PER CURIAM.
Plaintiff, Nordlund & Associates, Inc., appeals as of right the circuit court's order confirming an arbitration award and denying plaintiff's motion to vacate or modify the arbitration award. We affirm.
On January 7, 2005, plaintiff filed a breach of contract action against the village of Hesperia.
On January 22, 2007, the circuit court entered a stipulation and order for arbitration pursuant to MCL 600.5001 et seq. The order provided that the parties would submit "all issues in this action which are subject to the jurisdiction of this court" to binding arbitration. Pursuant to the circuit court's order, the parties executed an arbitration agreement, which stated that "[a]ll theories/defenses and affirmative defenses raised in the pleadings of the parties during the course of these proceedings and associated damages, offsets, and failure to mitigate claims" would be submitted for arbitration.
Before this dispute, plaintiff acted as defendant's engineer for roughly 22 years. Two projects are relevant to this appeal: (1) the Sunset Boulevard/Family Dollar water main project and (2) improvements to the sewer system and wastewater treatment plant, known as "the SRF project" for its connection to the State Revolving Fund.
Innovative Construction hired plaintiff to do work in relation to the opening of a Family Dollar store near Sunset Boulevard. In furtherance of this project, plaintiff filed an application on behalf of defendant, seeking authorization to extend a water main along Sunset Boulevard. Plaintiff billed defendant $600 for this work, but never received payment.
Plaintiff also prepared additional permit applications and gave them to defendant to submit to the proper authorities. These permits, which were subsequently denied, required approval by the Michigan Department of Environmental Quality (MDEQ) before the water main could be installed. However, Innovative Construction installed the water main before any permits were approved. As a result, the MDEQ fined defendant $12,140. Defendant sought reimbursement from plaintiff for that amount, charging that plaintiff was responsible for the premature installation.
On November 10, 2003, by written contract, defendant hired plaintiff to perform professional services. On August 5, 2004, defendant terminated the contract. The contract provided that it could be terminated without cause and that, upon termination, "[a]n equitable adjustment shall be made in the contract price." Defendant argued that because only 65 percent of plaintiff's work was salvageable by the engineering
The parties submitted to the arbitrator an "arbitration summary," in which they fully briefed the issues to be decided. Following a hearing, the arbitrator issued an opinion setting forth the following findings: (1) plaintiff was entitled to $14,787.29 for the use of its plans and specifications on the SRF project, (2) defendant was entitled to $19,787.42 in compensation for plaintiff's breach of the SRF project contract (that amount being the difference between plaintiff's contract price and what defendant ultimately paid another party to complete the contract), (3) defendant failed to prove that it had paid plaintiff $10,000 on the SRF project, (4) defendant was not entitled to recover any damages attributable to the Sunset Boulevard/Family Dollar project, and (5) plaintiff was entitled to payment of its overdue $600 invoice relating to the Sunset Boulevard/Family Dollar project. After calculating all offsets, the arbitrator awarded defendant a total of approximately $4,400.
Plaintiff moved to vacate or modify the arbitration award, arguing that the arbitrator had "miscalculated" the award of damages, MCR 3.602(K)(2)(a), and exceeded his powers by deciding an issue that had not been submitted to arbitration, MCR 3.602(J)(2)(c). Specifically, plaintiff argued that the breach of contract claim, which the arbitrator found entitled defendant to $19,787.42 in compensation, was never brought or argued at arbitration, and that the arbitrator's decision thus reached "beyond the boundaries of the submission" and should be vacated.
In response, defendant argued that there was no mathematical "miscalculation" as envisioned by MCR 3.602(K)(2)(a) and that the arbitrator did not exceed his powers because no express limit was placed on those powers under the arbitration agreement. The motion was heard on November 10, 2008, and the circuit court ruled from the bench as follows:
The circuit court thereafter issued a written order confirming the arbitration award and denying plaintiff's motion.
Plaintiff argues that the trial court erred by confirming the arbitration award because the arbitrator both exceeded his powers when he rendered a decision on an issue that had not been submitted to arbitration and "miscalculated" the award of damages. We disagree. A trial court's decision to enforce, vacate, or modify an arbitration award is reviewed de novo. Saveski v. Tiseo Architects, Inc., 261 Mich.App. 553, 554, 682 N.W.2d 542 (2004).
