This CEQA
Appellant Citizens Against Airport Pollution (CAAP) contends that the trial court erred in denying its petition for writ of mandamus challenging City's approval of the eighth addendum. CAAP argues that the amendments to the Airport Master Plan that are addressed in the eighth addendum constitute a new project as a matter of law, and therefore an environmental impact report (EIR) addendum is barred under CEQA. Alternatively, CAAP contends that an EIR addendum cannot be used to analyze the environmental impacts of the project changes included in the amendments, since those changes are substantial and require major revisions to the EIR with respect to noise, greenhouse gas emissions, toxic air contaminants, and the burrowing owl habitat.
For reasons that we will explain, we will affirm the judgment without reaching City's claim that CAAP failed to exhaust its administrative remedies.
In 1988, City began preparation of an update to the 1980 Airport Master Plan for the San Jose international airport in order to accommodate projected growth in passenger and air cargo traffic through a planning horizon year of 2010. In 1995, City issued a notice of preparation of an EIR for the proposed Airport Master Plan update.
The final EIR (FEIR) for the updated Airport Master Plan was approved in 1997. A supplemental EIR (SEIR) was certified in 2003. From 1997 through 2010, eight EIR addenda that addressed the environmental impacts of amendments to the Airport Master Plan were approved. At issue in the present appeal is the eighth addendum.
The eighth addendum to the Airport Master Plan EIR concerns amendments that change the Airport Master Plan by shifting the planning horizon year to 2027 and modifying certain master plan projects for air cargo and general aviation facilities. One reason for the amendments is that the level of air passenger activity that was projected to be reached by the year 2017 is now projected to be reached in 2027, due to a recent decrease in the annual number of passengers. Another reason for the amendments is that the current
Due to these changes in demand forecasts, City proposed amending the Airport Master Plan with the following modifications: (1) changes in the size and location of future air cargo facilities; (2) replacement of previously planned future air cargo facilities with 44 acres of general aviation facilities, in order to accommodate the forecast that large corporate jets will comprise the majority of general aviation; and (3) modification of Taxiway H and Taxiway K by adding new segments to provide better access for corporate jets.
The eighth addendum states that the proposed modifications "will not have any significant environmental impacts not previously disclosed in the Airport Master Plan EIR, nor will there be a substantial increase in the severity of previously-identified significant environmental impacts. Therefore, no subsequent or supplement EIR is warranted or required." The City Council approved the eighth addendum in June 2010.
In July 2010 CAAP filed a petition for writ of mandamus challenging City's approval of the eighth addendum. CAAP is an unincorporated association whose members include residents and property owners in San Jose.
In its petition, CAAP argued that City violated CEQA by approving a major amendment to the Airport Master Plan without preparing a supplemental or subsequent EIR. According to CAAP, the eighth addendum failed to adequately assess or analyze the impacts of the taxiway modifications and the construction of general aviation facilities on noise, air pollution, and the burrowing owl habitat. Additionally, CAAP argued that the eighth addendum failed to comply with newly adopted rules mandating review of project impacts on greenhouse gases and climate change.
In its opening brief in support of the petition, CAAP further argued that it was not required to exhaust administrative remedies since there had been no public comment period or noticed public hearing on the eighth addendum. Alternatively, CAAP contended that it had exhausted its administrative remedies by objecting to the eighth addendum in a letter to the City Council and during an informal meeting with airport staff.
CAAP also argued that the eighth addendum violated CEQA because the proposed major amendments to the Airport Master Plan constituted a new project that required preparation of a new environmental document with a
The trial court's order denying CAAP's petition for writ of mandamus was filed on August 2, 2012. At the outset, the court rejected City's contention that CAAP had failed to exhaust its administrative remedies. Although the court recognized that exhaustion of administrative remedies is a jurisdictional prerequisite to a CEQA action, the court found that CAAP was excused because there had been no public notice that "a CEQA determination or a CEQA document would be forthcoming or was contemplated."
