. Deposit Ins. Corp. v. Irwin, 727 F.Supp. 1073, 1074 (N.D. Tex. 1989), aff'd, 916 F.2d 1051 (5th Cir. 1990). But, even a narrow construction of the term "litigation" must include, within its scope, a matter on appeal. The common understanding of the term "litigation" requires as much. See, e.g., Black's Law Dictionary 952 (8th ed. 1999) (defining litigation as a "[l]egal action, including all proceedings therein").
Sharman undoubtedly remains good law in this circuit. See, e.g., Renda Marine, 509 F.3d at 1379-80; Case, 88 F.3d at 1009-10; see also Bath Iron Works Corp., 20 F.3d at 1579; Roxco, Ltd. v. United States, 77 Fed. Cl. 138, 149 (2007). This court must follow this binding precedent and so too must plaintiff. Under this precedent, this court plainly lacks jurisdiction over plaintiff's second complaint.
Based on the foregoing, plaintiff's complaint is hereby
28 U.S.C. § 516. Section 519 of the same title provides that:
28 U.S.C. § 519. These statutory provisions are the legislative descendants of section 5 of Executive Order 6166 (June 10, 1933) (reprinted at 5 U.S.C.A. § 901), which stated that "[a]s to any case referred to the Department of Justice for . . . defense in the courts, the function of decision whether and in what manner . . . to defend, or to compromise, . . . or to abandon . . . defense, now exercised by an agency or officer, is transferred to the Department of Justice." See Computervision Corp. v. United States, 445 F.3d 1355, 1372 (Fed. Cir. 2006).
Northrop Grumman Computing Sys., Inc. v. United States, No. 07-613 (July 1, 2011).