ANN D. MONTGOMERY, District Judge.
This matter is before the undersigned United States District Judge for a ruling on Plaintiff Unison Co., Ltd.'s ("Unison") Motion to Modify and Correct the Arbitration Award [Docket No. 181], Defendants Juhl Energy Development, Inc., Juhl Energy, Inc., Winona Wind Holdings, LLC, Winona County Wind, LLC, Daniel Juhl, John Mitola, John Brand, Bartly J. Loethen, Audrey Loethen, and Jeff Bendel's (collectively, "Defendants") Motion to Confirm Arbitration Award and Dismiss Plaintiff's Amended Complaint with Prejudice [Docket No. 211], and Defendants' Motion for Attorneys' Fees and Costs [Docket No. 214]. For the reasons set forth below, Unison's Motion is denied, Defendants' Motion to Confirm Arbitration Award and Dismiss Plaintiff's Amended Complaint with Prejudice is granted, and Defendants' Motion for Attorneys' Fees and Costs is denied.
Juhl Energy Development, Inc. ("JEDI") and Unison are parties to contractual agreements related to the design, manufacture, and sale of Wind Turbine Generators ("WTG") that were to be installed at a community wind farm project in Winona County, Minnesota. Am. Compl. [Docket No. 14] ¶¶ 1, 18-22. In its December 17, 2013 Amended Complaint, Unison alleged 16 claims which largely arose from an April 14, 2010 Financing Agreement.
On May 26, 2015, the Eighth Circuit ordered that Unison's claims be arbitrated.
Both Unison and JEDI submitted claims and defenses in arbitration. Unison claimed that JEDI fraudulently changed its ownership structure without Unison's consent. Berner Aff. [Docket No. 194] Ex. S ("Final Award") at 5. JEDI claimed that it was defrauded because the WTGs Unison sold lacked an essential cold weather package for the production of wind power in Minnesota.
On March 26, 2018, the arbitrators (the "Panel") issued a Final Award.
Unison was responsible for dismantling the WTGs.
On March 27, 2018, Defendants moved to Confirm the Arbitration Award and Dismiss Plaintiffs' Amended Complaint [Docket No. 130], and on May 7, 2018, Defendants moved for Attorneys' Fees and Costs [Docket No. 148]. The Motions were denied as premature since Unison had declared its intention to challenge the arbitration award under § 12 of the Federal Arbitration Act ("FAA"), which provides that any party may move to vacate, modify, or correct an arbitration award within 90 days of the initial arbitration award.
On June 22, 2018, Unison filed its Motion to Modify and Correct the Arbitration Award [Docket No. 181]. Unison raises two arguments in support of its Motion. First, Unison contends that the Final Award should be modified because it disproportionally places the financial burden on Unison, which is contrary to the Panel's equitable decision in rescinding the contracts. Second, Unison asserts that the Final Award should be vacated because the Panel exceeded its power by granting an award outside the scope of the parties' contractual agreements.
On June 28, 2018, Defendants filed its Response [Docket No. 192] to Unison's Motion. Defendants argue that Unison's Motion should be denied because it failed to first seek the same relief from the Panel. Defendants also argue that Unison arguments in support of modifying or vacating the Final Award lack merit.
On July 2, 2018, Defendants renewed their Motions to Confirm the Arbitration Award and for Attorneys' Fees and Costs.
Unison argues that the Final Award should either be vacated under § 10 or modified under § 11 of the FAA. Defendants respond that a party seeking to vacate, modify, or correct an arbitration award must first seek such relief from the arbitrators before filing a motion in district court. Since Unison failed to do so, Defendants contend that Unison's arguments challenging the Final Award have been waived. Defendants also challenge Unison's arguments on the merits, asserting that none of Unison's contentions constitute cognizable grounds for vacating or modifying the Final Award.
The FAA provides for judicial review to confirm, vacate, or modify arbitration awards.
9 U.S.C. § 11.
"When reviewing an arbitral award, courts accord an extraordinary level of deference to the underlying award itself."
Defendants allege that a party seeking to vacate or modify an arbitration award must first seek relief from the arbitrators before filing a motion in district court. However, the authority cited by Defendants does not directly support this contention. Rather, the cited authority states that "a party cannot refuse to participate in arbitration or fail in arbitration to raise a particular argument concerning the merits of the grievance and later seek judicial resolution of that same issue."
In its Final Award, the Panel determined that Unison and Defendants were mutually mistaken on the suitability of the WTGs for the proposed wind project. As a result, the Panel "concluded that the most appropriate and equitable remedy for both parties is rescission of all of the contracts between the parties." Final Award at 6. The Final Award, Unison argues, does not reflect the Panel's intent of equitable relief because it awarded JEDI construction, installation, freight, and decommissioning costs at the sole expense of Unison. Thus, Unison contends that the Final Award leaves it in a more detrimental position than it was prior to the rescinded contracts. This result is contrary to the Final Award's expressed intent to place the parties in the positions they were before the contracts were executed. Unison's challenge is aimed at how the Panel elected to most closely restore the parties to the "position they would have been had the contract[s] never existed."
