MATTHEW W. BRANN, District Judge.
Pending before this Court are eleven Motions for Emergency Hearings, eleven Motions for Partial Summary Judgment, and eleven Motions for Preliminary Injunction filed by Plaintiff UGI Sunbury, LLC, a wholly owned subsidiary of UGI Energy Services, LLC, a Pennsylvania limited liability company (hereinafter "UGI"). The Federal Energy Regulation Commission (hereinafter "FERC") has granted UGI a blanket certificate of public convenience and necessity (hereinafter the "FERC Certificate"), authorizing it to construct a 20-inch diameter pipeline over 34.4 miles spanning Snyder, Union, Northumberland, Montour, and Lycoming Counties. This Pipeline is designed to add 200,000 dekatherms per day of new pipeline capacity to industrial and residential users.
Easements over much of the 34.4 miles have previously been acquired by contract; condemnation actions pursuant to the Natural Gas Act, 15 U.S.C. § 717 and Federal Rule of Civil Procedure 71.1, however, have been filed against many of the landowners, interest holders, and all unknown owners of properties who have not yet agreed to contract terms.
In May 2016, motions for preliminary injunctions were filed in eleven of the cases in which condemnation actions were filed. A hearing on the motions was scheduled for June 3, 2016. Prior to the Preliminary Injunction hearing, however, the parties in five of the eleven cases reached agreements concerning these motions.
On July 14, 2016, UGI filed motions for preliminary injunction and motions for hearings in eighteen of the condemnation cases, six of which were familiar to the Court from its dealings with the parties in May and June 2016.
On July 20, 2016, a telephone conference was held by this Court. During the conference, counsel for the parties in the six cases that had already been addressed by the Court's June 14, 2016 Order agreed that the new motions filed in the cases were superfluous, as the relief sought by UGI had been granted in the prior Order. As such, this Court dismissed those motions as moot. Also during the telephone conference, the Court was informed that one of the "new" cases had settled.
Accordingly, this Memorandum and the Orders that follow will resolve the motions for emergency hearing, motions for partial summary judgment and motions for preliminary injunction in the now eleven remaining cases.
Because of the unique procedures associated with federal condemnation actions under the Natural Gas Act, UGI must first establish that it has a substantive right to condemn the property at issue. Once a substantive right has been found, a court "may exercise equitable power to grant the remedy of immediate possession through the issuance of a preliminary injunction" pursuant to Federal Rule of Civil Procedure 65, which governs the granting of preliminary injunctions.
Generally, a party seeking a preliminary injunction must establish four factors: (1) a reasonable probability of success on the merits of their argument; (2) irreparable harm to the movant in the absence of relief; (3) granting the preliminary injunction will not result in greater harm to the nonmoving party; and (4) the public interest favors granting the injunction.
UGI seeks an Order allowing immediate entry on the properties so that it may complete construction of its pipeline by February 1, 2017, a deadline fixed by an agreement reached with Hummel Station, LLC (hereinafter "Hummel"), (described as the "foundation shipper" with whom UGI contracted).
As a matter of correct procedure, this Court must first resolve the motions for partial summary judgment and find that UGI has a substantive right to condemn the properties at issue. This Court must then decide the preliminary injunction issue.
UGI's motion for partial summary judgment seeks a finding from the Court that UGI has a substantive right to condemn the property. It argues that it has secured the required FERC Certificate and that the only open issue is that of just compensation.
Summary judgment is appropriate where "the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law."
The burden of establishing the nonexistence of a "genuine issue" is on the party moving for summary judgment.
Where the moving party's motion is properly supported, the nonmoving party, to avoid summary judgment in his opponent's favor, must answer by setting forth "genuine factual issues that properly can be resolved only by a finder of fact because they may reasonably be resolved in favor of either party."
"When opposing summary judgment, the non-movant may not rest upon mere allegations, but rather must `identify those facts of record which would contradict the facts identified by the movant.'"
In deciding the merits of a party's motion for summary judgment, the Court's role is not to evaluate the evidence and decide the truth of the matter, but to determine whether there is a genuine issue for trial.
Section 717f(h) of the Natural Gas Act grants the right of eminent domain for construction of pipelines:
"[A] certificate of public convenience and necessity [therefore] gives its holder the ability to obtain automatically the necessary right of way through eminent domain, with the only open issue being the compensation the landowner defendant will receive in return for the easement."
It is undisputed that UGI has obtained a valid FERC Certificate. Defendants do not raise any further objections to a finding that UGI has the substantive right to condemn Defendants' property in light of this Court's June 14, 2016 Order.
During the Court's July 20, 2016 telephone conference, counsel for Defendants agreed that the motions for preliminary injunction in these eleven cases should be granted, as a result of the reasoning set forth in this Court's June 14, 2016 Order. That Order provided a detailed discussion justifying its granting of the motions and the relief requested by UGI. Accordingly, the Court declines to reiterate this analysis and instead applies the same reasoning in granting the instant motions for preliminary injunction.
The parties disagree on the issue of appropriate bond amount, however. Prior to the June 3, 2016 hearing, UGI and the Defendants in five cases
Defendants object to this formula in eight of the eleven remaining cases.
Defendants in six cases
Federal Rule of Civil Procedure 65(c) requires that the movant requesting a preliminary injunction give security in an amount the court considers proper to pay the costs and damages sustained by any party found to have been wrongfully enjoined. The United States Court of Appeals for the Third Circuit has held that "[a]lthough the amount of the bond is left to the discretion of the court, the posting requirement is much less discretionary. While there are exceptions, the instances in which a bond may not be required are so rare that the requirement is almost mandatory."
Other eminent domain cases provide further guidance in determining an appropriate bond amount. In Northern Border Pipeline Co. v. 127.79 Acres of Land, More or Less in Williams County, N.D.,
In the cases sub judice, the amount of just compensation is greatly disputed by the parties. Defendants provide proposed just compensation values in their briefs on the issue of bond amounts. UGI indicates that the $5,000 per acre figure "is the damage component of the total calculated compensation set forth in UGI's most recent offers to all landowners." This Court cannot assume that the amount proposed by UGI in an offer to settle is the actual value of just compensation calculated by UGI, especially considering that different parcels of land are undoubtedly worth more than others. As this Court has stated repeatedly, the issue of just compensation is a matter for another day, after appraisals have been conducted by all parties and the evidence is presented to the Court.
As such, this Court will adopt the bond amounts proposed by Defendants. Posting a bond in the higher amounts proposed poses less risk to all parties involved. As described above, to be prudent, courts must err on the "high side" so as to not limit a wrongfully enjoined party's recovery amount. The risk that Defendants were wrongfully enjoined is likely low considering that UGI has valid FERC certificates granting it eminent domain powers. Furthermore, UGI will only be required to pay the amount of just compensation if, at the time of the condemnation hearing, the Court determines that just compensation is less than the amounts posted in the bonds.
For the foregoing reasons, the Court will deny UGI's motions for hearings and grant UGI's motions for partial summary judgment. The Court will further grant UGI's motions for preliminary injunctive relief and Order a bond to be posted in each case in the amounts proposed by Defendants.
An appropriate Order follows this Memorandum.