PER CURIAM.
Plaintiff Township of West Deptford (Township) appeals from the November 26, 2012 order of the Chancery Division granting summary judgment to defendants Fulton Bank N.A. and Fulton Bank of New Jersey (Fulton Bank), and dismissing the Township's complaint that alleged improper disbursement of bond funds relating to the construction of a municipal golf course. For the reasons that follow, we affirm.
On May 6, 1999, the Township designated approximately 600 acres of land bordering the Delaware River as an area for redevelopment that would include a proposed golf course and related facilities (hereinafter known as the "Project"). The Township requested the Gloucester County Improvement Authority (GCIA)
In 2000, the Township entered into a Project development agreement with Arret Dobson and Emory Dobson (Dobson Brothers). The agreement provided that the Dobson Brothers would "be solely responsible in all respects and . . . indemnify and hold harmless the Township for all organizational, operational and other requirements necessary to construct, market and operate the Project."
On October 10, 2001, the bond transaction took place. The GCIA issued a $9,945,000 taxable guaranteed revenue bond which was secured under the "Guaranty Agreement Between the Gloucester County Improvement Authority and Township of West Deptford" (Guaranty Agreement), whereby the Township unconditionally and irrevocably guaranteed the principal and interest payments on the bond. The Guaranty Agreement included a waiver and release of any defense the Township may have to pay the full principal and interest of the bond. According to Section 5 of the Guaranty Agreement, the "obligations of the Township . . . shall remain in full force and effect until the entire principal of and interest on the Bonds . . . have been paid in full in accordance with and as required by law." Importantly, Section 5 further provided that the "Township's obligations shall not be affected, modified or impaired upon the happening . . . of any of the following events," including
Finally, Section 7 expressly stated that,
Also on October 10, 2001, the GCIA, River Winds Country Club, LLC, Riverwinds Golf Urban Renewal, LLC,
Beginning in October 2001, the Dobson Brothers began submitting requisitions for the payment of project costs to Fulton Bank in accordance with the Bond Agreement. The requisitions and disbursements continued for eighteen months until the full $9,945,000 was paid.
On October 21, 2002, the Dobson Brothers submitted a certification verifying the Project was substantially completed. The GCIA further completed the Borrower's Completion Certification stating that the Project was completed as of September 14, 2002. By November 2002, the Riverwinds Golf Course was open for business; in a letter dated November 25, 2002, the Township acknowledged the developer's substantial completion.
In 2007, the Township released the Dobson Brothers as the developer from the Ground Lease. In 2008, the Township entered into an agreement with a second developer. In this agreement, the Township, once again, represented and warranted that it was bound by the original Guaranty Agreement and that "there are no defenses, set-offs, or counterclaims of any kind or nature whatsoever with respect to the Loan Documents and with respect to any party hereto arising from the Loan Documents[;]" the Township also acknowledged that Fulton Bank was, in fact, relying on its representations and warranties in this letter.
In October 2008, after the second developer failed to make the required principal and interest payments on the Bond, Fulton Bank exercised its right under the Guaranty and gave notice of its demand for payment of all sums due and owing. The Township then released the second developer and paid Fulton Bank the overdue principal and interest payment.
Subsequently, in 2009 and 2010, the Township took possession of the project and entered into a management agreement and long-term lease agreement with River Winds RJM, LLC to operate the Project. On May 10, 2011, Fulton Bank and the Township acknowledged the default of the borrowers and the Township agreed to pay the past due principal, which then totaled $1,005,000, to Fulton Bank.
Then, in 2012, a new Township administration took office and raised questions about prior disbursements relating to the Project. The new administration wrote to Fulton Bank seeking documentation of certain transactions in connection with the loan; however, before Fulton Bank had an opportunity to supply the documents, the Township filed the present lawsuit.
On November 26, 2012, Judge Anne McDonnell heard argument on cross-motions for summary judgment and ruled in favor of Fulton Bank, based on the clear and binding language of the Guaranty Agreement. Judge McDonnell noted the language expressly and unambiguously waived and released any possible claim or defense as a basis to reduce or set-off the Township's guaranty obligation to Fulton Bank. The court further determined that the Township was not absolved of its responsibilities set forth in the Guaranty Agreement simply because Fulton Bank assumed GCIA's position as the paying agent of the bond. The trial court found the documents clearly indicate the Township has the obligation to make the required payments and Fulton Bank had no duty to the Township beyond disbursing the funds.
On appeal, the Township claims Fulton Bank disbursed millions of dollars without requiring proper documentation, and that these alleged improper disbursements constituted a breach of its fiduciary duty. The Township posits Fulton Bank had a duty to the Township taxpayers because it was not only the bond holder, but was also the paying agent, and therefore had an obligation to ensure the disbursements complied with payment requirements. Specifically, the Township maintains that Fulton Bank had "the duty to ensure that the monies which were disbursed actually went into the project." The breach of this alleged duty, the Township argues, relieves it of the obligation to pay the remaining principal and interest on the bond to Fulton Bank.
