PER CURIAM.
The Michigan Public Service Commission (PSC) entered an order approving a certificate of necessity (CON) for a life cycle management (LCM) project, comprised of 117 subprojects, at the Donald C. Cook Nuclear Power Plant owned by the Indiana Michigan Power Company (Indiana Michigan). The PSC preapproved recovery of a CON amount of $773,611,000 for projected project costs, as well as a 10% management reserve of $77,361,100, for a total of $850,972,100. In these consolidated appeals,
This appeal requires construction of MCL 460.6s. Subsection (1) of this statute provides that an electric utility can seek a CON for "a significant investment in an existing electric generation facility," and that a "significant investment" may include "a group of investments reasonably planned to be made over a multiple year period not to exceed 6 years for a singular purpose such as increasing the capacity of an existing electric generation plant." Subsection (4) requires that the PSC specify the costs approved if it approves a CON. Subsection (9) provides that the PSC must include in rates all reasonable and prudent costs for which the CON has been granted when the facility is considered "used and useful."
Appellants maintain that Indiana Michigan's LCM project does not qualify for a CON under the statute. Alternatively, they argue that the PSC erred by approving a management reserve for the LCM project. ABATE argues that eight subprojects that required an incremental expenditure for a potential future uprate should not have been approved, and the Attorney General argues that greater specification of costs allowed and disallowed was necessary.
The PSC did not err by construing the statute so as to determine that the LCM project is a significant investment comprised of a group of investments being made for a singular purpose. Moreover, the PSC did not err by approving the eight subprojects contested by ABATE. However, we conclude that the management reserve was not supported by substantial evidence on the whole record. We decline to address the specification-of-costs issue because it was not properly preserved.
In 1975 and 1978, the Donald C. Cook Nuclear Power Plant placed its two nuclear reactors in service. The Nuclear Regulatory Commission (NRC) had issued 40-year operating licenses for each reactor in 1974 and 1977, consistent with their expected 40-year life spans. In 2005, the NRC granted Indiana Michigan 20-year license renewals for the units, allowing them to operate until 2034 and 2037. Indiana Michigan indicated that the extension to 60 years would require "that the plant's systems, structures, and components be inspected, maintained, refurbished, and replaced on a managed basis." In fact, the NRC exacted a commitment to manage the aging of passive, long-lived components as a condition of continued operations. Indiana Michigan confirmed that continued investment was required to maintain highly reliable operations.
Specifically, Indiana Michigan claimed that to take advantage of the license renewals, it had to undertake a multiyear project involving LCM investment in the
Indiana Michigan sought a CON for its LCM project, which was originally projected to cost $1.169 billion. The LCM project included 117 subprojects that were to be implemented from the second half of 2011 through 2018. The subprojects involved replacing various components. The cost of each subproject was separately calculated, and included a risk reserve. Indiana Michigan also proposed a management reserve, incorporated in the $1.169 billion, to cover unknown contingencies for the project as a whole. It acknowledged that a power uprate of capacity was feasible (meaning power output could be increased) and that "a very small investment in the upsizing of certain equipment to accommodate a potential future uprate" was also included in the LCM project, as it would be less costly to upsize now.
Paul Chodak III, the president and chief operating officer of Indiana Michigan, testified that the
Michael Carlson, the vice president of site support services at the Cook plant, added that without capital to support the LCM project, the reactors would have to be shut down before their extended license lifetimes due to equipment degradation.
ABATE and the Attorney General argued that the LCM project was akin to capital expenditures for maintenance that would simply allow for continued operations. They maintained that the project did not qualify as a "significant investment in an existing electric generation facility" because it was not a "group of investments" made "for a singular purpose such as increasing the capacity of an existing electric generation plant." Regarding this point, the PSC concluded that the requirement that a project be for a "singular purpose" did not require that the project increase capacity and that "an LCM project, for the singular purpose of assuring that safe and reliable power can continue to be produced from a nuclear generation facility until the end of its extended license, comports with the requirements of Section 6s(1) and thus is eligible for a CON." Further, it concluded that the costs should cover the six-year period of 2013 through 2018 (rather than the second half of 2011 though 2018 as had been requested), and that the costs for this abbreviated period would total $773,611,000.
