DAVID S. DOTY, District Judge.
This matter is before the court upon the motion to dismiss by defendant Hennepin County. Based on a review of the file, record, and proceedings herein, and for the following reasons, the court denies the motion.
This contract dispute arises from the longstanding business relationship between plaintiff Covanta Hennepin Energy Resource Co., LLC and the County. Since 1989, Covanta has managed and operated the Hennepin Energy Recovery Center (HERC), which converts solid waste into electricity through combustion. Am. Compl. ¶ 9. In 2003, the County purchased the HERC and thereafter entered into an amended service agreement with Covanta, which expires on March 2, 2018 (Agreement).
To exercise its extension option, Covanta must notify the County "not later than four years prior to the expiration of the original Term, in the instance of the first extension option, and two years prior to the expiration of the original Term, in the instance of the second extension option." Agreement Art. 12.02(A). Following such notification, the Agreement requires the parties to "commence negotiations in good faith of a fair market value Service Fee
On February 28, 2014, Covanta notified the County that it was exercising its first option to extend the Agreement. Am. Compl. ¶ 23. The parties began negotiations with some excusable delays.
On September 8, 2015, the County requested proposals from third parties.
On September 15, 2016, just one week before the 30-day period expired, Covanta filed this suit alleging that the County breached the Agreement by failing to negotiate the first extension option in good faith and by soliciting alternative proposals outside the scope of the original agreement. Covanta also immediately moved for a temporary restraining order, asking the court to enjoin the County from moving forward with the GRE proposal. The court withheld ruling on the TRO motion to allow the parties additional time to reach a resolution.
Covanta submitted an alternate proposal, which the County rejected. Am. Compl. ¶¶ 55-57. The parties notified the court of the impasse, and the court then denied Covanta's TRO motion. ECF Nos. 22, 23. Covanta subsequently filed an amended complaint alleging that the County breached the Agreement by: (1) failing to negotiate the contract extension in good faith; (2) accepting GRE's terms, which create an entirely new contract rather than an extension of the Agreement; and (3) refusing to accept Covanta's better counter-proposal.
To survive a motion to dismiss for failure to state a claim, "`a complaint must contain sufficient factual matter, accepted as true, to state a claim to relief that is plausible on its face.'"
The court does not consider matters outside the pleadings under Rule 12(b)(6). Fed. R. Civ. P. 12(d). The court may, however, consider matters of public record and materials that are "necessarily embraced by the pleadings."
To establish a breach of contract claim under Minnesota law, Covanta must show formation of a contract, performance of any conditions precedent by the County, a material breach by the County, and damages.
The County argues that each of Covanta's claims fail as a matter of law based on a plain reading of the Agreement. Covanta responds that the contract is subject to interpretation, which precludes dismissal under Rule 12(b)(6). The court agrees with Covanta. As evidenced by the Agreement and related documents provided to the court, the question of whether the County breached the Agreement is a fact intensive inquiry that cannot be resolved on a motion to dismiss. The parties offer varying interpretations of the contract and the parties' obligations thereunder, and differing views on their course of conduct under the Agreement. As a result, the court must deny the motion to dismiss.
Accordingly, based on the above,