However, the trial court found no merit in CAAP's CEQA challenge to City's approval of the eighth addendum. Relying primarily on this court's decision in Santa Teresa Citizen Action Group v. City of San Jose (2003) 114 Cal.App.4th 689 [7 Cal.Rptr.3d 868] (Santa Teresa), the trial court found that there was substantial evidence to support City's decision that an EIR addendum, rather than a SEIR, was appropriate under CEQA because (1) the noise analysis attached to the eighth addendum showed that noise impacts from the proposed airport modifications would be less than the impacts that were disclosed in the 1997 FEIR and the 2003 SEIR; (2) the effects of greenhouse gases do not constitute new information that could not have been known at the time the 1997 FEIR was certified as complete; (3) the proposed airport modifications would not increase air pollution, since the projections showed that air cargo and general aviation traffic would be less than was originally projected, with a corresponding decrease in associated ground vehicle traffic; and (4) the biological survey attached to the eighth addendum stated that any burrowing owl habitat loss caused by the construction of the taxiway improvements could be mitigated, and therefore the severity of the previously identified impact on the burrowing owls would not be increased.
CAAP filed a timely notice of appeal from the trial court's order. We treat an order denying a petition for writ of mandamus under CEQA as an appealable final judgment. (Concerned Citizens of South Central L.A. v. Los Angeles Unified School Dist. (1994) 24 Cal.App.4th 826, 831-832 [29 Cal.Rptr.2d 492].)
The issues raised by CAAP on appeal include the following: (1) the trial court erred in denying its writ petition because the amendments to the Airport Master Plan addressed in the eighth addendum constitute a new project as a matter of law, and therefore CEQA bars the use of an addendum, and (2) alternatively, the trial court erred in denying its writ petition because the amendments to the Airport Master Plan addressed in the eighth addendum constitute substantial project changes that under CEQA require major EIR revisions with respect to noise, greenhouse gas emissions, toxic air contaminants, and the burrowing owl habitat. City contends that we need not reach the issues raised by CAAP on appeal since the CEQA challenge is precluded due to CAAP's failure to exhaust its administrative remedies.
We will begin our analysis with a brief overview of CEQA, the rules that apply to an EIR addendum, and the applicable standard of review.
The first tier of the CEQA process requires an agency to conduct a preliminary review to determine whether CEQA applies to a proposed project. (Guidelines, §§ 15060, 15061; Save Our Carmel River, supra, 141
"CEQA does not require an EIR to be prepared for every step taken in the course of a project. Once a proper EIR has been prepared, no subsequent or supplemental EIR [(SEIR)] is required unless (1) `[s]ubstantial changes' are proposed in the project, requiring `major revisions' in the EIR; (2) substantial changes arise in the circumstances of the project's undertaking, requiring major revisions in the EIR; or (3) new information appears that was not known or available at the time the EIR was certified. (§ 21166; see also Guidelines, § 15162; [citation].) `[S]ection 21166 comes into play precisely because in-depth review has already occurred, the time for challenging the sufficiency of the original EIR has long since expired (§ 21167, subd. (c)), and the question is whether circumstances have changed enough to justify repeating a substantial portion of the process.' [Citation.]" (Committee for Green Foothills v. Santa Clara County Bd. of Supervisors (2010) 48 Cal.4th 32, 54-55 [105 Cal.Rptr.3d 181, 224 P.3d 920].)
In addition to a SEIR, the Guidelines provide for an addendum to an EIR. "The lead agency or a responsible agency shall prepare an addendum to a previously certified EIR if some changes or additions are necessary but none of the conditions described in Section 15162[
"In reviewing an agency's compliance with CEQA in the course of its legislative or quasi-legislative actions, the courts' inquiry `shall extend only to whether there was a prejudicial abuse of discretion.' (... § 21168.5.) Such an abuse is established `if the agency has not proceeded in a manner required by law or if the determination or decision is not supported by substantial evidence.' [Citations.]" (Vineyard, supra, 40 Cal.4th at pp. 426-427, fns. omitted.)
Thus, as this court has stated, "[t]he reviewing court upholds an agency's decision not to require an SEIR if the administrative record as a whole contains substantial evidence to support the determination that the changes in the project or its circumstances were not so substantial as to require major modifications of the EIR. [Citation.] This deferential standard is a reflection of the fact that in-depth review has already occurred. [Citation.]" (Santa
"Our role here is precisely the same as the trial court's. `"[I]n an administrative mandamus action where no limited trial de novo is authorized by law, the trial and appellate courts occupy in essence identical positions with regard to the administrative record, exercising the appellate function of determining whether the record is free from legal error. [Citations.]" [Citation.] Thus, the conclusions of the superior court, and its disposition of the issues in this case, are not conclusive on appeal. [Citation.]' [Citations.]" (Bowman v. City of Petaluma (1986) 185 Cal.App.3d 1065, 1076 [230 Cal.Rptr. 413].)
