JEAN C. HAMILTON, District Judge.
This matter is before the Court on Defendants' Motion to Compel Arbitration and to Dismiss or Stay Proceedings, filed August 20, 2019. (ECF No. 8). The motion is fully briefed and ready for disposition.
On June 21, 2019, Plaintiff Jalliah Jaber filed her Complaint in this matter against Defendants GC Services Limited Partnership ("GC Services"), Barry Brashear, John Kokenge, and Trenda Thompson. (ECF No. 1). Plaintiff asserts claims pursuant to Title VII of the Civil Rights Act of 1964, 42 U.S.C. § 2000e et seq., the Missouri Human Rights Act, Mo. Rev. Stat. § 213.010 et seq., and 42 U.S.C. § 1981. (Id.).
On August 20, 2019, Defendants filed the instant Motion to Compel Arbitration and to Dismiss or Stay Proceedings. (ECF No. 8). In support of their motion, Defendants assert that Plaintiff executed a valid and enforceable Mutual Agreement for Dispute Resolution, containing the following relevant provisions:
(ECF No. 9-1, PP. 3-4).
Relying on the terms of the Agreement, Defendants maintain this Court must enforce its provisions as written and compel Plaintiff to pursue her claims through arbitration. (ECF Nos. 8, 9). Specifically, Defendants assert (1) that the Court must allow an arbitrator to determine whether the Agreement is valid and enforceable, and (2) that even if the Court declines to allow the arbitrator to determine if the Agreement is valid and enforceable, it should find a valid and enforceable agreement to arbitrate exists. (Id.). In response, Plaintiff asserts (1) that her signature on the Agreement was forged, thereby rendering the document fraudulent and unenforceable, and (2) even assuming Plaintiff did sign the Agreement, it is unenforceable due to a lack of consideration. (ECF No. 14).
As noted above, in her response to Defendants' motion Plaintiff first asserts the Agreement is unenforceable, because her signature thereon was forged. The Court held an evidentiary hearing on Plaintiff's claim on February 3, 2020.
Mr. Pryor testified that during the "onboarding" session, new employees were presented with approximately fifty pages to read and sign. He testified that for a class of about twenty people, it would take roughly one hour to obtain the required signatures. He further explained that it was not feasible for him personally to observe each employee sign his or her documents, and therefore he had no specific memory of Plaintiff signing her documents. He testified that while employees occasionally refused to sign certain documents
Defendants then called Plaintiff to the stand. She scrutinized each document presented to her, eventually agreeing that she signed some, and denying others.
Upon consideration of the parties' submissions, together with the evidence presented at the hearing, the Court now finds Plaintiff's signature was not forged on the Agreement, for two reasons. First, the Court's comparison of the signature on the Agreement with other signatures that Plaintiff admits to executing reveals a vast similarity, sufficient to convince the Court that Plaintiff in fact signed the Agreement at issue. See Greater Kansas City Laborers Pension Fund v. Thummel, 738 F.2d 926, 928 (8th Cir. 1984) (citations omitted) ("[G]enerally the trier of fact may compare a contested sample of handwriting with an authenticated sample and decide that the contested sample is authentic even in the absence of expert testimony."); Stine Seed Co. v. A&W Agribusiness, LLC, 862 F.3d 1094, 1099 (8th Cir. 2017) (same). Second, the Court finds Mr. Pryor's testimony at the hearing was credible, while Plaintiff's testimony was wholly incredible. Under these circumstances, the Court finds Plaintiff's claim that her signature on the Agreement was forged fails, and thus cannot serve to defeat Defendants' Motion to Compel Arbitration.
Plaintiff next asserts that even assuming she signed the Agreement, it is unenforceable due to a lack of consideration. Section 2 of the Federal Arbitration Act (FAA), 9 U.S.C. §§ 1-16, states that an agreement to arbitrate "shall be valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract." 9 U.S.C. § 2. This provision reflects the strong federal policy favoring arbitration. AT & T Mobility LLC v. Concepcion, 563 U.S. 333, 339 (2011). Because "arbitration is a matter of contract, .... courts must rigorously enforce arbitration agreements according to their terms." American Exp. Co. v. Italian Colors Rest., 570 U.S. 228, 233 (2013) (internal quotations and citations omitted). Any doubts concerning the scope of arbitrable issues should be resolved in favor of arbitration. Moses H. Cone Mem'l Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 24-25 (1983).
