JOHN G. KOELTL, District Judge.
This action arises from a failed real estate transaction. The plaintiff, Sigurd Sorenson, is an attorney proceeding
The standard for granting summary judgment is well established. "The [C]ourt shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law." Fed. R. Civ. P. 56(a);
The moving party bears the initial burden of "informing the district court of the basis for its motion" and identifying the matter that "it believes demonstrate[s] the absence of a genuine issue of material fact."
In determining whether summary judgment is appropriate, a court must resolve all ambiguities and draw all reasonable inferences against the moving party.
The following facts are undisputed unless otherwise indicated. Defendant Stanley Wolfson is a real estate developer and the owner of Bridge Capital Corporation ("Bridge"), the original sponsor of a residential condominium development at 257 West 117th Street in New York City. In or about January 2005, Sorenson executed three purchase agreements (the "Purchase Agreements") with Bridge to purchase three units in the condominium development for approximately $3.9 million.
The Purchase Agreements included various termination clauses. Section 37(c) to each agreement, (the "Overages Provision"), provided that either party could terminate the agreement, without penalty, if the parties could not reach an agreement with respect to apportioning liability for overages incurred as a result of construction of the relevant units. Section 49(i) to two of the Purchase Agreements, (the "Amendment Acceptance Provision"), provided that either party could terminate the agreement if the New York State Attorney General rejected a proposed amendment to the plan that offered units in the development to the public for sale (the "Plan Amendment").
Pursuant to the Amendment Acceptance Provision, Bridge submitted the Plan Amendment to the New York State Attorney General's Office (the "NYAGO") on February 11, 2005. (Sorenson Decl., Ex. 22 at 1.) In a memorandum dated March 14, 2005, the NYAGO requested that Bridge submit additional information about the Plan Amendment and make certain corrections to the Plan Amendment. (Sorenson Decl., Ex. 41.) Bridge did not respond to the NYAGO's requests. (Pl.'s Rule 56.1 Stmt. at ¶ 23; Def.'s Resp. to Pl.'s Rule 56.1 Stmt. at ¶ 23.) Instead, in a letter faxed on March 15, 2005, Bridge informed Sorenson that the NYAGO had rejected the Plan Amendment. (Sorenson Decl., Ex. 24 at 4.) Bridge invoked the Amendment Acceptance Provision shortly thereafter.
As required by the Purchase Agreements, Sorenson provided Bridge with custom architectural plans for purposes of constructing his units. (Sorenson Decl., Ex. 30 at 86-87.) On March 8, 2005, Bridge informed Sorenson that it had reviewed the plans, and proposed that Sorenson contribute an additional $729,900 for overages expected to result from construction of his units. (Sorenson Decl., Ex. 26 at 2.) On March 15, 2005, Sorenson replied to Bridge's proposal by purportedly offering to withdraw his custom plans and have his units built to the standard specifications contained in Bridge's offering plan. (Sorenson Decl., Ex. 27.) Bridge did not respond to Sorenson's alleged offer and instead terminated the Purchase Agreements pursuant to the Overages Provision. (Sorenson Decl., Ex. 25 at 2-3.)
The parties dispute when Bridge invoked the termination provisions. Sorenson maintains that Bridge invoked the termination provisions in correspondence that, while dated March 18, 2005, was not sent until March 21, 2005. (Sorenson Decl., Ex. 25 at 1-2.) Wolfson maintains that, in addition to sending a termination letter by fax on March 21, 2005, Bridge sent a termination letter by certified mail on March 18, 2005. (Sorenson Decl., Ex. 25 at 2.)
In April 2005, Sorenson brought suit against Bridge and Wolfson in New York State Supreme Court, New York County, asserting claims for breach of contract, specific performance, and other causes of action arising from the termination of the Purchase Agreements. In June 2005, Bridge sold the condominium development to a company called 257/117 Realty ("257 Realty"). Sorenson, believing that Wolfson had conveyed the development in order to evade a judgment against him, brought a second state court action in which he alleged fraudulent conveyance of the development against Bridge, Wolfson, and 257 Realty.