As a threshold matter, City contends that CAAP's CEQA challenge is barred because CAAP failed to exhaust its administrative remedies by objecting to City's approval of the eighth addendum during the public meetings that were held before the addendum was approved.
This court stated the exhaustion requirement in Santa Teresa: "In order to attack a decision that is subject to CEQA, the alleged grounds for noncompliance must have been presented to the public agency, and the person attacking the decision must have raised some objection during the administrative proceedings. (§ 21177, subds. (a), (b).)[
In Santa Teresa, this court determined that since the City had not either given notice that an initial study for a new water pipeline was being prepared or circulated the addendum adopting the initial study, "there was no clearly defined administrative procedure for petitioners to resolve their concerns about the project as it was finally configured, which means that the exhaustion requirement of section 21177 does not apply. [Citation.]" (Santa Teresa, supra, 114 Cal.App.4th at p. 702.) In contrast, in Mani Brothers the appellate court ruled that although no public hearing or public comment period had been provided for an addendum, the exhaustion requirement applied and was satisfied because the petitioners had repeatedly objected to the addendum at several public meetings. (Mani Brothers, supra, 153 Cal.App.4th at p. 1395.)
City relies upon the California Supreme Court's decision in Tomlinson v. County of Alameda (2012) 54 Cal.4th 281, 290 [142 Cal.Rptr.3d 539, 278 P.3d 803], in which the court ruled that "[i]f a notice of determination is filed, the public hearing provision [(§ 21177, subd. (a))] requires a party wishing to challenge the project in court to raise the party's objections to the project at a public hearing held before the notice of determination is filed." (Italics omitted.) City asserts that it filed a notice of determination for the project addressed in the eighth addendum and held several public meetings regarding the project before the addendum was approved. Additionally, City contends that CAAP merely made general comments on several environmental issues in its letter to the City Council, which did not satisfy the exhaustion requirement, or, alternatively, were insufficient to constitute exhaustion as to certain issues raised by CAAP in its writ petition.
CAAP acknowledges that in its letter to the City Council it "did not comment on the Eighth Addendum's inadequacy as to greenhouse gas emissions and toxic air contaminants." However, CAAP contends that it was not required to exhaust administrative remedies under Santa Teresa, supra, 114 Cal.App.4th 689 since there was no clearly defined administrative procedure to resolve concerns about the project addressed in the eighth addendum. CAAP also asserts that the public notice of the City Council hearing that was held before project approval did not give any notice of CEQA action.
CAAP's primary argument on appeal is that the changes proposed in the amendments to the Airport Master Plan addressed in the eighth addendum constitute a new project for which a new EIR, not an addendum, must be prepared. CAAP relies on the decision in Center for Sierra Nevada Conservation v. County of El Dorado (2012) 202 Cal.App.4th 1156 [136 Cal.Rptr.3d 351] (Center for Sierra Nevada) in arguing that as a matter of law the amendments addressed in the eighth addendum constitute a new project because the proposed changes are "not within the scope of the 1997 Airport Master Plan or its program EIR."
City rejects CAAP's characterization of the amendments addressed in the eighth addendum as a new project. According to City, "there is no `new project' but merely an adjustment to the existing plan that has already received environmental review." City also disputes CAAP's characterization of the 1997 EIR for the Airport Master Plan as a program EIR. According to City, the EIR "is a project-level document and has been used as such. Had the 1997 EIR been a program-level document, the many projects that have been constructed since that time would have undergone additional CEQA review."
The decision relied upon by CAAP, Center for Sierra Nevada, supra, 202 Cal.App.4th 1156 for the proposition that the reviewing court determines as a matter of law whether proposed changes constitute a new project for which an EIR is required, is distinguishable. That decision involved a program EIR adopted by El Dorado County in 2004 that acknowledged the impact of development on oak woodlands and wildlife, and provided that the effects would be mitigated by formulating an "integrated natural resources management plan" within five years. (Id. at pp. 1162-1163.) In 2008, the county board of supervisors adopted an oak woodland management plan that allowed developers to pay a fee for removing oak canopies, which was based on a negative declaration. (Id. at p. 1166.) The appellate court determined that the administrative record supported a fair argument that the oak woodland management plan and fee program would have "a potentially significant effect on the environment" and that the 2004 program EIR did not adequately cover the fee mitigation program. (Id. at p. 1184.) For those reasons, the court ruled that the oak woodland management plan was a specific project and the county was required to prepare a tiered EIR "to examine its specific mitigation measures and fee rate." (Id. at p. 1184.)
