MATTHEW W. BRANN, District Judge.
On March 28, 2017, Plaintiff, Transcontinental Gas Pipe Line Company, LLC, hereinafter "Transco," filed a complaint in condemnation pursuant to Federal Rule of Civil Procedure 71.1 and the Natural Gas Act, 15 U.S.C. § 717. Previously, on February 3, 2017, the Federal Energy Regulatory Commission, hereinafter "FERC," granted Transco a certificate of public convenience and necessity. Transco filed suit after proving unable to negotiate the amount of compensation to be paid for the right-of-way with the Defendants in order to construct, operate and maintain a pipeline for the Atlantic Sunrise Project; construct new and make modifications to existing compressor stations; construct new and make modifications to existing meter stations; make modifications to existing regulator stations; and make modifications to existing mainline valve locations in South Carolina, North Carolina, Virginia, Maryland, and, as largely relevant here, 199.5 miles through Pennsylvania.
On April 12, 2017, Transco filed a motion for partial summary judgment and, subsequently on June 29, 2017, a motion for preliminary injunction.
Summary judgment is appropriate where "the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law."
The burden of establishing the nonexistence of a "genuine issue" is on the party moving for summary judgment.
Where the moving party's motion is properly supported, the nonmoving party, to avoid summary judgment in his opponent's favor, must answer by setting forth "genuine factual issues that properly can be resolved only by a finder of fact because they may reasonably be resolved in favor of either party."
"When opposing summary judgment, the non-movant may not rest upon mere allegations, but rather must `identify those facts of record which would contradict the facts identified by the movant.'"
In deciding the merits of a party's motion for summary judgment, the court's role is not to evaluate the evidence and decide the truth of the matter, but to determine whether there is a genuine issue for trial.
With that standard of review in mind, Section 717f(h) of the Natural Gas Act grants the right of eminent domain for construction of pipelines, as follows:
"To condemn the easements at issue, [the gas company] must demonstrate (1) it holds a FERC certificate of public convenience and necessity; (2) the rights-of-way to be condemned are necessary for the construction, operation, and maintenance of the pipeline; and (3) it has been unable to acquire the proposed rights-of-way from the landowner."
Defendants' argue generally that "Plaintiff's motion for partial summary judgment is premature because Defendants and similarly situated landowners have been denied the opportunity to challenge the FERC Order and its findings."
Defendants also argue that Transco did not negotiate in good faith. Defendants' argument as to "good faith" negotiations fails, as well. Although "some courts have imposed a requirement that the condemnor engage in good faith negotiations"
In their brief, Defendants further argue that they were denied the opportunity to be heard by FERC. But they offer no substantive evidence to support this unfounded allegation.
FERC provided the landowners with multiple opportunities to be heard. The relevant dates are as follows. On March 31, 2015, Transco filed a project application. On October 22, 2015, FERC sent a letter to affected landowners. On May 5, 2016, FERC issued an Environmental Impact Statement. The public comment period ran for 45 days, from May 12, 2016 to June 27, 2016. Between June 13 and 16, 2016, FERC held four public comment meetings. On October 13, 2016, FERC sent landowners letters regarding two alternative pipeline routes. The public comment period ran for 30 days. On November 3, 2016, FERC issued a comment for a draft General Conformity Determination. On December 30, 2016, FERC issued a final Environmental Impact Statement. Finally, on February 3, 2017 FERC authorized the Atlantic Sunrise Project and granted Transco a certificate of public convenience and necessity.
The FERC certificate of public convenience and necessity lists timely and untimely intervenors.
Defendants also argue that the project is not for "public use" and disagree with the proposed route. Any challenge as to "public use" and/or the route this pipeline will take, could have, and more importantly, should have been taken up with FERC in the first instance.
The Defendants also request a stay of the FERC Order. However, "A party is not ordinarily granted a stay of an administrative order without an appropriate showing of irreparable injury."