By Order dated January 3, 2008, Justice Charles Ramos dismissed the plaintiff's complaint in his initial state court action (the "contract action"). By Order dated March 24, 2008, Justice Ramos dismissed the plaintiff's complaint in his fraudulent conveyance action. Sorenson appealed both orders. (Sorenson Decl., Exs. 6-7.) While Sorenson's appeals were pending, Bridge moved pursuant to a fee-shifting provision in the Purchase Agreements to recover the attorneys' fees and costs that it incurred defending the contract and fraudulent conveyance suits. (Sorenson Decl., Ex. 11 at 56-58.) On February 20, 2008, Justice Ramos granted Bridge's motion, and ordered that the parties submit proposed orders instructing the referee how to proceed with respect to calculating the relevant fees and costs. (Sorenson Decl., Ex. 11 at 59-60.)
On June 10, 2008, the Appellate Division affirmed the dismissal of Sorenson's complaint in the contract action, except with respect to Sorenson's claims for breach of the covenant of good faith and fair dealing, and for specific performance.
The parties also litigated a third suit in New York State court in which Bridge alleged libel against Sorenson and Sorenson counterclaimed against Bridge and third-party 257 Realty, alleging that the libel suit was a retaliatory strategic lawsuit against public participation prohibited under the New York Civil Rights Law.
Following the Appellate Division's decisions with respect to the contract and fraudulent conveyance actions, Sorenson initiated this action. On February 14, 2012, this Court dismissed or found withdrawn Sorenson's RICO claims, fraudulent conveyance claim, unfair competition claim, criminal copyright claim, and, to the extent predicated on activity that occurred on or before June 10, 2007, Sorenson's civil copyright claim. Sorenson then settled his remaining claims against all defendants except Wolfson. (
In settling the claims against it, Defendant 257 Realty stipulated that it be permitted to press its counterclaim for the attorneys' fees and costs that it and Bridge incurred in defending Sorenson's state and federal court actions. (
Sorenson moves for summary judgment dismissing 257 Realty's counterclaim for attorneys' fees and costs against him. Sorenson first argues that any claim for fees and costs incurred in defending the state court actions must be dismissed because 257 Realty cannot in a subsequent federal suit seek relief for which it could have counterclaimed in the prior state court actions. 257 Realty replies that it should recover in this case the attorneys' fees and costs it incurred in defending the state court actions because the relief it seeks is no broader than that already sought in state court, and because it has not yet recovered any fees or costs as a result of any state court judgment.
Under New York law, "[a]n attorney's fee must be sought in the action in which it is incurred, and not in a subsequent action."
In this case, 257 Realty seeks attorneys' fees and costs pursuant to a fee-shifting provision providing that "[i]f either party brings an action against the other arising from this Agreement, the non-prevailing party shall pay the reasonable attorneys' fees and costs of the prevailing party in such action." (
Moreover, 257 Realty has already moved in the contract and fraudulent conveyance actions to recover its reasonable attorneys' fees and costs. That motion was granted by Justice Ramos on February 20, 2008. (
257 Realty's counterclaim for attorneys' fees and costs incurred in defending the contract action also fails because the contract action remains pending. The fee-shifting provision at issue in this case provides that the "prevailing party" is entitled to reasonable attorneys' fees and costs. (
In the contract action, Sorenson brought several claims arising out of the termination of the Purchase Agreements, and sought either specific performance of his rights under the Agreements, or, alternatively, damages for breach of the Agreements. Although the trial court dismissed Sorenson's Complaint in its entirety, the Appellate Division reinstated Sorenson's claims for breach of the covenant of good faith and fair dealing, and for specific performance.
In its papers, 257 Realty argues that it should recover its attorneys' fees and costs in defending the contract action, despite the Appellate Division's decision, because Sorenson has not pursued the reinstated claims on remand. More specifically, 257 Realty argues that it is the prevailing party in the contract action because that action should be dismissed for failure to prosecute or under the doctrine of laches. However, it plainly is not for this Court to dismiss the contract action. Any dismissal of the contract action on the basis of failure to prosecute or laches must be sought in the state court.
257 Realty recognized at oral argument on these motions that it should properly have sought dismissal from the state court, and represented that the defendants in the contract action have now demanded pursuant to New York Civil Practice Law and Rules § 3216 that Sorenson file a note of issue in that action, or have it dismissed. 257 Realty also acknowledged in the course of oral argument that it could not be considered a prevailing party in the contract action at this time.
Because the contract action remains pending, the Court cannot determine that Bridge prevailed on the central relief that Sorenson sought in the contract action. Accordingly, 257 Realty cannot recover attorneys' fees incurred defending the contract action.