As we will explain, we find there is substantial evidence in the administrative record showing that the amendments to the Airport Master Plan that are addressed in the eighth addendum will not result in any new significant impacts on noise, air quality, and the burrowing owl habitat that are substantially different from those described in the 1997 EIR and the 2003 SEIR. (See Santa Teresa, supra, 114 Cal.App.4th at p. 704; Guidelines, § 15162, subd. (a)(1) & (2).) Therefore, even assuming, without deciding, that the 1997 EIR for the Airport Master Plan constitutes a program EIR, as CAAP argues, we are not persuaded that the proposed changes to the Airport Master Plan that are addressed in the eighth addendum constitute a new project that requires a new EIR.
The eighth addendum analyzed whether the changes proposed in the amendments to the Airport Master Plan would result in new or greater noise impacts than had been quantified in the 1997 EIR and the 2003 SEIR. The addendum concluded: "The proposed changes to the Airport Master Plan would not result in any new significant noise impacts and/or noise impacts
In support of this conclusion, the eighth addendum stated that the data showed that the number of average daily aircraft operations would be 20 percent less in 2027 than had been projected to occur in 2010 and 2017. Additionally, the data showed that in 2027 there would "be far fewer operations by older and noisier aircraft (e.g., Boeing 727, MD-80 series, etc.) than there will be in 2010/2017. This is a result of older aircraft gradually being phased out over time and being replaced with newer and quieter aircraft."
Using "the same methodology and thresholds as those contained in the 1997 Master Plan EIR, as updated by the 2003 Master Plan Supplemental EIR," the eighth addendum further stated that the noise levels at all of the reference point locations in the vicinity of the airport would be lower in 2027 than was projected for 2017. Also, using the community noise equivalent level (CNEL) contour, which depicts the "`noise footprint'" of the airport, the addendum stated that the area that would be exposed to aircraft noise of 65 decibels or greater in 2027 would be reduced by 28 percent from the area projected for 2017.
Relying on the decision in Berkeley Keep Jets Over the Bay Com. v. Board of Port Cmrs. (2001) 91 Cal.App.4th 1344 [111 Cal.Rptr.2d 598] (Berkeley Jets), CAAP argues that the eighth addendum failed to include any analysis of the noise impacts of single-event noise from the nighttime operation of large corporate jets, and also failed to analyze the noise impact of the support facilities for those jets. Additionally, relying on this court's decision in Lighthouse Field Beach Rescue v. City of Santa Cruz (2005) 131 Cal.App.4th 1170 [31 Cal.Rptr.3d 901] (Lighthouse), CAAP argues that the eighth addendum improperly used an "`overall'" or "`net'" approach to analyzing the noise impacts of the proposed amendments to the Airport Master Plan. CAAP therefore contends that there is not substantial evidence to support the eighth addendum's conclusion that the noise impacts of the proposed amendments to the Airport Master Plan would not be significant.
City responds that the 1997 EIR contains an extensive noise impact analysis, including the impact of aircraft maintenance and support facilities and both cumulative and single-event noise analysis; the 2003 SEIR included a noise impact analysis stating that single-event noise levels had not been recomputed since the aircraft fleet had become quieter since completion of the 1997 EIR; and the eighth addendum used the same methodology as the 1997 EIR and the 2003 SEIR in finding that noise impacts will decrease due to fewer aircraft operations and a higher percentage of new, quieter airplanes.
In Santa Teresa, this court rejected a CEQA challenge to the City's use of an addendum to the FEIR for a proposed water pipeline realignment, instead of a SEIR, because "the record contain[ed] substantial evidence supporting the conclusion that the environmental impact of the Silver Creek alignment upon the groundwater in North Coyote Valley was not substantially different from or greater than the impacts considered in the previous [environmental] studies." (Santa Teresa, supra, 114 Cal.App.4th at p. 705.) We reach a similar result in the present case.