In reviewing a grant of summary judgment, we apply the same familiar standard under
The question of whether a fiduciary duty exists is a matter of law.
Nevertheless, we have adopted the reasoning of the Third Circuit Court of Appeals that it "`would be anomalous to require a lender to act as a fiduciary for interests on the opposite side of the negotiating table,' because their respective positions are essentially adversarial."
Accordingly, a breach of fiduciary duty claim against a lender can only arise where there are special circumstances.
Finally, "[a]bsent a contractual duty, a bank has no obligation to manage, supervise, control or monitor the financial activity of its debtor[.]"
The question presented is whether Fulton Bank breached a fiduciary duty to the Township. Because the record does not support the Township's claim that a fiduciary relationship existed between it and Fulton Bank, we answer the question in the negative. After careful review, we find no special circumstances between Fulton Bank and the Township to give rise to a fiduciary duty. The record lacks any evidence the Township placed special trust in Fulton Bank. Nor does the Township claim it sought advice from the bank.
As a guarantor of the bond, the Township was a party to an arms-length transaction with Fulton Bank, with each party bound to the other by contractually agreed-upon provisions. The fact that the Guaranty Agreement was actually between the Township and the GCIA, with Fulton Bank later acquiring GCIA's rights as an assignee, further proves the absence of a special relationship. The purpose of the Guaranty Agreement was to make the bond marketable and induce the purchase of the bond, not to create a special relationship in the nature of a fiduciary duty. It is difficult to imagine a scenario where a bank would voluntarily enter into an arrangement that created a fiduciary duty to oversee and manage a borrower's business activities. The record provides no support this occurred here.
Additionally, the language in the Bond Agreement authorized Fulton Bank to make the required disbursements for the project directly to the developer, and in turn, directly receive the principal and interest on the bond when payments became due. Fulton Bank was not required to monitor the disbursements of the funds once they were made; as noted, imposing such a duty "would be impractical as a matter of public policy."
Furthermore, the record lacks evidence the Township placed its trust and confidence in Fulton Bank to supervise the developer; the bank was neither in a dominant nor a superior position with respect to the Township. The Township's developer provided Fulton Bank with the requisitions that listed the expenses and consistent with the Bond Agreement, Fulton Bank disbursed the money. However, once the developer deposited the money into its own bank account, Fulton Bank was not charged with the responsibility of overseeing the developer's management of the project. Moreover, the Township's Phase I Redevelopment Agreement and Management Agreement explicitly authorized and directed the Township to implement and manage project development.
Importantly, the relationship here is one between a guarantor and a guarantee, an adversarial relationship, rather than a "special relationship" the Township needed to overcome the presumption against a fiduciary relationship in the lender-borrower context. "Banks cannot be expected to be their borrowers' financial guarantors."
The Township next argues that it is not bound by the waiver and unconditional guaranty because it did not voluntarily waive its right to avoid paying the full principal and interest. Certainly a waiver is only valid if it was made voluntarily and "there must be a clear act showing the intent to waive the right."
Plaintiff correctly states that "waiver cannot be predicated on consent given under a mistake of fact."
The Bond Agreement clearly indicates each party's intent for the Township to bear the risk of a default or other failure by the developer, rather than the GCIA or the ultimate purchaser of the bond. Importantly, the Township's recourse for non-performance was against the Dobson Brothers, pursuant to an indemnity provision and a performance bond. In 2007, the Township waived its recourse against the Dobson Brothers and their performance bond, in order to move forward with a new agreement with another developer. Having made this decision, the Township has no basis to challenge its liability to Fulton Bank under the Bond Agreement.
The Township waived all claims and defenses it could raise to avoid paying the full principal and interest on the bond in the event of a default by its developer. Thus, we find that the extremely broad waiver and release language was intended to make it absolutely clear that the Township's obligation to pay the full principal and interest on the bond was absolute, unconditional and irrevocable and could not be avoided, limited, modified or reduced.
Finally, plaintiff contends that the 2007 and 2011 agreements were neither a release nor a waiver of any claim, but rather a reaffirmation of the guaranty. Alternatively, the Township asserts the releases were never approved by the governing board. However, the Township Committee passed a resolution in May 2007 specifically authorizing the Township Administrator to enter into all necessary agreements for the project to continue. Additionally, the Township's subsequent conduct in complying with all aspects of the 2007 and 2011 transactions and accepting all of the benefits constitutes ratification of those agreements. As such, this argument lacks sufficient merit to warrant further discussion in this opinion.
Affirmed.