The park is home to redwood trees 300 feet tall and thousands of years old, of particular importance because of the high quality of the old growth redwood trees.
As Route 101 passes through the park, it narrows to a two-lane road that curves tightly between the trees. The curves of the roadway and inadequate shoulder widths, among other things, do not meet current design standards. As a result, large vehicles traveling on this roadway find it difficult "to stay within the travel lane without using part of the opposing lane of traffic (`off-tracking') or traveling off the roadway and using the shoulders." Due to the current size and configuration of the road, industry standard-sized trucks authorized by the Surface Transportation Assistance Act of 1982 (Pub.L. No. 97-424 (Jan. 6, 1983) 96 Stat. 2097; STAA trucks) are prohibited from using this portion of Route 101.
Caltrans issued a notice of preparation for an EIR in May 2008 and released the draft EIR (DEIR) on December 4, 2008. Following a public comment period, Caltrans released and certified the final EIR and approved the project on May 18, 2010. The notice of determination approving the EIR
The EIR describes the project as involving "minor road adjustments including realignments, curve corrections, and shoulder widening" as well as "culvert improvements and repaving the roadway." As relevant to this appeal, the primary environmental impacts resulting from the project are tree removal and potential damage to the structural root zones of other trees caused by, among other things, excavation and placement of impervious material or fill over the roots.
Focusing on the "community" of redwood trees as a whole, rather than on individual trees, the EIR provides summary information regarding the project's environmental impacts. No old growth redwood trees will be removed. Only six redwood trees ranging in size from four to 19 inches in diameter will be removed. "Within the project limits, there would be construction activities that occur within the structural root zone of approximately 74 redwood trees ranging in diameter from 18 inches to 15 feet ...." With respect to impacts to old growth redwood trees caused by fill, the EIR states: "About 41 redwood trees thirty inches or greater in diameter within the park would have fill placed within the structural root zone. The maximum depth of fill on these redwoods would be three and a half feet. Of those redwood trees affected by fill, about 50 percent would have fill of six inches or less and over 70 percent would have fill of 12 inches or less." With respect to impacts to old growth redwood trees caused by excavation (or cuts), the EIR states: "It is estimated that construction excavation would occur within the structural root zone of 58 redwood trees thirty inches in diameter or greater within the park. The maximum depth of the excavation within the structural root zone of redwoods thirty inches in diameter or greater within the park is two feet. Nearly thirty percent of these redwood trees affected would experience excavation of six inches or less." With regard to placement of impervious roadway materials, the EIR states: "The proposed realignments would require locating the roadbed nearer to some trees and locating it further from other trees and removing the existing pavement. An additional 0.30 acres of impervious surface would [be] placed overall within the project limits. Of this, 0.14 acre of roadbed material would be placed within the structural root zone area of trees. This represents a nearly five percent increase in the total amount of hardened surface (roadbed) within the structural root zone area of
The EIR also describes "Avoidance, Minimization and/or Mitigation Measures" that "have been incorporated into the project to avoid and minimize impacts as well as to mitigate expected impacts." (Italics omitted.) These include, "M-l: Restorative planting of 0.56 acre of former US Route 101 roadbed alignment.... [¶] M-2: To offset the impacts to the trees where construction occurs within the structural root zone, mitigation will be provided to increase the amount of invasive plant removal. A contract with the California Conservation Corps will be established to provide 300 hours a year for four years (three days each year for a crew of twelve, the minimum crew size). Crew to be directed at the discretion of the California Department of Parks and Recreation." In addition, the following "avoidance and minimization measures" will be implemented for work in the park: "[1] An arborist shall be present to monitor any ground disturbing construction activities. [¶] [2] All excavation below the finish grade within a setback equal to three times the diameter of any redwood trees shall be done with shovels, pick axes, or pneumatic excavator or other methods approved by the construction engineer to minimize disturbance or damage to the roots with the exception of culvert work at PM 1.18, 1. 28, 1.34 and 1.35. Mechanized equipment can be used at these locations upon approval of the construction engineer. [¶] [3] The contractor will be required to use a pneumatic excavator (such as an air spade) while excavating the soil within the structural root zone of redwood trees to minimize physical injury to the tree roots. [¶] [4] Smaller roots less than 2 inches in diameter that must be cut shall be cut cleanly with sharp instrument in order to promote healing. [¶] [5] The structural section for new pavement shall consist of Cement Treated Permeable Base (CTPB) to minimize the thickness of the structural section, provide greater porosity, minimize compaction of roots, and minimize thermal exposure to roots from Hot Mix Asphalt paving. [¶] [6] After construction, the ... cut-slope area between PM 1.35 and PM 1.37 will be replanted. After tree removal, but prior to excavation of the cut-slope areas, the upper four to six inches of duff and native soil (topsoil) will be set aside for placement on finished fill slopes to provide the nutrients and a seed bank for natural revegetation. [¶] [7] To help minimize potential stress on the redwood trees during construction, watering will be provided. In areas where roadway excavation will take place below the finish grade within the structural root zone of redwoods 30 inches in diameter or larger, watering equivalent to 1/2 inch depth to an area defined as from the edge of existing pavement to 25 feet beyond the edge of pavement shall be performed. Watering to be performed not more than 24 hours after the roadway excavation work at a site and shall occur weekly thereafter between the dates of June 1st and September 30th. [¶] [8] Caltrans will
Ultimately, the EIR concludes that "[n]o significant environmental effects are expected as a result of this project with the implementation of the stated special construction techniques."