"The CEQA Guidelines define `substantial evidence' as `enough relevant information and reasonable inferences from this information that a fair argument can be made to support a conclusion, even though other conclusions might also be reached.... Argument, speculation, unsubstantiated opinion or narrative, evidence which is clearly erroneous or inaccurate, or evidence of social or economic impacts which do not contribute to or are not caused by physical impacts on the environment does not constitute substantial evidence.' (Guidelines, § 15384, subd. (a).) Additionally, `[s]ubstantial evidence shall include facts, reasonable assumptions predicated upon facts, and expert opinion supported by facts.' (Guidelines, § 15384, subd. (b).)" (Pfeiffer v. City of Sunnyvale City Council (2011) 200 Cal.App.4th 1552, 1569 [135 Cal.Rptr.3d 380].)
We find there is substantial evidence to support the eighth addendum's conclusion that the proposed changes to the Airport Master Plan would not result in any new significant noise impacts and/or noise impacts that are substantially different from those described in the 1997 EIR and the 2003 SEIR. Appendix A to the eighth addendum includes the January 11, 2010 "analysis of changes in predicted future aircraft noise exposure that would occur upon adoption of the proposed Updated Master Plan Forecast for the year 2027 (2027 forecast) at [San Jose International Airport]," which was
The Brown-Buntin noise analysis includes tables that (1) compare the forecasts for daily aircraft operations and show a decrease in daily operations from 904.10 in 2010 to 722.70 in 2027; (2) state the 2027 forecast for annual average runway use by various types of aircraft, including corporate jets; and (3) show a decrease in the CNEL from 2010 to 2027 at the reference grid locations used in the 1997 EIR and 2003 SEIR. Thus, Brown-Buntin's analysis of the forecast changes and the data constitutes expert opinion based on facts that the noise impact from aircraft operations is decreasing, and therefore it may be reasonably assumed that the changes proposed in the amendments to the Airport Master Plan will not result in any new significant noise impacts and/or noise impacts that are substantially different from those described in the 1997 EIR and the 2003 SEIR. As we have noted, the Guidelines provide that substantial evidence includes "reasonable assumptions predicated upon facts, and expert opinion supported by facts." (Guidelines, § 15384, subd. (b).)
Moreover, the decisions in Berkeley Jets and Lighthouse, on which CAAP relies for a contrary conclusion, do not aid CAAP. Those decisions are distinguishable since neither one involved an addendum to an EIR. In Berkeley Jets, supra, 91 Cal.App.4th 1344 citizen groups challenged the adequacy of the EIR prepared for an expansion proposal for the Metropolitan Oakland International Airport. (Id. at p. 1350.) In Lighthouse, an advocacy association challenged the City of Santa Cruz's decision to adopt a negative declaration, instead of preparing an EIR, for revisions to the general plan for a state beach. (Lighthouse, supra, 131 Cal.App.4th at p. 1177.)
As we have discussed, a different standard applies where, as here, the agency has already prepared an EIR. "In the first instance, an agency must prepare an EIR `whenever it can be fairly argued on the basis of substantial evidence that the project may have significant environmental impact.' [Citation.] This test establishes a low threshold for initial preparation of an EIR, which reflects a preference for resolving doubts in favor of environmental review. [Citation.] [¶] When the public agency has already prepared an EIR ... [t]he reviewing court upholds an agency's decision not to require an SEIR if the administrative record as a whole contains substantial evidence to support the determination that the changes in the project or its circumstances were not so substantial as to require major modifications of the EIR. [Citation.]" (Santa Teresa, 114 Cal.App.4th at p. 703.) In short, "`[a]fter a project has been subjected to environmental review, the statutory presumption flips in favor of the developer and against further review.' [Citation.]" (Citizens for Responsible Equitable Environmental Development v. City of San Diego (2011) 196 Cal.App.4th 515, 532 [129 Cal.Rptr.3d 512] (CREED).)
According to CAAP, the eighth addendum violates CEQA because it failed to comply with section 15064.4, subdivision (a)
City maintains, relying on the decision in CREED, supra, 196 Cal.App.4th 515, that "[a]nalysis of greenhouse gas impacts was not required when the 1997 EIR or the 2003 Supplemental EIR were prepared, nor is a supplemental EIR required for that purpose now." We agree.