Appellants also argued that a management reserve should be disallowed. The PSC agreed that Indiana Michigan had not carried its burden of proving that a proposed management reserve of $220 million, in addition to the risk reserve included in the CON amount, was reasonable. However, acknowledging that "knowledge of the future is not achievable given the complexity of the LCM project and the tasks and resources required to achieve it," the
Finally ABATE argued that, to the extent eight subprojects involved upsizing some equipment to accommodate a potential future uprate, they should be disallowed. The PSC held that the cost of replacing a turbine nearing the end of its life with significant signs of wear should be allowed. With respect to the seven other projects, the PSC held that they should be permitted even though there were incremental costs associated with future uprates for which a current need could not be established.
In In re Application of Consumers Energy Co. For Rate Increase, 291 Mich.App. 106, 109-110, 804 N.W.2d 574 (2010), this Court described the scope of our review as follows:
The operation of the competent, material, and substantial evidence test was explained in In re Application of Detroit Edison Co., 483 Mich. 993, 764 N.W.2d 272 (2009):
We reject ABATE's suggestion that the substantial evidence test does not apply on grounds that approval of the CON involved ratemaking. In Detroit Edison Co. v.
MCL 460.10a(1) provides: "The commission shall issue orders establishing the rates, terms, and conditions of service that allow all retail customers of an electric utility or provider to choose an alternative electric supplier." In contrast, MCL 460.6s(4) requires a contested case hearing on a CON application, MCL 460.6s(1) requires various findings before a CON can be approved, and a determination regarding the amount of estimated costs that should or should not be approved requires factual input and factual findings. Since a determination of factual matters is required, the substantial evidence test applies.
ABATE further argues that the PSC's decision regarding the management reserve was arbitrary and capricious. This Court recently held in In re Application of Detroit Edison, Co. to Increase Rates, 297 Mich.App. 377, 383, 823 N.W.2d 433 (2012), aff'd 495 Mich. 884, 838 N.W.2d 701 (2013), quoting Attorney General v. Pub. Serv. Comm., 206 Mich.App. 290, 296, 520 N.W.2d 636 (1994), that MCL 462.26(8) "`requires a reviewing court to determine only whether an order is unlawful or unreasonable, not whether it is arbitrary and capricious.'"
Finally, the standard of review for an agency's interpretation of a statute was set forth in In re Complaint of Rovas Against SBC Mich., 482 Mich. 90, 103, 754 N.W.2d 259 (2008), quoting Boyer-Campbell Co. v. Fry, 271 Mich. 282, 296-297, 260 N.W. 165 (1935):
In this case of first impression, we hold that the PSC did not err by construing MCL 460.6s(1) so as to conclude that the proposed LCM project is a "significant investment in an existing electric generation facility" and that it qualified as "a group of investments reasonably planned to be made over a multiple year period not
MCL 460.6s(1) provides:
Whether the investment at issue qualifies as a "significant investment" within the meaning of the statute depends on how the statute is construed.
ABATE asserts that the other qualifying projects would increase power supply and that the doctrine of ejusdem generis requires an interpretation that a "significant investment" must be one that will also increase power supply. The investment at issue here, ABATE urges, "is not for new capacity but is intended to keep old capacity running in the future." According to ABATE, such "preventative maintenance" does not fall within the scope of MCL 460.6s(1).
