Summary: DECISION AND ORDER JEREMIAH J. McCARTHY, Magistrate Judge. The parties have consented to proceed before a Magistrate Judge pursuant to 28 U.S.C. 636(c). 1 Before me is the motion of third-party defendant Kroff Chemical Company, Inc. ("Kroff") [141] 2 pursuant to Fed. R. Civ. P. ("Rule") 12(c) to dismiss the Second Amended Third-Party Complaint of defendant/third-party plaintiff, Superior Well Services, Inc. ("Superior") seeking contribution and indemnification. Oral argument was held on Sep
Summary: DECISION AND ORDER JEREMIAH J. McCARTHY, Magistrate Judge. The parties have consented to proceed before a Magistrate Judge pursuant to 28 U.S.C. 636(c). 1 Before me is the motion of third-party defendant Kroff Chemical Company, Inc. ("Kroff") [141] 2 pursuant to Fed. R. Civ. P. ("Rule") 12(c) to dismiss the Second Amended Third-Party Complaint of defendant/third-party plaintiff, Superior Well Services, Inc. ("Superior") seeking contribution and indemnification. Oral argument was held on Sept..
More
DECISION AND ORDER
JEREMIAH J. McCARTHY, Magistrate Judge.
The parties have consented to proceed before a Magistrate Judge pursuant to 28 U.S.C. §636(c).1 Before me is the motion of third-party defendant Kroff Chemical Company, Inc. ("Kroff") [141]2 pursuant to Fed. R. Civ. P. ("Rule") 12(c) to dismiss the Second Amended Third-Party Complaint of defendant/third-party plaintiff, Superior Well Services, Inc. ("Superior") seeking contribution and indemnification. Oral argument was held on September 25, 2014. For the following reasons, Kroff's motion is denied, without prejudice to renewal at a later date.
BACKGROUND
Familiarity with the facts and procedural history of this case is presumed.
ANALYSIS
"It is well established that district courts possess the inherent power and responsibility to manage their dockets so as to achieve the orderly and expeditious disposition of cases." In re World Trade Center Disaster Site Litigation, 722 F.3d 483, 487 (2d Cir. 2013). "This power includes the authority to decide the order in which to hear and decide pending issues." Marinechance Shipping, Ltd. v. Sebastian, 143 F.3d 216, 218 (5th Cir.), cert. denied, 525 U.S. 1055 (1998).
As I stated at oral argument, Kroff's argument that Superior's claims can be clearly resolved on the pleadings appears to be somewhat undercut by the timing of its motion, which was not made until approximately one year after the Third Amended Complaint [117] and Second Amended Third-Party Complaint [122] were filed and until almost the close of more than two-and-a-half years of discovery. Given that anomaly and the fact that discovery is now complete, I believe that proper resolution of the current issues would benefit from consideration of a full factual record. Counsel for plaintiff and Superior confirmed at oral argument that they each intend to move for summary judgment on their respective claims and/or defenses.
CONCLUSION
For these reasons, Kroff's motion [141] to dismiss the Second Amended Third-Party Complaint is denied, without prejudice to renewal either as a motion for summary judgment or as a Rule 12(b)(6) motion in conjunction with the other forthcoming dispositive motions.
SO ORDERED.