"[W]hen deciding whether to compel arbitration, a court asks whether a valid agreement to arbitrate exists, and if so, whether the dispute falls within the scope of that agreement." Newspaper Guild of St. Louis, Local 36047 v. St. Louis Post Dispatch, LLC, 641 F.3d 263, 266 (8th Cir. 2011) (citation omitted). "A court must grant a motion to compel arbitration if a valid arbitration clause exists which encompasses the dispute between the parties." 3M Co. v. Amtex Security, Inc., 542 F.3d 1193, 1198 (8th Cir. 2008) (citations omitted). Plaintiff does not dispute that her claims fall within the ambit of the Agreement. Rather, Plaintiff maintains the arbitration agreement itself is unenforceable because it lacks bargained-for consideration.
As noted above, the parties agreed to abide by the JAMS Employment Arbitration Rules & Procedures. Rule 11(b) states in relevant part as follows: "Jurisdictional and arbitrability disputes, including disputes over the formation, existence, validity, interpretation or scope of the agreement under which Arbitration is sought, .... shall be submitted to and ruled on by the Arbitrator. Unless the relevant law requires otherwise, the Arbitrator has the authority to determine jurisdiction and arbitrability issues as a preliminary matter."
Parties are free to agree to arbitrate threshold or "gateway" questions of arbitrability. Rent-A-Center, West, Inc. v. Jackson, 561 U.S. 63, 68-69 (2010) (noting that this "reflects the principle that arbitration is a matter of contract"). By incorporating the JAMS Rules, the parties agreed to allow the arbitrator to determine threshold questions of arbitrability. See Frazier v. GC Services Limited Partnership, No. 19CV2330 RWS, 2019 WL 6016338, at *2-3 (E.D. Mo. Nov. 14, 2019). "When an arbitration clause contains a clear and unmistakable agreement to arbitrate issues of arbitrability, as here, issues of the clause's enforceability will be for the arbitrator to decide unless the provision delegating such authority to the arbitrator is specifically challenged." Hubbard v. Career Educ. Corp., No. 4:11CV995 CDP, 2011 WL 5976070, at *2 (E.D. Mo. Nov. 30, 2011) (citing Rent-A-Center, 130 S.Ct. at 2779) (addressing arbitration agreement that incorporated the Commercial Arbitration Rules of the American Arbitration Association); accord Frazier, 2019 WL 6016338, at *1 (internal quotations and citation omitted) ("A delegation provision is an additional, severable agreement to arbitrate threshold issues that is valid and enforceable unless a specific challenge is levied against the delegation provision.").
Plaintiff here does not challenge the provision of the Agreement that delegates the authority to resolve issues of arbitrability to the arbitrator. See Wallace v. Communications Unlimited, Inc., No. 4:18CV503 JAR, 2019 WL 1001701, at *5 (E.D. Mo. Mar. 1, 2019) ("As in Rent-A-Center, Plaintiffs do not directly challenge the enforceability of the delegation provision, only the validity.... of the contract as a whole.... Assertions that the contract lacked adequate.... consideration.... are clearly challenges to the validity and enforceability of the contract as a whole."). Thus, it is for the arbitrator to determine the validity of the arbitration agreement as a whole. See Rent-A-Center, 561 U.S. at 72 ("Accordingly, unless [employee] challenged the delegation provision specifically, we must treat it as valid under § 2 [of the FAA], and must enforce it under §§ 3 and 4, leaving any challenge to the validity of the Agreement as a whole for the Arbitrator."). Accord Driver v. BPV Market Place Investors, L.L.C., No. 4:17CV1607 CAS, 2018 WL 3363795, at *6 (E.D. Mo. Jul. 10, 2018) (citation omitted) ("Plaintiff argues the Agreement lacks legal consideration, but this argument also goes to the validity of the Agreement as a whole, and concerns the issue of contract formation. The Agreement's delegation clause grants the arbitrator exclusive authority to resolve any dispute relating to the Agreement's applicability, enforceability, or formation. Again, because plaintiff does not argue that the delegation provision itself lacks legal consideration, the Court must treat it as valid, and leave plaintiff's formation challenge to the arbitrator"); Arment v. Dolgencorp, LLC, No. 2:18CV26 CDP, 2018 WL 5921369 at *2 (E.D. Mo. Nov. 13, 2018).
In accordance with the foregoing, Defendants' Motion to Compel Arbitration must be granted. See Wallace, 2019 WL 1001701, at *6 (quoting Jones v. Titlemax of Missouri, Inc., No. 4:15CV1361 JAR, 2016 WL 4158886, at *4 (E.D. Mo. Aug. 5, 2016)) ("The Court concludes that [Plaintiff has] not shown that the delegation provision in the Agreement is invalid. As such, `the Court's only role will be to enter an order compelling arbitration.'").
Accordingly,