"Under the statutory construction doctrine known as ejusdem generis, where a general term follows a series of specific terms, the general term is interpreted `to include only things of the same kind, class, character, or nature as those specifically enumerated.'" Neal v. Wilkes, 470 Mich. 661, 669, 685 N.W.2d 648 (2004), quoting Huggett v. Dep't of Natural Resources, 464 Mich. 711, 718-719, 629 N.W.2d 915 (2001). In Huggett, 464 Mich. at 718, 629 N.W.2d 915, quoting Belanger v. Warren Consol. Sch. Dist. Bd. of Ed., 432 Mich. 575, 583, 443 N.W.2d 372 (1989), quoting 2A Sands, Sutherland Statutory Construction (4th ed.), § 47.17, p. 166, the Court stated:
The series of terms at issue is "construct an electric generation facility, make a significant investment in an existing electric generation facility, purchase an existing electric generation facility, or enter into a power purchase agreement for the purchase of electric capacity." While three possibilities in the series could increase the capacity of a plant, this shared characteristic does not transform "mak[ing] a significant investment in an existing electric generation facility" into a general term. It is specific in its own right. Moreover, it does not follow the terms that appellees would identify as "specific" so that it might be viewed as an extension of those terms. Accordingly, the ejusdem generis doctrine does not guide our construction.
"Significant investment" is expressly defined in the statute to include "a group of investments reasonably planned to be made over a multiple year period not to exceed 6 years for a singular purpose such as increasing the capacity of an existing electric generation plant." Appellants argue, in essence, that "singular" should be construed to mean unique or extraordinary. Black's Law Dictionary (10th ed.), defines "singular," when used as an adjective, as "[i]ndividual; each." In The American Heritage Dictionary, Second College Edition (1991), "singular" is defined, when used as an adjective, as "[b]eing only one; individual" or alternatively as "[d]eviating strongly from a norm; rare." The two lead definitions in Webster's New Twentieth Century Dictionary Unabridged (1979), are "individual; separate or of or having to do with an individual or peculiar to one; private" and "remarkable; eminent; extraordinary." The dictionaries suggest that "singular" is generally thought to mean "individual," "one," or "extraordinary." Since the term is subject to two interpretations, it is ambiguous and judicial construction is required to effectuate legislative intent. We note the juxtaposition of "group of investments" with "singular purpose." This context indicates that the Legislature's intent was to include a qualifying group of investments that had a common purpose, but not to require an extraordinary purpose.
Appellants note that the phrase "such as increasing the capacity of an existing electric generation plant" describes "singular purpose," and argue that the singular purpose therefore must be to increase capacity. However, had the Legislature intended that result, it would have said that a significant investment would include "a group of investments ... for the singular purpose of increasing the capacity of an existing electric generation plant." The phrase "such as" connotes that "increasing the capacity of an existing electric generation plant" was meant to be an example of a singular purpose, not the only singular purpose that would qualify.
Appellants indicate that the 117 subprojects at issue in essence involve replacing old equipment and qualify as legally insignificant capital expenditures. However, it appears that the project more closely amounts to a full-scale renovation of the Cook Nuclear Power Plant. The PSC found that it was "for the singular purpose of assuring that safe and reliable power
As part of a 2010 feasibility study to define work associated with a power uprate, Indiana Michigan solicited an evaluation of "the existing plant systems and components in regard to Life Cycle Management considering the recent operating license extension." The power uprate was abandoned but the study was used in designing the LCM project. In the interest of cost efficiency, some LCM components were sized for uprated capacity to accommodate future demand. Specifically, the testimony indicated that "costs associated with upsizing are included in 7 of the 117 LCM sub-projects. By including the cost of upsizing in the LCM Project, we will avoid having to replace this equipment at a large expense should our customers require the power uprate." Evidence demonstrated that an eighth project involved the Unit 2 low-pressure and high-pressure steam turbines, which needed extensive repairs due to erosion and were nearing the end of their service lives. The testimony supported that the turbines in place were no longer commercially available and would be replaced with a technologically improved turbine that would incidentally add capacity. Further testimony supported the prudence of proactively replacing aging and obsolete equipment before failure or unreliability, which would serve to avert unscheduled downtime and the need for expedited repairs and replacement, and would allow the safety of the units to be maintained at their current levels. Moreover, there was testimony that the projects were "necessary to allow the Cook Plant to safely and reliably reach the end of the extended operating licenses."