The Court declines to modify the manner in which the Panel elected to restore the parties to their pre-contract positions. Rescission requires that a party be placed "as nearly as possible in his situation before the contract."
Unison next makes two arguments that the Final Award should be vacated under §10 of the FAA because the Panel exceeded its authority. First, Unison asserts that the Panel's Final Award of $792,720 exceeds the contracts' limitation of liability provisions, which caps damages at 10% of the $2.57 million purchase price, or $257,000. Second, Unison contends that the Panel acted beyond its authority by ordering rescission, which is not one of the sole and exclusive remedies set forth in the contracts and was not a type of relief requested by any party.
Unison argues that the Final Award must be vacated because the amount of money Unison was ordered to pay Defendants exceeds the limitation of liability provisions found in the contracts. Article 9.2 of the Turbine Supply Agreement ("TSA") provides
Choi Decl. [Docket No. 184] Ex. B at Art. 9.2.
There are two main flaws with Unison's argument. First, unlike Unison's other arguments, this could have been presented to the arbitrators. In its arbitration brief, Defendants claimed they were "entitled to recover all of their damages approximating $6,000,000.00 including attorneys' fees and costs incurred as a result of Unison's fraud." Berner Aff. Ex. N. This is an argument concerning the merits of the grievance that Unison cannot raise for the first time in district court.
Second, since the contracts were rescinded, the limitation of liability provision does not restrict how the parties are to be restored to their pre-contract positions. "Rescission is the unmaking of a contract, which not only terminates the contract but abrogates it and undoes it from the beginning."
Since the effect of rescission is the complete undoing of the contracts, in restoring the parties to their pre-contract positions, the Panel's determination on how to accomplish that result is not constrained by any contractual provision.
Unison also asserts that the Final Award should be vacated because the Panel exceeded its authority. Unison appears to make two arguments in support of this assertion. The first argument is based upon similar provisions found in the contracts at issue. For example, Article 18.18 of the TSA provides
Choi Decl Ex. B. The thrust of this argument is that since rescission is not listed as a remedy in the TSA, the Panel's decision to rescind the contracts conflicts with the contractual language and must therefore be set aside.
This raises an issue of contract interpretation; whether the arbitrators exercised their authority according to or in violation of the contracts subject to arbitration. "Contract interpretation is left to the arbitrator."
The parties' Warranty, Maintenance & Service Agreement ("WMSA") arguably grants the Panel contractual authority to rescind the contracts. The WMSA provides that in the event one party breaches any representation or warranty it made, the other party shall, in addition to terminating the agreement, "have all other rights and remedies to which it is entitled at law or in equity." Choi Decl. Ex. C at Art. 20.1. Defendants accused Unison of fraud, essentially arguing that Unison made warranties concerning the WTGs that Unison knew the WTGs could not meet.
Unison's second argument more broadly contends that the Panel exceeded its authority by deciding the case with a remedy not requested by the parties. Contrary to Unison's assertion, in its initial position paper submitted to the Panel, Defendants claimed that "the principal remedy sought by JEDI and [Defendant Winona County Wind, LLC] in this arbitration is to rescind the TSA and WMSA as well as the parties' ancillary agreements relative to financing this transaction." Berner Aff. Ex. T [Docket No. 209] at 9. Moreover, as recognized in the Final Award, arbitrators have the power and the authority to grant equitable relief even if it is not sought by the parties. The arbitration clause in the parties' agreements are broad in scope. The WMSA, for example, authorizes arbitrators to decide "All claims, disputes or other controversies arising out of, or relating to, [the WMSA]." Choi Decl. Ex. C at Art. 21.1, 21.2. Similarly, the TSA authorizes the arbitrators to resolve "any dispute." Choi Decl Ex. B at Art. 16.1, 16.2. Such a broad grant of authority is sufficient to affirm the authority of the Panel.
Unison's challenges to the Final Award under §§ 10 and 11 of the FAA are denied. Accordingly, Defendants' Motion to Confirm the Arbitration Award is granted.
Defendants request an award of attorneys' fees and costs totaling over $2 million. Defendants first sought their attorneys' fees and costs in arbitration, but the Panel denied the request. Defendants now renew their request here, arguing that since they were the prevailing party in the arbitration, they are entitled to an award of attorneys' fees and costs.
Defendants' Motion is denied for two reasons. First, it is unclear Defendants are the prevailing parties. The Minnesota Supreme Court has explained that the "prevailing party in any action is one in whose favor the decision or verdict is rendered and judgment entered."
Second, this case has only been minimally litigated in district court. The vast majority of the hours incurred in litigating this matter have been spent in arbitration. The Panel's refusal to award Defendants' its attorneys' fees is credible evidence that an award of attorneys' fees is unwarranted. This conclusion is underscored by the methodology for awarding attorneys' fees—the lodestar, "which is the product of a reasonable hourly rate and the number of hours reasonably expended on the matter."
Based upon the foregoing, and all the files, records, and proceedings herein,