MARIANNE O. BATTANI, District Judge.
Before the Court is Defendant LaSalle Group Incorporated's ("LaSalle") Motion for Summary Judgment brought pursuant to Fed. R. Civ. P. 56(a). (Doc. 22). Plaintiff Gerken brought a breach of contract action against Defendant pursuant to Michigan common law after Defendant refused to agree to a price increase. Defendant motioned for summary judgment and the Court heard oral argument on July 19, 2012. For the reasons that follow, the Court
Defendant LaSalle Group Inc., a contractor, entered into a contract with non-party Menards ("Owner"), a home improvement store chain, to build a store location in Oregon, Ohio. On July 17, 2007, Defendant entered into a fixed price subcontract ("Project") with Plaintiff Gerken Paving Inc. for a price of $545,705.00. (Doc. 24 p. 3). Plaintiff was required to pave the access roads and parking lots for the project, including an outlot on Curtis Road, and complete items on a punchlist generated by LaSalle. (
Under the terms of the contract, all preliminary grading work was to be completed by October 26, 2007. (Doc. 22 Ex. A at 2a). Gerken was required to finish all asphalt paving work no later than November 16, 2007, and the project was to be completed no later than December 3, 2007. (
The start of the project was delayed a number of weeks. Although Gerken employees believed the delay was due to unstable soil on the store grounds, the record is not entirely clear regarding the reason for the delay. (Doc. 22 Ex. C pp. 61-63). However, neither LaSalle nor Gerken appear to be at fault. (
Gerken began paving on November 12, 2007 and worked for the next three days, November 12, 13, and 14, in temperatures above the 40 °F required by the ODOT guidelines. (Doc. 25 Ex. 1). Despite the adequate weather conditions on those three days, Plaintiff exceeded its projected amount of asphalt by 162 tons on leveling and 254 tons on surface. (Doc. 22 Ex. D).
Gerken did not resume paving work on the project until November 28. (Doc. 22 Ex. H p. 32). Gerken employee John Yocum, the area manager, noted on November 27 that air temperature for parts of the next day, November 28, were forecasted to below the 40 °F requirement. (Doc. 22 Ex. C at 24-25). Yocum wrote a letter to Defendant letting them know that the temperature would be below ODOT guidelines, and warning that any paving done in conditions below 40 °F would prevent the asphalt from "achieving density and adhesion at the joints." (Doc. 22 Ex. K). Gerken also stated that it would not warrant any work that was completed when the air temperature was below 40 °F. (
Defendant also signed two field directives on November 29, 2007 allowing an increase in the contract price for additional materials that were required due to "hidden conditions." (Doc. 25 Ex. 4 p. 1). LaSalle permitted a $2,000 increase in the contract price for additional asphalt to fix very specific area of the project. (
Plaintiff completed paving on the main portion of the project after thirteen days of work spanning from November 12 — December 15, 2007. Plaintiff had not paved the outlot as required under the terms of the contract, claiming the cold weather prevented any further work. (Doc. 22 Ex. C at 59). On December 20, Gerken wrote LaSalle asserting that Gerken used substantially more asphalt to complete the job than anticipated in the contract price. (Doc. 22 Ex. D). Plaintiff incurred overages in asphalt every day of paving, including the three days in November when the weather was within the ODOT specifications. (
Plaintiff did not do any further work for Defendant after December 15, 2007. On March 26, 2008, Defendant wrote Plaintiff refusing to pay for the asphalt overages stating the parties had a fixed contract price. (Doc. 22 Ex. I). On June 3, 2008, over six months after Plaintiff first introduced the asphalt overages, Plaintiff sent a day-by-day accounting of the overages incurred on the project and requested payment from LaSalle. (Doc. 25 Ex. 11). Defendant did not pay Gerken the overages.
In Spring 2008, LaSalle contacted Gerken and demanded that Gerken complete the paving of the outlot and the punchlist items as required by the contract. On May 23, 2008, Plaintiff responded that they could not pave the outlot unless Defendant agreed to a $7,442 price increase due to the increased cost of petroleum. (Doc. 25 Ex. 8). Defendant refused to pay the additional amount and on June 12, 2008 sent an email informing Plaintiff that if the outlot was not paved before that Monday, Owner would pave it at Plaintiff's expense. (Doc. 25 Ex. 9). Gerken never paved the outlot and LaSalle stated it had a third party pave the outlot at a cost of $24,880.00.
Under the contract, Gerken was required to complete punchlist items prepared by LaSalle. (Doc. 22 Ex. A at 2a). The record is unclear regarding what punchlist items were requested and whether or not Plaintiff failed to complete them. Defendant simply claims that Plaintiff failed to complete the punchlist. (Doc. 22 at 6). Plaintiff claims that there were only two items on the punchlist, the first to fill in a crack in the asphalt and the second to fill in low spots in the asphalt. (Doc. 25 Ex. 12). It claims it does not have to repair the crack in the asphalt because LaSalle waived the warranty for that work. (
Defendant paid Plaintiff $491,134.50 for the paving work, which was the full contract price ($545,705.00) less the 10% ($54,570.50) retainage (a common practice in the construction industry in which the contractor retains a certain percentage of the amount due to ensure that the remainder of the work is completed). (Doc. 22 at 6). LaSalle claims they withheld the retainage due to Gerken's failure to pave the outlot and complete the punchlist items.