Sorenson also argues, correctly, that 257 Realty is not entitled to collect attorneys' fees and costs for prevailing in this federal action because 257 Realty settled this action in Sorenson's favor. 257 Realty acknowledges that it paid a settlement in exchange for the dismissal without prejudice of all claims brought against it in this case. 257 also acknowledges that, as a result of its settlement, it is not the prevailing party in this action and cannot collect attorneys' fees and costs incurred in connection with this action. (
Sorenson also seeks summary judgment dismissing two of Wolfson's potential defenses to the remaining fraudulent termination claim, namely, that Wolfson did not fraudulently terminate the Purchase Agreements because termination was permissible under the Amendment Acceptance Provision and the Overages Provision.
Sorenson argues that Wolfson was not entitled to terminate the Purchase Agreements under the Amendment Acceptance Provision for two reasons: first, because Wolfson invoked the provision only after the deadline for doing so had passed, and, second, because the NYAGO never rejected the Plan Amendment. Sorenson also argues, and Wolfson concedes, that Wolfson was not entitled to terminate the Purchase Agreement for one of Sorenson's three units, unit 6B, pursuant to the Amendment Acceptance Provision because the relevant Purchase Agreement did not contain an Amendment Acceptance Provision.
The Amendment Acceptance Provision provides in relevant part that the "Purchaser and Sponsor shall have the right, without penalty, to cancel, rescind, and or/terminate [the] Agreement within 5 days after Sponsor notifies Purchaser that the Attorney General has not accepted the Plan Amendment." (
Sorenson also argues that Wolfson invoked the Amendment Acceptance Provision in error because the Provision became operative only when the NYAGO rejected the Plan Amendment, and the NYAGO did not reject the Amendment until January 3, 2006. Wolfson contends that termination was proper because the Amendment Acceptance Provision became operative when the NYAGO issued its March 14, 2005 letter, which requested that Bridge submit additional information about the Plan Amendment, and make several corrections to the Plan Amendment.
The Amendment Acceptance Provision provides both parties with a right of termination in the event that "the Attorney General does not accept the Plan Amendment." (
The parties' dispute is a question of contract interpretation that must be resolved pursuant to New York law because the Purchase Agreements contain a New York choice of law clause. (
In this case, both parties offer reasonable interpretations of the Amendment Acceptance Provision. Wolfson's argument that the phrase "does not accept the Plan Amendment" refers not only to outright rejection of the Plan Amendment, as Sorenson maintains, but also to other indications that the Plan Amendment had not been or would not be accepted without changes, does not strain the meaning of Amendment Acceptance Provision beyond its reasonable and ordinary meaning. Therefore, the Court cannot conclude that the phrase "does not accept the Plan Amendment" definitely and precisely requires that the NYAGO finally reject the Plan Amendment in order to trigger the Amendment Acceptance Provision. Accordingly, the phrase is ambiguous, and the Court must look to extrinsic evidence of the parties' intent.
Sorenson offers two documents as extrinsic evidence for this purpose: an affidavit from former New York State Assistant Attorney General Oliver Rosengart and a letter from the NYAGO dated January 3, 2006, both of which purportedly show that the NYAGO's March 14, 2005 request for additional information and for revisions did not constitute a final rejection of the Plan Amendment. (Sorenson Decl., Ex. 28 at 1; Sorenson Decl., Ex. 29 ¶¶ 1, 4.) These documents do not resolve the ambiguity underlying the parties' dispute because they do not clarify whether the parties intended the phrase "does not accept the Plan Amendment" to require final rejection of the Plan Amendment, or, rather, to cover other indications that the NYAGO had not accepted or would not accept the Plan Amendment. Accordingly, the phrase "does not accept the Plan Amendment" is susceptible to different, reasonable interpretations, and the Court cannot conclude that Wolfson impermissibly invoked the Amendment Acceptance Provision at this stage in the proceedings.
Sorenson also argues that Wolfson was not entitled to terminate the Purchase Agreements under the Overages Provision for two reasons. First, Sorenson argues that Wolfson invoked the Overages Provision only after Sorenson ostensibly waived the Provision. Second, Sorenson argues that Wolfson invoked the Provision prematurely. Issues of fact preclude summary judgment with respect to both arguments.
"Contractual rights may be waived if they are knowingly, voluntarily, and intentionally abandoned."
