PER CURIAM.
Defendant/third-party plaintiff Watchung Crest, LLC (Watchung Crest or defendant) appeals
Defendant advances several arguments on appeal:
After reviewing these arguments in light of the applicable legal principles and the record, we are satisfied that defendant's arguments lack sufficient merit to warrant discussion in a written opinion,
Our scope of review in this case is limited. The factual findings of a judge in a non-jury case "are considered binding on appeal when supported by adequate, substantial and credible evidence."
In his opinion, Judge Miller set forth a detailed history of the facts pertaining to this construction dispute, which need not be repeated here. We summarize only the salient facts that are relevant to the issues on appeal.
Watchung Crest owned a parcel of land that it sought to develop into a residential subdivision. In November 1999, Adamsville submitted a proposal to do site improvement work for Watchung Crest. After the initial proposal was rejected, plaintiff submitted a revised proposal to perform "Phase I" improvements for a lump sum contract price of $287,051. This work related to the creation of roadways, the installation of sewer lines and other utilities, storm drainage, excavation, grading, and soil erosion control. However, after Phase I was started, significant changes to the scope of work were required, which plaintiff's principal, Richard Scagliotta, attributed to inaccuracies in the plans, additional requirements imposed by the Borough, and modifications requested by Ehrenworth, Watchung Crest's manager.
The documentation regarding this contract, and indeed, the ongoing dealings between the parties, is poor. As Judge Miller noted, "[t]he record is clearly incomplete regarding all of the writings between the parties[,]" and "[p]laintiff's record keeping can be described as sloppy at best." Nevertheless, "by piecing together the oral agreements, written memorializations of estimates, confirmations and memorandums provided in [the exhibits,]" Judge Miller concluded that the parties agreed that all additional work was to be performed on a time and material (T&M) basis.
The work for Phase I was performed in 1999-2000. Plaintiff billed defendant $469,599 for the Phase I improvements, which included the original contract price of $287,051 plus $182,548 for the additional work provided on a T&M basis. Ehrenworth testified that he never questioned any of the Phase I work invoices and paid them promptly.
The "Phase II" work was performed several years later. In December 2003, defendant asked plaintiff to complete paving of the roadways at the project. The work was performed in January 2004 for the agreed upon price of $50,800. Aside from "punch list" items, it was agreed that this work was performed satisfactorily.
In May 2004, the parties agreed that defendant would perform additional work for the sum of $14,225, as memorialized in a "proposal/contract." However, once again, there were many changes and additions and, once again, deficiencies in the documentation made it difficult for the parties and the court to reconstruct the scope and performance of the work undertaken. Judge Miller observed that "the custom and practice of both parties with regard[] to the Phase II work was that it proceeded between the parties on a very informal, verbal basis." Plaintiff invoiced defendant for the Phase II work periodically. The charges totaled $296,894.68. Defendant paid the invoices promptly, without any significant complaints, for most of the Phase II work.
Plaintiff filed a complaint against Watchung Crest in January 2008, seeking $48,765 for unpaid services performed during the period from 2004 to 2007. On April 8, 2008, Grimes filed a lis pendens against the property then owned by Watchung Crest on behalf of plaintiff. As a result, a scheduled closing for the sale of the property was delayed and Watchung Crest had to deposit $100,000 into escrow until July 25, 2008, when the lis pendens was discharged.
Defendant filed an answer, counterclaim, and third-party complaint against Grimes, alleging, inter alia, intentional interference with contractual relations and slander of title. Watchung Crest asserted that it suffered damages in the amount of $6391.94 as a result of the allegedly improper filing of the lis pendens. As to plaintiff's claim against it, Watchung Crest alleged that the fair and reasonable price for the work done on Phases I and II was $381,655.15 and that, in light of its payment of $726,293.86, it had overpaid for the work by $344,638.71. Watchung Crest also contended that it was entitled to additional credits of $59,898.31.
Judge Miller determined that, for both the Phase I and Phase II portions of the project, enforceable contracts existed between the parties for plaintiff to perform work on a T&M basis. Citing established principles of contract law, Judge Miller found that the parties had demonstrated their intent to be bound by those terms through "a course of conduct ... that clearly corroborated that a contract existed between them."