On June 17, 2010, appellants filed their petition for writ of mandate and injunctive relief. The trial court initially issued an order finding in favor of Caltrans on most issues but noting that "Caltrans may not have complied with [Public Resources Code section 21000, et seq. (California Environmental Quality Act or CEQA)] in adopting mitigation measures." The court explained, "if a project will have a significant effect, one way to comply with CEQA is to incorporate measures into the project that would `avoid or substantially lessen the significant environmental effect....' [Citations.] An agency adopting such mitigation measures, however, must also adopt a `reporting or monitoring program' that is `designed to ensure compliance during project implementation.' [Citations.] [¶] The fact of the matter is that Caltrans has adopted mitigation measures, some of which are labeled `special construction techniques.' [Citation.] More important, Caltrans's finding of no significant environmental effects is explicitly premised on mitigation measures; namely `the implementation of stated special construction techniques.' [Citation.] [¶] The Court does not believe that Caltrans violated CEQA simply by taking into account mitigation measures in making its determination that no significant effects will occur. It seems perfectly appropriate and realistic for an agency in a case like this and in many others to: (1) be uncertain as to whether a project, without mitigation, will have a `significant effect' within the meaning of CEQA (a fundamentally vague standard that this
Caltrans filed a response to the order to show cause on August 11. Although much of the submission was ruled inadmissible, the court ultimately concluded, based on evidence contained in the administrative record, that Caltrans had adopted a sufficient mitigation monitoring program. Among other things, the court relied on the environmental commitments record for the proposed project, which is a tool used by Caltrans "to track the project specific environmental commitments for a given project," as well as Caltrans's assurances in response to comments on the draft EIR that "[t]he minimization measures would be incorporated into the contract plans and specifications." Accordingly, the trial court issued an order denying the petition for writ of mandate and this appeal timely followed.
"In a mandate proceeding to review an agency's decision for compliance with CEQA, we review the administrative record to determine whether the agency abused its discretion. [Citation.] `Abuse of discretion is shown if (1) the agency has not proceeded in a manner required by law, or (2) the determination is not supported by substantial evidence.' [Citation.] `When the informational requirements of CEQA are not complied with, an agency has failed to proceed in "a manner required by law" and has therefore abused its discretion.' [Citation.] Furthermore, `when an agency fails to proceed as required by CEQA, harmless error analysis is inapplicable. The failure to comply with the law subverts the purposes of CEQA if it omits material necessary to informed decisionmaking and informed public participation. Case law is clear that, in such cases, the error is prejudicial.' [Citation.] [¶] `In reviewing an agency's decision to certify an EIR, we presume the
1., 2
As quoted extensively above, the EIR in this case contains information regarding the overall impacts on the community of redwood trees. Though somewhat less clearly presented, the EIR also contains information about project activity that will take place within the root zones of specific old growth redwood trees. For example, table 10 shows the cut and fill depths for each old growth redwood tree in the project area. With this data, it is possible to identify the trees that will be subject to the most cut or fill work and plot them on a map to determine the location of the tree in relation to the proposed roadway modifications. It is also possible using the data available in the EIR (table 8) to calculate the square footage of the root zones and determine what percentage of the root zone will be impacted by the cut and fill work. The EIR also indicates the changes that will result in the impermeable area covering the root zones of some of the old growth redwood trees, both in terms of the number of square feet and as a percentage of the total square footage of the root zone. The EIR does not, however, include any information that enables the reader to evaluate the significance of these impacts.