However, the potential environmental impact of greenhouse gas emissions has been known since the 1970's. "`In the late 1970's, the Federal Government began devoting serious attention to the possibility that carbon dioxide emissions associated with human activity could provoke climate change. In 1978, Congress enacted the National Climate Program Act, 92 Stat. 601, which required the President to establish a program to "assist the Nation and the world to understand and respond to natural and man-induced climate processes and their implications," [citation]....' [Citation.]" (CREED, supra, 196 Cal.App.4th at p. 531, quoting Massachusetts v. EPA (2007) 549 U.S. 497, 507-508 [167 L.Ed.2d 248, 127 S.Ct. 1438].)
Moreover, as one appellate court has noted, "`In 2002, information about the potential impacts of GHGs [(greenhouse gases)] was widely known. The United Nations Framework Convention on Climate Change was established in 1992. The regulation of greenhouse gas emissions to reduce climate change impacts was extensively debated and analyzed throughout the early 1990s. The studies and analyses of this issue resulted in the adoption of the Kyoto Protocol in 1997. In the early and mid 2000s, GHG's and climate change were extensively discussed and analyzed in California. In 2000, SB 1771 established the California Climate Action Registry for the recordation of greenhouse gas emissions to provide information about potential environmental impacts.'" (Concerned Dublin Citizens v. City of Dublin (2013) 214 Cal.App.4th 1301, 1319 [154 Cal.Rptr.3d 682] (Concerned Citizens).)
Thus, information about the potential environmental impact of greenhouse gas emissions was known or could have been known at the time the 1997 EIR and the 2003 SEIR for the Airport Master Plan were certified. We reiterate, as stated in CREED, that under section 21166, subdivision (c), "an agency may not require an SEIR unless `[n]ew information, which was not known and could not have been known at the time the [EIR] was certified as complete, becomes available.'" (CREED, supra, 196 Cal.App.4th at p. 532.)
Regarding air quality, the eighth addendum concludes that "[t]he proposed changes to the Airport Master Plan would not result in any new significant air quality impacts and/or air quality impacts that are substantially different from those described in the 1997 SJC Master Plan Update EIR." (Italics omitted.)
In support of this conclusion, the eighth addendum states: "[N]one of the proposed modifications to the approved Airport Master Plan will result in 1) an increase in activity levels at the Airport beyond that identified in the Plan, or 2) an increase in the capacity of the Airport beyond that identified in the Plan. Therefore, emissions of air pollutants, as pertains to the Airport, and as identified in the 1997 Airport Master Plan EIR, are not expected to change."
CAAP briefly argues, in reliance on the decision in Berkeley Jets, that the eighth addendum "simply states that there will be no change in air pollutants" and that the change in general aviation operations triggers the need for an updated analysis of toxic air contaminants.
City responds that the eighth addendum correctly concluded that the proposed changes to the Airport Master Plan will not result in any significant or substantially different air quality impacts, since "the 1997 EIR disclosed air pollution for higher levels of activity at the Airport than that anticipated for the horizon year 2027."
We determine that CAAP has not met its burden to show that the eighth addendum's conclusion regarding air quality is not supported by substantial evidence. (See American Canyon, supra, 145 Cal.App.4th at p. 1070.) CAAP does not dispute the evidence showing that daily aircraft operations are projected to decrease from 904.10 in 2010 to 722.70 in 2027. Thus, the record contains substantial evidence supporting the eighth addendum's conclusion that impact of the Airport Master Plan project changes upon air quality was not substantially different from or greater than the impacts considered in the previous EIR and SEIR. (See Santa Teresa, supra, 114 Cal.App.4th at p. 705.)
The eighth addendum concludes that "[t]he proposed changes to the Airport Master Plan would not result in any new significant biologic impacts and/or biologic impacts that are substantially different from those described in the 1997 SJC Master Plan Update EIR." (Italics omitted.)
In support of this conclusion, the eighth addendum states that the 2008 biological survey showed that the four acres of airfield that will be used for the proposed taxiway extensions are limited to grassland and herbaceous plants, and that trees and wetlands are absent. The eighth addendum also states that there is no suitable habitat on the airfield for any endangered species. However, the eighth addendum acknowledges that construction of the taxiway extensions will cause the permanent loss of approximately four acres of burrowing owl habitat. The burrowing owl is a "... California species of concern, ... known to nest and forage on portions of the Airport, most notably the unpaved areas of the airfield." To offset the loss of four acres of burrowing owl habitat, the eighth addendum includes a number of mitigation measures.