Finally, Defendant Susquehanna Coal Company argues that Transco set forth a "restriction against surface mining operations which use blasting within fifteen-hundred (1500) feet of the pipeline, effectively widening the area of the permanent taking by sixty times and preventing the Defendant from engaging in the development of its property and its mineral resources."
FERC has, on multiple occasions, expressly conditioned certificates of public convenience and necessity based on concerns raised by coal companies. For example, in an action involving a pipeline constructed between Missouri and Ohio, the United States Court of Appeals for the Sixth Circuit wrote: "FERC issued the certificate subject to several conditions, one of which required the pipeline company to `collaborate with the coal companies to develop a construction and operations plan' addressing `pipeline integrity and operation' for the portion of the pipeline that runs over the mine."
In another case, the Western District of Virginia explained that a certificate of public convenience and necessity was conditioned on environmental conditions which included a condition that that plaintiff gas company `work with' several coal companies to avoid disruption of mining operations: "Anker Mining ... is planning to commence construction of a coal mining operation that would be located between approximate MPs 0.5 and 3.8."
Here, I find that there is no genuine issue of material fact as to the three conditions precedent. First, FERC has issued a certificate of public convenience and necessity to Transco, a natural gas company as defined by the Natural Gas Act 15 U.S.C. § 717a(6). Second, the rights-of-way to be condemned are necessary for the construction, operation, and maintenance of the pipeline. "By issuing the Certificate [of public necessity] to [Plaintiff], FERC has determined that the Subject Property is necessary to the operation of the Pipeline[; t]his determination cannot be challenged by Defendants."
Because of the unique procedures associated with federal condemnation actions arising under the Natural Gas Act, Plaintiff must first establish that it has a substantive right to condemn the property at issue. Once a substantive right has been found, a court "may exercise equitable power to grant the remedy of immediate possession through the issuance of a preliminary injunction" pursuant to Federal Rule of Civil Procedure 65, which governs the granting of preliminary injunctions.
"It is well established that `a preliminary injunction is customarily granted on the basis of procedures that are less formal and evidence that is less complete than in a trial or on the merits.'"
Generally, a party seeking a preliminary injunction must establish four factors: (1) a reasonable probability of success on the merits of their argument; (2) irreparable harm to the movant in the absence of relief; (3) granting the preliminary injunction will not result in greater harm to the nonmoving party; and (4) the public interest favors granting the injunction.
First, Transco has succeeded on the merits. Unlike preliminary injunctions in other types of civil actions, those sought in condemnation cases also request an entry of judgment on the merits contemporaneously with the motion for preliminary injunction. Defendants argue in their brief that because "the certificate [of public use and necessity] is currently being challenged by a number of landowners and environmental groups"
Second, Transco will suffer irreparable harm in the absence of preliminary relief. In their brief opposing the motion, Defendants argue that the only harm in not granting the motion is monetary harm. This is not the case. In fact, Transco set forth several examples of irreparable harm both in its papers and at the hearing. The first is monetary. Transco contends non-possession will cost it $500,000 per month, and will delay revenues of thirty-three million dollars ($33,000,000) per month because Transco needs possession in order to begin construction. Defendants argue in their brief that these values are speculative. Defendants are correct in one respect, as "purely speculative harm will not suffice, but rather, a plaintiff who can show a significant risk of irreparable harm has demonstrated that the harm is not speculative and will be held to have satisfied his burden."
The next type of irreparable harm set forth by Transco is that it will breach contracts with both subcontractors and vendors if it cannot possess the subject properties in a timely fashion. The contract with shippers wass designed so that the pipeline is in service by the 2017-2018 winter heating season. Mr. Sztroin testified that the contracts with shippers were a prerequisite to filing with FERC, and Transco would break contracts with the shippers if it was not permitted to enter the property by August 18, 2017. I note that this argument also cuts against Plaintiff, as Transco has acknowledged that delays in obtaining the FERC certificate have already caused it to miss that deadline; the current anticipated completion date for the project is now July 2018.