The PSC determined that these subprojects should be covered as part of the CON. It found it reasonable to replace the Unit 2 turbine "as part of the LCM rather than wait for a catastrophic failure that could result in an extended and costly outage." Also, the PSC "agree[d] ... that the modest incremental cost associated with upsizing certain components is justified in light of the possibility that the plant may be uprated in the not-too-distant future. The Commission also agrees that the other contested subprojects meet the LCM screening criteria."
MCL 460.6s(4) provides, in pertinent part:
Although some costs involved in the LCM indirectly relate to potential future uprates, we find no statutory barrier to their PSC approval. MCL 460.6s(4)(a) requires a determination regarding whether there is a "need for the power that would be supplied by the existing or proposed electric generation facility...." The statutory language does not require a separate finding of need for each individual outlay forming the group of investments that comprises a "significant investment" in an existing facility under MCL 460.6s(1). If the need for power is established, the facility must be "the most reasonable and prudent means of meeting the power need" under MCL 460.6s(4)(d). MCL 460.6s(4)(c) requires an additional determination that the "estimated cost of power from the existing or proposed electric generation facility ... is reasonable...." If an investment or part of an investment was not needed to accomplish the singular purpose for which a significant investment was being made, it and its cost would arguably fail the "reasonable and prudent" test.
Here, the evidence established that the LCM project and 117 subprojects would allow for continued operation of the facility for the duration of the extended licenses; the facility would continue to serve the need already being served. Thus, the need for the power supplied by the facility was established. The evidence also established that the turbine was both an uprate and an LCM project, that the seven other subprojects would be of a quality that would allow for future uprates, and that there was an incremental cost, at least for some of the seven, for this allowance. However, the evidence clearly supported that the turbine was needed. That it increased capacity was incidental; it was being replaced because of need rather than a current desire to uprate capacity. Moreover, because there was a current need for the seven subprojects, whether current need existed for each aspect of the subprojects did not have to be determined under MCL 460.6s(4). Rather, Subsection (4) merely required that the costs be reasonable and prudent. Given testimony that the components being replaced needed replacement currently and would have to be replaced again at a much higher cost if there was an uprate, it cannot be said that the PSC acted unlawfully or unreasonably by determining that the current expense for replacements with features that would accommodate an uprate was both reasonable and prudent. Although there was a risk involved that the uprates might never occur, substantial evidence supported the determination that, on balance, the current expenditure was warranted.
Indiana Michigan offered testimony establishing that individual cost estimates were calculated for each subproject and the estimates included individual risk reserves. However, Indiana Michigan claimed that while there was a high level of confidence in the cost estimating, it was "unrealistic to assume that all anomalies have been both recognized and accounted
In contrast, Indiana Michigan explained that management reserve
Indiana Michigan claimed that the amount it was requesting for management reserve was
The PSC staff originally opposed the management reserve, maintaining that the costs were purely speculative and that risk reserve of 15% to 25% had already been built into the subprojects. The staff believed that
Indiana Michigan responded by claiming that 32 subprojects specified in a certain report had a cost and a contingency, but that to develop the cost for the LCM project, "we removed all the contingency" "so we had a raw cost" "and then we added the indirect costs[, a straight 10%,] and those were the individual sub-project costs."
Indiana Michigan maintained that if "management reserve margins are not included in the approved cost estimate as typically done, then the total cost estimate will be understated and not reflect the foreseeable cost of the project."
The administrative law judge recommended that the management reserve be denied, concluding, in pertinent part, that Indiana Michigan had not met its burden of proof:
The PSC concluded that Indiana Michigan had "failed to carry its burden of proof to show that its proposed management reserve, over and above what appears to be a risk reserve added to at least some projects, is reasonable. The portion of the record in this case dedicated to [Indiana Michigan's] testimony is rife with contradictions and late attempts to correct misstatements made in the course of the proceeding." The PSC therefore removed the proposed management reserve from the costs approved but, professing to understand
Preliminarily, MCL 460.6s does not expressly address whether a management reserve can be included as an approved cost. Regarding approval of costs, the statute simply says:
MCL 460.6s(9) then provides:
Thus, Subsection (9) provides that approved costs can be recovered in rates when a facility becomes used and useful. If the costs are not preapproved but are nonetheless incurred, Subsection (9) provides that they may be recovered if reasonable and prudent. Thus, the question is not whether the utility will be able to recover the costs, but whether they will be preapproved.