Judge Miller observed that the documentary evidence regarding Phase II work was less extensive but reached the same conclusion:
Defendant contended that it was entitled to certain credits pertaining to the Phase II work. Judge Miller correctly noted that defendant carried the burden of proving by a preponderance of the evidence its entitlement to a credit and also quantifying the amount of the credit due. The judge concluded that defendant failed to satisfy this burden as to credits claimed for "machine down time," improper backfilling of the basement of the foundation, and the improper installation of a fire hydrant. However, Judge Miller found that defendant had satisfied its burden of proving the existence and amounts of other credits it claimed.
A significant issue that arose during Phase I concerned whether plaintiff had "over cleared" a sewer easement that ran over Watchung Crest's property. Although the easement was only twenty-feet wide, plaintiff cleared "a swath of land that was at some point at least 70 feet in width[.]" There were complaints from affected private residents as well as the Borough Engineer, who required defendant to post an additional $8400 in escrow to secure the restoration work that was required. Defendant submitted the invoice of Hesperides, a landscape company, showing that the cost of designing and installing the improvements required by the Borough was $19,962. Judge Miller found that the evidence "overwhelmingly" supported defendant's claim that the easement was overcleared and that the Hesperides estimate was the best evidence of the damages incurred by defendant. Accordingly, the judge awarded defendant a credit of $19,962.
Defendant also claimed a credit for defective or incomplete work set forth in deficiency reports from the Borough Engineer, dated October 31, 2005, August 24, October 22, and November 13, 2007. Because these issues were not raised until five years after the completion of Phase I improvements, plaintiff had invoiced and been paid for all the work with the exception of the $8400 escrow. Defendant presented a deficiency list to plaintiff and, by letter dated October 18, 2006, plaintiff admitted responsibility for a portion of the list and asked defendant to "get a quote on what is mine, so I can determine [what there is] for me to do, or to have you pay and take off the $48,765.02 owed plus the Watch Crest $8,400."
Defendant hired Sun Valley Landscape, Inc. to perform remediation of the deficiencies, at a cost of $26,224.31. The court acknowledged plaintiff's admission of responsibility for "most of the cure work," and found that defendant satisfied its burden to show what portion of the bill was plaintiff's responsibility. Clark Cheshire, the principal of Sun Valley, was unable to provide specific testimony on this point due to health problems. However, Judge Miller heard and accepted as credible the testimony of counsel for defendant regarding her conversation with Cheshire about this allocation. In response, Cheshire sent a letter and a stack of invoices for the work that highlighted the charges attributable to the repairs necessary to correct plaintiff's work. The highlighted portions of the bills amounted to $24,308.70, which the court credited to defendant.
Defendant also hired Oswald Enterprises to perform a mandrel test at the site, at a cost of $1712, which apparently was necessary before the Borough would accept the sewer line. Judge Miller rejected defendant's claim for a credit for this amount:
Accordingly, Judge Miller concluded that plaintiff was entitled to the outstanding balance of $45,985 and defendant was entitled to a credit of $44,270.70, resulting in a judgment in plaintiff's favor of $1714.30.
Judge Miller also dismissed defendant's claims against Grimes. The court correctly dismissed defendant's claim for slander of title, based upon the filing of the lis pendens, as barred by the litigation privilege.
In sum, Judge Miller navigated the competing claims of the parties under difficult circumstances. The claims dated back to 1999 and included contentions regarding work that had long been completed and paid for. There were deficiencies in the documentary evidence presented by both sides. Nonetheless, the trial court made findings of fact based upon the testimony, its credibility determinations, and the available documentary evidence. We are satisfied that those findings are amply supported by the record. Further, Judge Miller applied established principles of contract law to conclude that the parties had enforceable contracts regarding the work done by plaintiff and that defendant was entitled to certain credits. We discern no reason to disturb those conclusions. As to the dismissal of the claims against Grimes, Judge Miller again relied upon a determination of the facts and credibility of Grimes that was supported by the evidence, and reached conclusions that were supported by legal authority.
Affirmed.