Transco also argues that it will experience other substantial delays in completion of the project if it is not granted access. It asserts that non-possession could set the construction project back an entire year because it must conduct surveys on endangered and threatened wildlife species that are only permitted during certain dates each year. Additionally, certain work must be completed in Pennsylvania prior to the annual October deadline for work on wild trout streams. Specifically, Transco must install in-stream supports for equipment bridges prior to October 1, 2017.
In sum, the Atlantic Sunrise Project is large in both scope and geography, spanning five states. "The magnitude of the Project requires a complex and coordinated construction process, with work activities being performed in sequential phases"
Third, granting the preliminary injunction will not result in greater harm to the landowner, despite Defendants arguments to the contrary in their brief. Transco has the substantive right to possession. Defendants argue that if the preliminary injunction is granted, they lose the right to the "use and enjoyment of their property" and granting the motion will "change the status quo."
"The Fifth Amendment guarantees the landowners just compensation for their land no matter when the condemnor takes possession."
It is commonplace for district courts to order immediate possession after FERC has taken a lengthy period of time determining whether or not to issue a certificate of public convenience and necessity. "District courts in a number of jurisdictions grant immediate possession in the form of a preliminary injunction to a gas company that has established its right to condemn under the [Natural Gas Act]."
Moreover, "the court does not have jurisdiction to review a collateral attack on the FERC certificate."
For these reasons, this factor favors Transco.
Fourth, granting the preliminary injunction is in the public interest as it will give the general public access to natural gas from the Marcellus Shale deposits for heating their homes. This pipeline will transport 1.7 million decotherms of natural gas to the north east and mid atlantic markets. "Congress passed the Natural Gas Act and gave gas companies condemnation power to insure that consumers would have access to an adequate supply of natural gas at reasonable prices."
For all of these reasons, Transco's motion for preliminary injunction is granted.
"Rule 65(c) gives the district court wide discretion to set the amount of a bond."
Joseph Prociak, President and CEO of Defendant Susquehanna Coal Company, testified at the August 3, 2017 hearing that he values the loss to the property to be one-hundred million dollars ($100,000,000.00). Accordingly, he requests a bond for that amount. However, that value represents his valuation of the
A bond in the amount of one-hundred million dollars is unreasonable. Transco is only seeking to condemn a 5.67 acre permanent easement on this property. To put the matter in perspective, the permanent easement is a taking of only 0.01% of the total acreage of the property. Moreover, Prociak's value is based on a developed property with an operating coal mine. However, he testified that Susquehanna Coal Company has never mined the property, and may never mine the property. Furthermore, Prociak testified that and he has consistently refused third parties offers to mine the property. Although Defendant has a mining permit, it is currently not bonded, and thus the property cannot presently be mined.
Accordingly, Defendants' demand for a bond of one-hundred million dollars is unsubstantiated; Transco's proposed bond amount trebling the appraisal value is comparatively reasonable. Transco has appraised the easement at $34,180 and proposed a bond of three times that amount for $102,540. I will accept Transco's proposed bond amount trebling the appraisal value.
Finally, Defendants made an oral motion during the August 3, 2017 hearing demanding that compensation be paid prior to entry on the land. This oral motion is denied. The Constitution "does not provide or require that compensation be paid in advance of the occupancy of the land to be taken."
Transco indicates that third parties have expressed their intention to engage in civil disobedience. I have the authority and "inherent power to enforce compliance with lawful orders through civil contempt."
An Order will issue this date granting Plaintiff's Motions for Partial Summary Judgment and for Preliminary Injunction. Plaintiff will be ordered to post a surety bond with the Clerk of Court.
Commencing August 18, 2017, pursuant to the Order of the Federal Regulatory Commission dated February 3, 2017, Plaintiff Transcontinental Gas Pipe Line Company, LLC is granted access to, possession of and entry to the rights of way allowed under that Order for the above captioned property. The Order will include an enforcement mechanism to deter those who seek to obstruct Plaintiff.