Appellants suggest that the proper measure of significance is found in the State Parks Natural Resources Handbook (handbook), which includes information for safeguarding protected trees when planning for construction. According to the handbook, "Construction activities in close proximity to trees can wound or destroy tree roots, the closer the activity to the tree trunk, the higher the probability that the tree will suffer injury. This includes soil disturbance from 0 to 3 foot depth including trenching, grade changes, storage of vehicles and materials, or compaction caused by machinery traversing the zone.... [¶] ... [¶] There should be no construction activities in the Structural Root Zone of a protected tree. This includes soil disturbance from 0 to 3 foot depth including trenching, grade changes, storage of vehicles
Caltrans implicitly acknowledges the value of the handbook in its appellate brief, citing it for the statement that "even the most low vigor trees can lose 10% of the roots from their `root health zones' [fn. omitted] without a significant loss in health. [Fn. omitted.]" The EIR itself, however, does not reference the handbook or apply the standards it prescribes to evaluate impacts to the old growth redwoods that may be expected to result from the highway construction. In fact, the EIR fails to identify any standard of significance, much less to apply one to an analysis of predictable impacts from the project.
The two expert opinions cited in the EIR, both of which conclude that the project will have no significant impact on the root health of the redwoods, suffer from the same deficiency. Both fail to discuss the significance of the environmental impacts apart from the proposed "avoidance, minimization and/or mitigation measures" and thus fail to consider whether other possible mitigation measures would be more effective.
This structural deficiency in the EIR was brought to the attention of Caltrans but was disregarded. A letter from California's Department of Parks and Recreation commenting on the draft EIR advised Caltrans, "After careful review, the North Coast Redwoods District has identified several inconsistencies in the DEIR and there is a general lack of data or information that is necessary for our staff to make qualified determinations as to the impact to the State Park resources, and the viability of the mitigation measures that are presented.... Several sections of the DEIR are not consistent with CEQA for which we believe additional analysis or mitigation measures need to be developed. The document also contains numerous mitigation measures that are not enforceable and are therefore not compliant with CEQA. [¶] Because of the apparent inconsistencies, lack of clear mitigation methods and a lack of sufficient data to evaluate the proposed project, we are not able to make a determination on some critical aspects of the project's impact to the State Park. We are concerned that the document does not meet its requirement to be an enforceable environmental tool." The letter specifically warns, "[T]he DEIR states that the proposed action will not result in any significant adverse effects to the environment and that no mitigation measures are proposed. These statements conflict with many of the Environmental Consequences sections of this document.... The DEIR also contains mitigation measures which are not acknowledged in this section but are described in Appendix D. These measures need to be listed in this section and the CEQA checklist needs to be corrected to indicate that significant adverse effects will occur and then determine if those measures are adequately mitigated. The DEIR also contains other measures that should be listed as mitigation but which will only be done at the discretion of the contractor. These need to be measurable and enforceable and listed as mitigations." Despite Caltrans's assurance that "[t]he final document will be revised to identify the avoidance
The failure of the EIR to separately identify and analyze the significance of the impacts to the root zones of old growth redwood trees before proposing mitigation measures is not merely a harmless procedural failing. Contrary to the trial court's conclusion, this shortcutting of CEQA requirements subverts the purposes of CEQA by omitting material necessary to informed decision-making and informed public participation. It precludes both identification of potential environmental consequences arising from the project and also thoughtful analysis of the sufficiency of measures to mitigate those consequences. The deficiency cannot be considered harmless. For this reason, we must reverse the denial of the petition for a writ of mandate and remand the case for issuance of a writ directing Caltrans to set aside its certification of the final EIR pending modification of those portions of the EIR discussing impacts on old growth redwood trees and proposed mitigation measures in compliance with CEQA. (Pub. Resources Code, § 21168.9.)
Caltrans is not required to start the EIR process anew. Caltrans need only correct the deficiencies we have identified before considering recertification of the EIR. Whether the correction requires recirculation of the EIR is for Caltrans to decide in light of the standards governing recirculation of an EIR prior to certification. (Pub. Resources Code, § 21092.1; Guidelines, § 15088.5.)
The judgment is reversed and the matter is remanded to the trial court with directions to enter a new judgment, consistent with Public Resources Code section 21168.9 and this opinion, granting plaintiffs' petition for a writ of mandate. Appellants shall recover their costs on appeal.
McGuiness, P. J., and Jenkins, J., concurred.