Summary Judgment is appropriate only when there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law. Fed. R. Civ. P. 56(a). The central inquiry is whether the evidence presents a sufficient disagreement to require submission to a jury or whether it is so one-sided that one party must prevail as a matter of law.
The moving party bears the initial burden of showing the absence of a genuine issue of material fact.
Plaintiff filed a breach of contract complaint against Defendant for $143,014.56 in damages; $90,915.01 in asphalt overages and $52,099.55 in retainage fees. Defendant filed a motion for summary judgment contending A) Gerken is not entitled to the asphalt overages because it did not follow the terms of the contract to increase the contract price, and B) LaSalle is entitled to a portion of the retainage amount because Gerken failed to pave the outlot. The Court begins with the overages issue.
The parties dispute whether Plaintiff followed the terms of the contract to increase the contract price and whether Plaintiff is therefore entitled to asphalt overages. The cardinal rule of contract interpretation is to ascertain the intent of the parties. The intent of parties is discerned from the agreement itself.
The court "must look for the intent of the parties in the words used in the instrument. The court does not have the right to make a different contract for the parties or to look to extrinsic testimony to determine their intent when the words used by them are clear and unambiguous. . . ."
"If the contract language is clear and unambiguous, its meaning is a question of law. Where the contract language is unclear or susceptible to multiple meanings, interpretation becomes a question of fact."
On the other hand, "[a] contract is ambiguous if `its words may reasonably be understood in different ways.'"
The paving contract explicitly required that any changes must be submitted in writing. The writing requirement was clearly stated at the beginning of the document (Doc. 22 Ex. A at 2 of 2) and affirmed again a number of times in § 5, which governed contract changes or claims. (
Section 5 requires a written request for any additional materials; Plaintiff never made a written request for more asphalt. Even if the Contractor makes the original request for additional materials orally, the Subcontractor is still required to submit written confirmation of the request within five days of the agreement. There is no exception in the contract to this requirement. Plaintiff claims that there is an exception contained in § 5.6 for time and material contracts. Gerken asserts that the November 29 field directive changed the contract from a fixed price contract to a time and material contract, and therefore Gerken did not need a written request for the additional work before that work started.
Plaintiff's assertion is incorrect for two reasons. First, the November 29 field directive did not change the contract from a fixed price contract to a time and material contract. The contract was for a fixed price. The existence of one very specific, relatively minor change in the terms does not transform the entire agreement from a fixed price contract to a time and material contract. The field directive was clear that the time and material work was limited to the "board shed area which is from the catch basin line to 13 feet from the board shed . . . not to exceed $4,000." (Doc. 25 Ex. 4 at 2). This field directive was expressly limited in scope to a small area of the project and did not change the entire contract into a time and material contract. Moreover, the additional materials were required because a third party damaged the area, not because, as Plaintiff claims, the cold weather necessitated additional asphalt. Because the need for additional materials on November 29 was not caused by cold weather, Plaintiff's contention that Defendant knew other cold days would also require more time and material work is baseless.
Second, § 5.6 provides an exception to the requirement that a detailed pricing be submitted five days before the start of the work. It does not provide an exception to § 5.4, which requires the subcontractor to submit, in writing, any change based on the contractor's written or verbal order within five days of the start of the work. Section 5.6 states "If the work is to be performed on a time and material basis, this detailed pricing must be submitted within five (5) days from the completion of the work." (Doc. 22 Ex. A at 4). In time and material contracts, the only difference is that the subcontractor does not need to know or submit the detailed price of the additional work before that work begins. The section also states that "nothing in this paragraph effects or impacts any other paragraph of this agreement including, but not limited to, the requirement that all claims must be in writing." (
Finally, Plaintiff was undeniably aware of the writing requirement and of the process for changing the contract. Gerken demonstrated this knowledge when it complied with the change process on a number of occasions during its work on the project. First, Plaintiff sent ten separate letters to request, in writing, that Defendant release Plaintiff from warranting its work. Gerken failed to mention LaSalle's alleged oral promise to pay for additional material in any of these letters. Additionally, Plaintiff complied with the change procedures in § 5 when the parties agreed to the field directives on November 29, 2007. The parties noted that a third party had damaged an area of asphalt, agreed that additional materials were required to fix the damage, and issued a written confirmation of the decision to use additional materials. Plaintiff was clearly aware of the change procedures in the contract, including the writing requirement, because it correctly used those procedures on several occasions during the paving work. Despite this awareness, Plaintiff failed to submit a written request for asphalt overages in accordance with the parties' express agreement. It is therefore not entitled to recover those overages in this breach of contract action.
The parties disputed in their briefs whether LaSalle is entitled to withhold the entire 10% retainage amount after Gerken failed to pave the outlot. At the hearing, LaSalle changed its position and acknowledged that it owes Gerken the retention amount minus the cost of paving outlot, the cost of which LaSalle calculated to be $24,880.00. However, Defendant also contends that it is entitled to attorney fees, which would be taken out of the remaining retainage amount. This issue was not before the Court and it therefore makes no ruling on this matter. LaSalle has ten days from the date of this Opinion and Order to file a motion for attorney fees and it may withhold the retainage amount until this issue is resolved.
For the reasons discussed above, the Court