PAUL A. MAGNUSON, District Judge.
This matter is before the Court on the parties' cross-Motions for Summary Judgment or Partial Summary Judgment. For the following reasons, Plaintiff's Motion for Summary Judgment is denied and Defendant's Motion for Partial Summary Judgment is granted.
Defendant Miller Architects and Builders, Inc. ("Miller"), is a Minnesota-based design/build company. In 2013, a real-estate trust called IRET-Cardinal Point LLC ("IRET") hired Miller to design and build a two-building luxury apartment complex in Grand Forks, North Dakota. IRET ultimately terminated Miller's role in the project, ostensibly because of faulty construction and poor design. IRET then commenced arbitration against Miller under the terms of the parties' contract. That arbitration is ongoing, and is still in its preliminary stages.
In March 2015, Miller tendered IRET's allegations to its insurer, Plaintiff Westfield Insurance Company. Westfield determined that it had no duty to defend or indemnify Miller in the arbitration, and Westfield filed this lawsuit seeking a declaration to that effect. Westfield now seeks summary judgment on its duty to defend. Miller has cross-moved for partial summary judgment, contending that Westfield's breach of its duty to defend means that Miller is entitled to recover the attorney's fees it has thus far expended in the arbitration as well as the fees it has incurred in defending this coverage action.
The parties focus their discussions on five broader categories of claimed damage, rather than each of the more than 65 separate damages claims IRET has preliminarily raised in the underlying arbitration. (Medeiros Aff. (Docket No. 31) Ex. 2.) Miller contends that all of these five categories fall within its insurance policies' coverage, and thus that the Court need look no further than the five categories to determine that Westfield has the duty to defend Miller in the arbitration. Westfield argues that none of these categories is covered and that Miller's failure to discuss the remaining items of damages constitutes a waiver of its claims regarding those remaining items. The waiver argument is specious and the Court will not address it further. The Court agrees with Miller that it can resolve the parties' dispute by examining these five categories of damages:
An insurer's duty to defend is determined by comparing "the allegations in the complaint in the underlying action with the relevant language in the insurance policy."
This case requires construction of perhaps the most oft-litigated provisions in standard Commercial General Liability ("CGL") insurance policy
Miller's CGL policy provides insurance for "those sums that the insured becomes legally obligated to pay as damages because of `bodily injury' or `property damage'" that is "caused by an `occurrence.'" (Compl. Ex. 1, CG0010413 ¶ 1.a-.b (Docket No. 1-1 at 125).) However, the policy excludes from coverage "property damage" to
(
The "products-completed operations hazard" in turn provides for coverage from damage "arising out of . . . `your work'" unless the "work . . . has not yet been completed or abandoned." (
Thus, according to these provisions, the policy excludes from coverage all damage caused by defective work, unless the damage was caused after the insured's work was completed. And even if the work was completed, damages are still excluded unless the work was performed by a subcontractor. There seems to be no dispute that Miller's subcontractors' work cause most if not all of the five categories of damages listed above.
Westfield first argues that the Court should apply the business risk doctrine to the policy provisions. Under that doctrine, commercial insurance policies are interpreted to exclude coverage for damage caused by conduct that would constitute a breach of contract, such as defective design, faulty construction, and the like.
But the business risk doctrine arose out of a previous, even more opaque, version of the standard-form CGL policy, one that was replaced in 1986 by the current version and the exclusions quoted above.
Westfield next asserts that the damages IRET claims in the underlying arbitration are not "occurrences" within the meaning of the CGL policy. The policy defines "occurrence" as "an accident, including continuous or repeated exposure to substantially the same general harmful conditions." (Compl. Ex. 1, CG0010413 ¶ 13 (Docket No. 1-1 at 139).) The parties agree that Minnesota law defines "accident" as "an unexpected, unforeseen, or undesigned happening or consequence from either a known or an unknown cause."
Westfield relies on cases in which a contractor knowingly deviated from contract specifications for its argument that an "occurrence" did not cause the damages at issue. But even if discovery in the arbitration reveals that Miller's subcontractors knowingly or intentionally deviated from the design specifications, that deviation is still unintended and an "accident" from Miller's perspective. Moreover, as the policy acknowledges, damage caused by the work of a subcontractor is not excluded from coverage. (Compl. Ex. 1 CG0010413 ¶ l (Docket No. 1-1 at 129).) Westfield cannot escape its duty to defend through a creative interpretation of the policy's definition of "occurrence."
The policy excludes from coverage damage to which the products-completed operations hazard applies, unless that work was performed by a subcontractor. (Id. ¶ l (Docket No. 1-1 at 129).) Although the exclusion purports to exclude from coverage all damage "arising out of `your product' or `your work' (
Westfield concedes that if the claims fall within the subcontractor exception in exclusion l, the claims are arguably covered. According to Westfield, exclusion l does not apply because Miller's work on the project was not "complete" and thus the productscompleted operations hazard does not apply in the first instance.
Westfield characterizes Miller's departure from the project as a termination for cause, arguing that therefore Miller did not complete its work on the project. The evidence, however, does not support this characterization. Rather, Miller and IRET agreed that IRET terminated Miller "for convenience" and not for cause. (Kallhoff Decl. (Docket No. 34) Ex. C at 1 (stating that "IRET terminated the MAB Contract under Section 9.3");
Miller seeks a ruling that Westfield breached its duty to defend and owes Miller the costs and fees Miller expended in defending the arbitration and in defending this coverage action. Westfield does not take issue with the premise that if a claim is arguably covered, it had the duty to defend as of the time Miller tendered the offer. Instead, Westfield insists that IRET has not raised any arguably covered claims in the arbitration.
Having determined that at least some of the claims in the arbitration are arguably covered, the inescapable conclusion is that Westfield breached its duty to defend and Miller is entitled to recover its defense costs, including attorney's fees, from Miller's tender to Westfield in March 2015 to the present. Those costs include the fees and costs Miller incurred in litigating this coverage action.
Accordingly,