If an agreement to arbitrate provides that judgment may be entered on the arbitration award, then it is considered a statutory arbitration. Gordon Sel-Way, Inc. v. Spence Bros., Inc., 438 Mich. 488, 495, 475 N.W.2d 704 (1991). Here, the parties' arbitration agreement stated that a party could move to enforce the award
MCR 3.602 governs judicial review and enforcement of statutory arbitration agreements. MCR 3.602(A). MCR 3.602(K) sets forth the reasons for which a trial court may correct or modify an arbitration award:
In addition, a trial court must vacate an arbitration award if a party has filed a motion requesting it and one of the following has occurred:
Plaintiff first argues that the arbitrator exceeded his powers, MCR 3.602(J)(2)(c), when he rendered a decision on an issue that had not been submitted to arbitration. Specifically, plaintiff claims the arbitrator exceeded his powers in ruling that defendant was entitled to $19,787.42 in damages for plaintiff's breach of the contract for the SRF project.
The scope of an arbitrator's remedial authority is "limited to the contractual agreement of the parties." Ehresman v. Bultynck & Co., PC, 203 Mich.App. 350, 355, 511 N.W.2d 724 (1994). Thus, "[a]rbitrators exceed their power when they `act beyond the material terms of the contract from which they primarily draw their authority, or in contravention of controlling principles of law.'" Saveski, 261 Mich.App. at 554, 682 N.W.2d 542, quoting DAIIE v. Gavin, 416 Mich. 407, 434, 331 N.W.2d 418 (1982).
In this case, the parties' arbitration agreement provided that "[a]ll theories/defenses and affirmative defenses raised in the pleadings of the parties during the course of these proceedings and associated damages, offsets, and failure to mitigate claims" shall be submitted for arbitration. Defendant's amended counterclaim included the following allegations:
It is clear from these allegations that defendant was seeking damages for breach of the SRF project contract. Thus, the arbitrator did not exceed his powers by concluding that defendant was entitled to $19,787.42 in compensation for plaintiff's breach of the SRF project. See Saveski, 261 Mich.App. at 554, 682 N.W.2d 542. The terms of the agreement limited the scope of arbitration to those issues raised in the pleadings, and defendant raised the issue of damages for breach of the SRF project contract in its pleadings. That this issue was not raised in the parties' subsequent arbitration summaries is irrelevant to whether the arbitrator exceeded his powers when rendering the award. Therefore, the arbitrator did not exceed his powers as set forth in the arbitration agreement, see Ehresman, 203 Mich.App. at 355, 511 N.W.2d 724; Saveski, 261 Mich.App. at 554, 682 N.W.2d 542, and the trial court therefore did not err by confirming the arbitration award and denying plaintiff's motion to vacate or modify it.
Plaintiff's final argument on appeal is that the arbitrator miscalculated the award of damages, asserting that the calculation was faulty because the arbitrator failed to grasp the clear and concise meaning of the contract. Plaintiff contends that this Court must review various valuations and contract interpretations made by the arbitrator by characterizing them as a miscalculation of the award. We disagree.
MCR 3.602(K)(2)(a) states that a court must modify an arbitration award if "there is an evident miscalculation of figures or an evident mistake in the description of a person, a thing, or property referred to in the award." This Court has repeatedly emphasized that it must carefully evaluate claims of arbitrator error to ensure that they are not being used as a ruse to induce this Court to review the merits of the arbitrator's decision. Gordon Sel-Way, Inc., 438 Mich. at 497, 475 N.W.2d 704; Washington v. Washington, 283 Mich.App. 667, 675, 770 N.W.2d 908 (2009). MCR 3.602(K)(2)(a) allows for modification or correction of an award only when it is based on a mathematical miscalculation, such as where an arbitrator erred in adding a column of numbers, or an evident mistake in a description. Because plaintiff's alleged error concerns the interpretation of the underlying contract, and not descriptions or mathematical calculations, it cannot be said that there was an evident mistake for purposes of MCR 3.602(K)(2)(a). Therefore, the circuit court properly refused to modify the arbitration award on that basis.
Affirmed.