CAAP contends that there is no substantial evidence that the changes proposed in the amendments to the Airport Master Plan "will not be significant" and asserts that the impacts on the burrowing owl habitat "must be studied and subjected to public and agency review." Further, CAAP argues that a much more detailed burrowing owl plan was found inadequate in San Joaquin Raptor Rescue Center v. County of Merced (2007) 149 Cal.App.4th 645 [57 Cal.Rptr.3d 663] (San Joaquin Raptor). In response, City argues that the eighth addendum explains that the impact on the burrowing owl habitat will be mitigated as stated in the Burrowing Owl Management Plan set forth in the 1997 EIR.
We determine that, with regard to the burrowing owls, the record contains substantial evidence to support City's conclusion that the project changes proposed in the amendments to the Airport Master Plan were not substantial enough to require a SEIR, because the impact on the burrowing owl population is not substantially different from or greater than the impact considered in the 1997 EIR. (See Santa Teresa, supra, 114 Cal.App.4th at p. 705.)
The 1997 EIR for the Airport Master Plan concluded that implementation of the projects proposed in the Airport Master Plan update would impact the burrowing owl population by replacing 38 acres of their grassland habitat with paving or structures or by destroying nesting habitat during construction activities. The EIR further stated: "The elimination of burrowing owl habitat and the potential mortality of burrowing owls due to construction or operational causes are both direct effects to a California species of special concern."
The 1997 EIR included measures to mitigate the impact on the burrowing owl population, which were set forth in the Burrowing Owl Management Plan. Among other detailed measures, the Burrowing Owl Management Plan provided that "[a]pproximately 84 acres of infield will be designated specifically for burrowing owl management at the ends of the runways and between taxiways Y and Z. Burrowing owls that have established nests in Runway Safety Areas or construction area will be relocated to designated management areas. Burrowing owl management areas will be mowed according to the regular mowing regime throughout the Airport infields to maintain the low, open vegetation that is an important characteristic of burrowing owl habitat." The mitigation measures also include the regular monitoring of the burrowing owl population. The 1997 EIR further states: "The above feasible mitigation measures, which are incorporated into the Project as a condition of approval, will avoid or substantially lessen the significant environmental impact described above to a less-than-significant level."
The mitigation measures included in the eighth addendum additionally provide that the Airport will offset the four acres of burrowing owl habitat
The eighth addendum's mitigation measures also provide that a biologist will survey the area of the taxiway extensions before construction begins to identify the burrowing owls' burrows so that one-way doors can be installed for at least 48 hours, in order to avoid trapping owls inside a closed burrow. Additionally, the artificial burrows that will be impacted by the taxiway extensions will be installed elsewhere in the airport. The eighth addendum states: "This mitigation is part of the Burrowing Owl Management Plan and is a standard mitigation for all airfield projects."
Thus, there is substantial evidence in the record to support City's reasons for changing the mitigation measures for the impact on the burrowing owl population. (See Mani Brothers, supra, 153 Cal.App.4th at p. 1403.) Due to the construction of the taxiway extensions, City will change the location of four acres of the 84 acres originally designated as the burrowing owl management area in the 1997 EIR, prevent the owls from being trapped in the burrows, and relocate the impacted artificial burrows. The newly designated four acres will be managed under the existing Burrowing Owl Management Plan as set forth in the 1997 EIR. We may therefore reasonably assume that the mitigation measures incorporated in the eighth addendum will maintain the environmental impacts on the Airport's burrowing owl population to less a than significant level. Accordingly, the relocation of four acres of burrowing owl management area does not constitute "a substantial increase in the severity of previously identified significant effects" that would warrant a subsequent EIR. (Guidelines, § 15162, subd. (a)(1) & (2).)
The decision in San Joaquin Raptor does not aid CAAP's contrary argument because that decision did not involve review of an EIR addendum and is otherwise distinguishable. In San Joaquin Raptor, the CEQA challenge concerned the adequacy of the EIR's analysis regarding the impacts on biological resources and wildlife habitat, including burrowing owl habitat. (San Joaquin Raptor, supra, 149 Cal.App.4th at p. 668.) The appellate court determined that "[a]lthough many valid mitigation measures are described, no reason is given for deferral of the land management plan concerning the burrowing owl preserve, nor are any criteria or standards of performance set forth." (Id. at p. 671.) By contrast, in the present case there is no indication
The judgment is affirmed. Costs on appeal are awarded to respondents.
Márquez, J., and Grover, J., concurred.