Appellants argue that the provision in Subsection (9) for recovery of actual costs implies that a management reserve was not contemplated as part of the costs pre-approved with issuance of a CON. However, nothing in Subsection (6) or Subsection (9) would preclude pre-approval of a management reserve cost. If testimony established that a management reserve was a legitimate cost associated with a qualifying project, Subsection (6) would merely require that it be specified. Subsection (9) provides that all reasonable and prudent costs for a facility covered by a CON be
Here, ample testimony supported the inclusion of a cost for contingencies in the estimated costs of the LCM Project. However, the testimony was confusing regarding whether contingencies were covered in part by risk reserve built into the individual subprojects. Indiana Michigan first presented testimony indicating that some contingencies were covered by risk reserve and then presented undocumented testimony indicating that all contingencies had been stripped out of at least some subprojects. Given the questions that remained regarding management reserve, the PSC did not err when it found that Indiana Michigan did not establish that management reserve was a reasonable cost by substantial evidence on the whole record.
Indiana Michigan had proposed a management reserve of 20% of estimated costs. There was no evidence explaining the origin of this figure or its reasonableness. Thus, even if Indiana Michigan had established that a management reserve was a reasonable cost generally, it failed to establish that the amount of the cost was reasonable. Coextensively, there was no factual basis for the PSC's determination that 10% of estimated costs represented a reasonable management reserve. Citing Consumers Power Co. v. Pub. Serv. Comm., 189 Mich.App. 151, 187, 472 N.W.2d 77 (1991), it is suggested by appellees that the PSC's provision for 10% as a management reserve was within a range of values presented and was therefore supported by substantial evidence. However, the PSC expressly found that the reasonableness of a 20% management reserve was not supported by the record.
The Attorney General argues that the PSC did not specify the costs it allowed
The Attorney General asserts that a remand is necessary for such specification. Further, the Attorney General insists that this issue was preserved by several citations to MCL 460.6s(6) in exceptions to the proposal for decision. The Attorney General mentioned that MCL 460.6s(6) requires the specification of costs in the context of its argument that the PSC had to approve or reject, but could not amend or modify, Indiana Michigan's application for a CON, an argument that the Attorney General has not pursued on appeal. Moreover, the Attorney General noted that MCL 460.6s(6) relates to the nature and reasonableness of costs, and discussed this provision in the context of discussing whether contingent costs can be approved as a specific cost. The Attorney General never challenged the failure to specify costs allowed and disallowed. "Failure to file exceptions to a proposal for decision in a timely manner constitutes a waiver of the objection." Attorney General v. Pub. Serv. Comm., 174 Mich.App. 161, 164, 435 N.W.2d 752 (1988). This issue is not preserved.
The record indicates that the costs for each subproject were broken down and that these were the costs approved by the PSC. However, it is not clear from the record on appeal to what extent costs were itemized. The statute speaks of "costs approved" but does not indicate the level of specificity required. (Emphasis added.) It could mean the total cost of each composite project or require itemization of each project. If itemization is called for, what degree of itemization should be required? With a project of this complexity, itemization down to nuts and bolts would presumably be too cumbersome to be useful. Had the Attorney General argued below that the statute contemplated more specificity, the pros and cons of more specificity and the degree of appropriate specificity would have been developed and addressed by the PSC. Moreover, in considering this question it would be helpful to understand how the PSC will assess cost overruns so that it can be determined what is an overrun and what was a pre-approved cost. Since we have neither this information nor the benefit of the PSC's determination regarding this issue, we decline to consider it.
We affirm in part and reverse in part.
FITZGERALD, P.J., and GLEICHER and RONAYNE KRAUSE, JJ., concurred.