PER CURIAM.
We are asked to review a decision of the Atlantic County Special Civil Part awarding judgment to plaintiff Harbor Pines Land, LLC, against defendants South Jersey Gas Company (SJ Gas) and J.F. Kiely Construction Company (J.F. Kiely) for damage they admittedly caused during the installation of a gas main. Defendants argue the judgment must be reversed as a matter of law because the trial judge applied an incorrect legal standard and because plaintiff failed to prove J.F. Kiely violated any provisions of the Underground Facilities Protection Act,
During the bench trial, plaintiff presented the testimony of one of its owners, Joseph Gurwicz, who supervised the day-to-day construction of plaintiff's development project. Defendants presented the testimony of Keith L. Kirsch, a foreman for J.F. Kiely. Each party also introduced documentary evidence in support of their position. These facts are taken from the trial evidence.
Plaintiff was constructing a residential community located in Egg Harbor Township known as the Harbor Pines Golf Club and Estates (the Development). The Development included the creation of a golf course and two residential construction phases; "phase one" consisted of 117 lots, and "phase two" consisted of 122 lots.
On March 14, 2005, plaintiff contracted with and paid defendant SJ Gas $7256 to install a gas main on the subdivided lots to be developed in phase two. SJ Gas subcontracted with defendant J.F. Kiely to perform the actual installation of the gas main and J.F. Kiely agreed to indemnify SJ Gas for claims arising from the work.
In July 2005, J.F. Kiely installed the gas lines. At that time, all other utilities, including the underground septic lines, were in place even though actual construction of the homes on the lots had not yet commenced.
The main sanitary sewer line, comprised of thirty-six inch pipe, was located in the center of the street with four inch plastic lateral sewer lines running off the main to each of the individual lots. Although predominantly underground, the lateral for each lot had a three or four foot high stanchion or "cleanout stack," protruding above the ground.
Prior to the installation, J.F. Kiely obtained "markouts" of the existing underground utilities, including the sewer lines. "Markouts" are simply symbols or marks spray-painted on the ground that show the location and characteristics of the underground utilities.
Defendants installed the gas main parallel to the sewer main, but perpendicular to the sewer laterals. Kirsch explained the crew, using a trencher, would excavate a trench approximately thirty-six inches deep and six to eight inches wide in which the main would be laid. Areas in close proximity to the markouts would be hand dug to locate the identified utility. Once the gas main was laid, the trench was backfilled.
Plaintiff did not realize problems occurred until early 2007, when an air pressure test of the sewer system failed. After further investigation, plaintiff determined the sewer lines had been intersected during the trenching process. Specifically, plaintiff found three of the plastic laterals had been intersected by the gas line. Photographs depict several broken plastic sewer lateral lines, sections of missing pipe, and the gas line running in the same plane as the areas of missing pipe, perpendicular to where the pipe had been. Consequently, dirt and debris infiltrated the sewer main, clogging the system and causing its failure.
Plaintiff hired R.E. Pierson Construction Company (Pierson) to repair the damaged laterals and clean the resultant infiltration from the sewer main at a cost of $4,560.50. Pierson completed the repairs in July and August 2007. Once the repairs were completed, plaintiff notified SJ Gas. After approximately six to eight months, SJ Gas instructed plaintiff to speak to J.F. Kiely about the damage, which subsequently denied plaintiff's request for reimbursement.
On February 22, 2011, plaintiff filed its single count Special Civil Part complaint, alleging it suffered damage resulting from defendants' non-compliance with the Act, and negligence. Principally, the complaint alleged defendants violated their obligations set forth by the Act, suggesting they failed to "call into the damage prevention system prior to engaging in any excavation[,]" failed to "report any observed damage to the underground facilities" while performing excavation and installation of the gas line, and acted negligently.
The trial judge rendered an oral opinion finding in favor of plaintiff and awarding $4560 in damages, noting Kirsch conceded J.F. Kiely caused the damage to the sewer laterals as it was the last utility to be installed, and apparently rejecting defendants' assertions that they had fully complied with all obligations under the Act. Defendants appealed.
A trial court's factual findings made following a non-jury trial are not disturbed when they are "supported by adequate, substantial and credible evidence."
To properly review defendants' assertions on appeal, we must examine provisions of the Act and regulations promulgated by the Board of Public Utilities (BPU),
The Act requires an excavator, before performing an excavation, to "notify the [One-Call System]... of his intent to engage in excavation or demolition not less than three business days and not more than [ten] business days prior to the beginning of the excavation or demolition."
Once an excavator notifies the One-Call System, the One-Call center notifies all existing underground facility operators of the pending excavation.
In the event of a problem during an excavation, the excavator "shall immediately report to the operator of an underground facility any damage to the underground facility caused by or discovered by the excavator in the course of an excavation or demolition."
Defendants assert they fully complied with the Act's requirements, contrary to the allegations in plaintiff's complaint. Specifically, defendants showed they notified the One-Call System, waited for the completion of the markouts, and excavated thereafter. Defendants argue plaintiff's complaint must be dismissed because the claim based on statutory noncompliance was not sustainable.
We agree defendants' compliance with the defined markout duties under the Act obviate the application of the prima facie evidence of negligence provision contained in
Here, not only were defendants charged with complying with the One-Call System to obtain markouts for each location where the gas line would be installed, they also were charged with compliance of the provisions of
In this regard, Kirsch testified on cross-examination, as follows:
It was clear to the crew that the sewer laterals were installed in the area where J.F. Kiely desired to trench. Nevertheless, when digging in a marked area for a sewer lateral did not successfully locate the sewer lateral, the crew kept on going with the trencher. As Kirsch explained, if "[y]ou don't hit it [two, three] f[ee]t away from that mark then, you know, you just keep on going.... You can't sit there, dig all day and look for something."
Proof of negligence requires "`(1) [a] duty of care, (2) [a] breach of [that] duty, (3) proximate cause, and (4) actual damages[.]'"
Following our review, we conclude the trial evidence sufficiently establishes each of these elements supporting a conclusion that J.F. Kiely was negligent. The J.F. Kiely crew knew the sewer laterals were installed perpendicular to the proposed path of the gas main, admittedly the sewer stanchions were visible, and the underground facilities were marked. Kirsch agreed the sewer lateral damage was caused by the gas main mechanized trenching equipment and understood the statute imposes a duty of care when using mechanized equipment within two feet of markouts. More important, a lack of due care can be found in Kirsch's description of the crew's hand digging procedure, that is, when the sewer lateral was not immediately found in the marked location, they "just keep going" because they "can't just sit there and dig all day[.]" The entirety of the evidence satisfactorily supports the trial judge's finding of negligence.
Defendants further argue the court erred by applying the res ipsa loquitur standard in order to find negligence.
Affirmed.