In this case, Sorenson contends that Wolfson was not entitled to terminate the Purchase Agreements under the Overages Provision because the provision was applicable only if Sorenson had his units built to custom specifications, and Sorenson waived his contractual right to have his units built to custom specifications. According to Sorenson, he effected this waiver in an email dated March 17, 2005, which purportedly offered to withdraw the custom specifications for each of the units, and thus mooted the need to apportion liability for overages. (
Sorenson also argues that Wolfson did not lawfully terminate the Purchase Agreements pursuant to the Overages Provision because he invoked the Provision prematurely. The Overages Provision provides in relevant part:
(Sorenson Decl., Ex. 2 ¶ 37(c).) The parties dispute whether the plans that Sorenson provided to Wolfson were Purchaser's Specifications that triggered this provision.
The Overages Provision defines "Purchaser's Specifications" as "approved architectural plans and building specifications" prepared by Sorenson's architect. (Sorenson Decl., Ex. 2 ¶ 37(a).) Although Sorenson now urges the Court to find that the phrase "approved architectural plans and building specifications" refers only to plans approved by the New York Department of Buildings, there is a reasonable basis for disagreement about whether the parties intended to refer to approval by the Department of Buildings or by other entities. Moreover, Sorenson has not identified any extrinsic evidence of the parties' intent with respect to the phrase at issue. Accordingly, the phrase "approved architectural plans and building specifications" is ambiguous, and the Court cannot conclude on this motion that Wolfson prematurely invoked the Overages Provision.
Sorenson also moves to amend his Second Amended Complaint to add claims for fraudulent conveyance, breach of contract, and alter ego liability, and to add Bridge and USWA Realty, LLC as defendants. More specifically, Sorenson seeks to add fraudulent conveyance claims against Bridge, Wolfson, and USWA Realty; breach of contract claims against Bridge and Wolfson; and an alter ego claim against Bridge, as an alter ego of Wolfson.
Federal Rule of Civil Procedure 15(a)(2) provides that "[t]he court should freely give leave [to amend] when justice so requires." Undue delay, undue prejudice to the opposing party, and the futility of the amendment are among the reasons to deny leave.
Sorenson argues that his delay in seeking leave to amend is explicable because the facts underlying his application were not elicited until the end of discovery. However, Sorenson fails to identify any facts that bear on his proposed contract claims that were learned during discovery in the federal action. Sorenson identifies some facts discovered late in discovery that bear on his proposed fraudulent conveyance and alter ego claims, namely, facts pertaining to a series of payments and transfers directed by Wolfson and made by either 257 Realty or Bridge in September, 2010. However, Sorenson discovered the relevant facts no later than May 2, 2013, (
Unexplained undue delay is typically insufficient to deny a motion to amend without some showing that amendment would prejudice the non-movant or is sought in bad faith.
Sorenson seeks leave to amend almost a year after the close of discovery, more than six months after the defendant sought summary judgment, and only after the defendant's summary judgment motion had been resolved. In such circumstances, the Second Circuit Court of Appeals has regularly found that a nonmovant is prejudiced by amendment.
It is also apparent that Sorenson's motion to amend is dilatory. Sorenson previously sought leave to file a Third Amended Complaint on August 2, 2013, only after Wolfson had expended the time and expense necessary to prepare a summary judgment motion predicated on the Second Amended Complaint. Sorenson amended his initial motion to amend nearly one month after filing, without leave from the Court and shortly before Wolfson's response to that motion was due. Sorenson later withdrew the initial motion to amend, but only after Wolfson had submitted his response. When Sorenson renewed his motion to amend on March 14, 2013, several of Wolfson's arguments with respect to the motion were moot, forcing Wolfson to decide whether to expend additional resources to revise his response.
Moreover, Sorenson delayed consideration of Wolfson's summary judgment motion for several months by failing to comply with three separate Court Orders that he submit courtesy copies of his fully-briefed motion. Because Sorenson's motion to amend is dilatory, made after significant undue delay, and would prejudice Wolfson, the motion for leave to amend is
Wolfson requests in passing that he be awarded the attorney's fees and costs expended defending the motion to amend. However, Wolfson has not explained the basis for why he is entitled to an award of fees and costs and his request is therefore
The Court has considered all of the arguments of the parties. To the extent not specifically addressed above, they are either moot or without merit. For the foregoing reasons, Sorenson's motion for summary judgment dismissing 257 Realty's counterclaim for attorneys' fees and costs is